MAG Silver Reports Second Quarter Juanicipio Underground Mine Production

MAG Silver Corp. (TSX NYSE American: MAG) ("MAG" or "MAG Silver") is pleased to report 2021 second quarter production of underground development material from the Juanicipio Project (56% 44% joint venture between Fresnillo plc ("Fresnillo") and MAG Silver). As reported to MAG by the project operator Fresnillo, 44,435 tonnes of development material were processed during the quarter ended June 30, 2021. Total Juanicipio production for the quarter based on provisional estimates before offtake agreement adjustments, totaled 434,885 silver ounces and 787 gold ounces (MAG's attributable 44% interest: 191,349 ounces of silver and 346 ounces of gold). The associated lead and zinc production will be reported with MAG's second quarter filings.

Mineralized development material from the Juanicipio Project is being processed through the nearby Fresnillo beneficiation plant (100% owned by Fresnillo) with the lead (silver rich) and zinc concentrates treated at market terms under off-take agreements with Met-Mex Peñoles, S.A. de C.V. in Torreón, Mexico. The revenue from this production, net of processing and treatment charges, is being used by the joint venture to offset initial project capital cash requirements.

"We are very pleased with the progress of the Juanicipio plant as we now enter the last stages of construction and would like to draw your attention to the regularly updated construction photos at www.magsilver.com where the impressive work done by Fresnillo can be viewed," said George Paspalas, MAG Silver's President and CEO. "The metallurgical results from the ongoing processing of mineralized development materials through the Fresnillo plant continue to de-risk the commissioning and ramp-up stage of the Juanicipio plant later this year, as well as providing a nice side-stream cash injection."

Construction of the Juanicipio processing plant continues to make good progress, with the mechanical installation of the flotation cells and filters completed in the quarter ended June 30, 2021. According to the operator, Fresnillo, the plant remains on schedule to commence commissioning in Q4 2021. Mineralized development material will continue to be batch processed on commercial terms at a targeted rate of 16,000 tonnes per month at the Fresnillo plant until the Juanicipio plant is commissioned.

Qualified Person: Dr. Peter Megaw, Ph.D., C.P.G., has acted as the Qualified Person as defined in National Instrument 43-101 for this disclosure and supervised the preparation of the technical information in this release. Dr. Megaw has a Ph.D. in geology and more than 38 years of relevant experience focused on ore deposit exploration worldwide. He is a Certified Professional Geologist (CPG 10227) by the American Institute of Professional Geologists and an Arizona Registered Geologist (ARG 21613). Dr. Megaw is not independent as he is Chief Exploration Officer and a Shareholder of MAG.

About MAG Silver Corp. ( www.magsilver.com )

MAG Silver Corp. (MAG: TSX / NYSE A) is a Canadian development and exploration company focused on becoming a top-tier primary silver mining company by exploring and advancing high-grade, district scale, silver-dominant projects in the Americas. Its principal focus and asset is the Juanicipio Project (44%), being developed in a Joint Venture partnership with Fresnillo Plc (56%), the Operator. Juanicipio is located in the Fresnillo Silver Trend in Mexico, the world's premier silver mining camp, and the Joint Venture is currently developing an underground mine and constructing a 4,000 tonnes per day processing plant which is expected to commence commissioning in Q4 2021. Underground mine production of development material commenced in Q3 2020, and an expanded exploration program is in place targeting multiple highly prospective targets both at Juanicipio by the Joint Venture and by MAG at the Deer Trail 100% earn-in project in Utah.

Neither the Toronto Stock Exchange nor the NYSE American has reviewed or accepted responsibility for the accuracy or adequacy of this press release, which has been prepared by management.

This release includes certain statements that may be deemed to be "forward-looking statements" within the meaning of the US Private Securities Litigation Reform Act of 1995. All statements in this release, other than statements of historical facts are forward looking statements, including statements that address future mineral production, reserve potential, exploration drilling, exploitation activities and events or developments. Forward-looking statements are often, but not always, identified by the use of words such as "seek", "anticipate", "plan", "continue", "estimate", "expect", "may", "will", "project", "predict", "potential", "targeting", "intend", "could", "might", "should", "believe" and similar expressions. These statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements. Although MAG believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include, but are not limited to, changes in commodities prices, changes in mineral production performance, exploitation and exploration successes, continued availability of capital and financing, and general economic, market or business conditions, political risk, currency risk and capital cost inflation. In addition, forward-looking statements are subject to various risks, including that data is incomplete and considerable additional work will be required to complete further evaluation, including but not limited to drilling, engineering and socio-economic studies and investment. The reader is referred to the Company's filings with the SEC and Canadian securities regulators for disclosure regarding these and other risk factors. There is no certainty that any forward-looking statement will come to pass and investors should not place undue reliance upon forward-looking statements.

Please Note: Investors are urged to consider closely the disclosures in MAG's annual and quarterly reports and other public filings, accessible through the Internet at www.sedar.com and www.sec.gov LEI: 254900LGL904N7F3EL14


For further information on behalf of MAG Silver Corp. Contact Michael J. Curlook, VP Investor Relations and Communications Phone: (604) 630-1399 Toll Free: (866) 630-1399 Website: www.magsilver.com Email: info@magsilver.com

Primary Logo

News Provided by GlobeNewswire via QuoteMedia

The Conversation (0)
Silver bars and coins.

Silver Price Update: Q1 2024 in Review

2023 was a relatively lackluster year, silver largely traded on volatility between US$22 and US$25 per ounce.

The white metal started 2024 with less volatility and remained rangebound for the first eight weeks. Silver dropped to US$22.08 per ounce on January 21, marking its quarterly low.

Silver started seeing gains in March with the expectation that the US Federal Reserve was getting closer to lowering interest rates. Improving sentiment gave the precious metals markets momentum, causing silver to reach its quarterly high of US$25.62 on March 20, before continuing on to an 11 year high of US$29.26 on April 12.

Keep reading...Show less

Endeavour Silver Provides Q1 2024 Construction Progress Update on Terronera; Construction Progress Reaches 53% Completion

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to provide a Q1 2024 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project Progress Photos . All dollar ($) references in this news release are United States dollars.

The Terronera project made significant progress in the first quarter, as concrete work was nearly complete on the Upper Plant Platform and erection of structural steel advanced for areas including crushing, coarse-ore storage, grinding, flotation, and thickening. Mechanical installation of major equipment continued to advance on schedule and the project remains on track for commissioning in Q4 2024.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Silver bars and price chart.

Silver Due to Record Second Highest Deficit in 20 Years

Industrial demand for silver rose to a new record high in 2023, coming in at 654.4 million ounces (Moz).

The surge was fueled by significant advancements in green economy sectors, particularly photovoltaics (PV), where demand skyrocketed by 64 percent year-on-year to hit 195.3 Moz, surpassing previous estimates.

PV is included in the electrical and electronics segment, which experienced demand growth of 20 percent year-on-year.

Keep reading...Show less

Endeavour Silver Celebrates Milestone: Terronera Surpasses 50% Construction Completion

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) announces a significant milestone in the construction of its new Terronera mine, in Jalisco state, Mexico. The project has surpassed the 50% completion mark, marking a crucial step forward in the Company's expansion efforts.

To celebrate this achievement, the Company is pleased to provide a short video offering investors an exclusive look at the new mine with insights from the executive team. This video highlights the construction progress, showcases the scale and scope of the project, and emphasizes the positive impact on both the company and the local community. Investors, stakeholders, and the public are invited to watch this milestone video here . The video was filmed in mid-March and represents construction progress at that time.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Fortuna to release first quarter 2024 financial results on May 7, 2024; Conference call at 12 p.m. Eastern Time on May 8, 2024

Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) announces that it will release its unaudited financial statements and MD&A for the first quarter on Tuesday, May 7, 2024, after the market closes.

A conference call to discuss the financial and operational results will be held on Wednesday, May 8, 2024, at 9:00 a.m. Pacific Time | 12:00 p.m. Eastern Time. Hosting the call will be Jorge A. Ganoza, President and CEO, Luis D. Ganoza, Chief Financial Officer, Cesar Velasco, Chief Operating Officer - Latin America, and David Whittle, Chief Operating Officer - West Africa.

News Provided by GlobeNewswire via QuoteMedia