Hudbay Releases Copper Mountain Technical Report and Advances Mine Stabilization Plans

  • Average annual copper production of 46,500 tonnes over the first five years with cash costs of $1.89 i per pound, and 45,000 tonnes over the first 10 years with cash costs of $1.72 i per pound.
    • Represents an approximate 90% increase over 2022 production levels and 50% decrease from 2022 cash costs as a result of the implementation of Hudbay's operational efficiencies as part of its stabilization and optimization plans.
  • Mine plan reflects Hudbay's plans to stabilize the operation by remobilizing idle haul trucks, opening additional mining faces and accelerating stripping over the next three years, optimizing ore feed to the plant and implementing plant improvement initiatives.
  • On track to deliver more than $20 million in targeted annual operating efficiencies and $10 million in corporate synergies over the next three years.
  • Efficient capital utilization with minimal capital investment required to expand the mill throughput to the permitted limit of 50,000 tonnes per day.
  • Copper Mountain is expected to increase Hudbay's annual copper production by approximately 50% after 2025 ii .
  • Copper Mountain provides additional leverage to gold with approximately 49,500 ounces of annual gold production on average over the next 10 years.
  • Mineral reserve estimates of 367 million tonnes at a copper grade of 0.25% and gold grade of 0.12 grams per tonne support a 21-year mine life and position Copper Mountain as the longest life producing asset in Hudbay's portfolio.
  • Additional 140 million tonnes of measured and indicated resources at 0.21% copper and 0.10 grams per tonne gold and 370 million tonnes of inferred resources at 0.25% copper and 0.13 grams per tonne gold, exclusive of mineral reserves, provide significant upside potential for reserve conversion and extending mine life, with infill drilling planned for 2024.
  • The technical report represents Hudbay's base case mine plan after acquisition and there are numerous technical studies underway to further enhance the production profile, reduce mining costs and continue process optimization.

Hudbay Minerals Inc. ("Hudbay" or the "company") ( TSX, NYSE: HBM) today announced that it has completed a National Instrument 43-101 technical report in respect of its 75%-owned Copper Mountain mine in British Columbia, Canada. This is Hudbay's first technical report for the Copper Mountain mine since acquiring Copper Mountain Mining Corporation ("CMMC") in June 2023. All dollar amounts are in US dollars, unless otherwise noted.

"We are pleased to release our first mine plan for Copper Mountain which demonstrates the meaningful copper production this long-life asset brings to our operating platform and the unique opportunity we have to leverage our efficient operating capabilities to drive value," said Peter Kukielski, Hudbay's President and Chief Executive Officer. "We have applied our proven reserve and resource estimation methodology to develop a prudent and reliable mine plan and are now positioned to implement several operating enhancements to transform Copper Mountain into a stable cash flow generator for our business. With the addition of Copper Mountain, we expect to maintain annual consolidated copper production above 150,000 tonnes through to the end of the decade and are better positioned to achieve our deleveraging objectives and deliver on future copper growth. This increased scale and diversification enhances the company's ability to prudently advance our organic growth pipeline of brownfield expansion and greenfield development opportunities in tier-one mining jurisdictions."

Mine Plan Summary

The Copper Mountain mine is located 21 kilometres south of the town of Princeton and 304 kilometres east of Vancouver, as shown in Figure 1. The operations include a series of open pits, an ore processing plant, a waste rock facility, a tailings management facility and other ancillary facilities that support the operations. Please refer to Figure 2 for a site layout map. All claims are controlled by Copper Mountain Mine (BC) Ltd., a joint venture held 75% by Hudbay and 25% by Mitsubishi Materials Corp.

The mine plan contemplates average annual copper production of 46,500 tonnes in the first five years, 45,000 in the first ten years and 37,000 tonnes over the 21-year mine life. Average cash costs and sustaining cash costs over the mine life are expected to be $1.84 and $2.53 per pound of copper i , respectively. The updated mine plan represents an approximate 90% increase in average annual copper production and a 50% decrease in cash costs over the first 10 years compared to 2022.

As shown in Figure 3, Copper Mountain increases Hudbay's expected consolidated annual copper production by approximately 50% and maintains the 150,000 tonne per year level beyond 2025.

A summary of key production and cost details can be found below. For further details, please refer to the detailed mine plan table in Exhibit 1.

2024 2025 2026 2027 2028 2024-2028 Avg. 2029-2033 Avg. 2034-2038 Avg. 2039-2043 Avg. LOM
Total
Contained Metal in Concentrate
Cu production tonnes
(000s)
37 40 49 50 56 47 43 39 26 783
Au production ounces
(000s)
21 36 26 44 47 35 64 60 26 935
Ag production ounces
(000s)
378 334 500 434 477 425 235 213 226 5,590
Capital Expenditures
Sustaining capital (after capitalized stripping) 1 US$ millions $63 $122 $91 $59 $94 $   86 $   67 $   55 $   13 $   1,106
Discretionary capitalized stripping 2 US$ millions $22 $42 $21 - - $   17 - - - $   85
Growth capital US$ millions $3 $41 $69 $6 $7 $   25 - - - $   126
Cash Costs
Cash costs, net of by-product credits 3 US$/lb Cu $2.69 $1.89 $1.89 $1.90 $1.36 $   1.89 $   1.53 $   1.75 $   2.31 $   1.84
Sustaining cash costs, net of by-product credits (excl. discretionary stripping) 3 ,4 US$/lb Cu $3.49 $3.40 $2.74 $2.45 $2.13 $   2.76 $   2.26 $   2.46 $   2.58 $   2.53

Note: Totals may not add up correctly due to rounding. "LOM" refers to life-of-mine total.
1 Sustaining capital includes capitalized stripping.
2 Discretionary capitalized stripping relates to a portion of accelerated stripping activities over 2024-2026 to access higher grade ore but could be reduced or deferred to a later date based on further geotechnical evaluation and other considerations.
3 By-product credits calculated using the following commodity prices and foreign exchange assumptions: gold price of $1,940 per ounce for 2024, $1,900 per ounce for 2025, $1,800 per ounce for 2026, $1,764 per ounce for 2027, $1,725 per ounce for 2028 and $1,700 per ounce long-term; silver price of $24.00 per ounce for 2024, 2025 and 2026, $23.75 per ounce for 2027, $23.38 per ounce for 2028 and $23.00 per ounce long-term; C$/US$ exchange rate of 1.35 in 2024 and 1.33 in 2025 onwards.
4 Sustaining cash costs incorporate all costs included in cash costs plus sustaining capital expenditures, capitalized stripping, payments on capital leases, royalties and accretion and amortization of decommissioning obligations, and excludes discretionary capitalized stripping. Cash costs and sustaining cash costs are non-IFRS financial performance measures with no standardized definition under IFRS. For further details on why Hudbay believes cash costs are a useful performance indicator, please refer to the company's most recent Management's Discussion and Analysis for the period ended September 30, 2023.

Hudbay's Stabilization Plans

Since completing the acquisition of CMMC in June 2023, Hudbay has been focused on advancing its plans to stabilize the Copper Mountain mine over the next few years to improve reliability and drive sustainable long-term value. The technical report reflects Hudbay's base case stabilization plan including many elements as described further below.

Increased Mining Activities

The company has commenced a fleet ramp-up plan which remobilizes idle haul trucks. The fleet ramp up plan entails a ramp-up from 14 trucks to 26 trucks by the end of 2023, with 23 trucks ramped up to-date. Once the fleet ramp up plan is complete, Copper Mountain is expected to have improved flexibility in the mine with additional mining faces.

Accelerated Stripping to Access Higher Grades

As reflected in the technical report, the company is planning a campaign of accelerated stripping over the next three years to enable access to higher grade ore and to mitigate the substantially reduced stripping undertaken by Copper Mountain over the four years prior to completion of the acquisition (please refer to Figure 4). The accelerated stripping program is also expected to improve operating efficiencies and lower unit operating costs. A portion of the accelerated capitalized stripping costs is considered discretionary and could be reduced or deferred to a later date based on further geotechnical evaluation and other considerations.

Improved Mill Throughput and Recoveries

Hudbay's mine plan for Copper Mountain assumes a mill ramp up to its nominal capacity of 45,000 tonnes per day in 2025. An expansion to the permitted capacity of 50,000 tonnes per day is planned in 2027. The mine plan assumes approximately $23 million in growth capital spending over 2025 and 2026 in connection with the mill expansion. The company also plans to improve mill recoveries with a more consistent ore feed grade, changes to the flotation reagents and replacement of key pumps.

Operating Efficiencies and Corporate Synergies

Hudbay's stabilization plans as reflected in the technical report are expected to generate more than $20 million in annual operating efficiencies over the next three years, compared to Copper Mountain's performance in 2022, through improvements in copper recovery, higher throughput rates and lower combined unit operating costs. In addition, Hudbay has realized approximately $9 million of the targeted $10 million in annual corporate synergies and is on track to exceed the target. A full comparison of Hudbay's plan versus Copper Mountain's 2022 performance is presented in the following table.

Copper Mountain 2022A 1 2024-2028 Avg. Change
Mill throughput tonnes per day 34,814 46,851 +12,037
Copper recovery % 79.1% 84.5   % +5.4%
Corporate G&A C$ millions $17 $   4 -$13
Total unit operating costs (after capitalized stripping) 2 C$/tonne milled $23.95 $   17.06 -$6.89
Cash costs, net of by-product credits 2 US$/lb Cu $3.53 $   1.89 -$1.64
Sustaining cash costs, net of by-product credits (excl. discretionary stripping) 2,3 US$/lb Cu $4.78 $   2.76 -$2.02

1 2022 actuals as disclosed by CMMC on March 27, 2023. CMMC Financial Statements and Management's Discussion & Analysis for the applicable periods are available under CMMC's SEDAR+ profile at www.sedarplus.ca . 2022 total unit operating costs includes direct mining and milling costs, employee compensation and benefits, transportation costs and corporate and mine site administration expenses.
2 Cash costs, sustaining cash costs and unit operating costs are non-IFRS financial performance measures with no standardized definition under IFRS. For further details on why Hudbay believes cash costs and unit operating costs are useful performance indicators, please refer to the company's most recent Management's Discussion and Analysis for the period ended September 30, 2023.
3 By-product credits calculated using the following commodity prices and foreign exchange assumptions: gold price of $1,940 per ounce for 2024, $1,900 per ounce for 2025, $1,800 per ounce for 2026, $1,764 per ounce for 2027, $1,725 per ounce for 2028 and $1,700 per ounce long-term; silver price of $24.00 per ounce for 2024, 2025 and 2026, $23.75 per ounce for 2027, $23.38 per ounce for 2028 and $23.00 per ounce long-term; C$/US$ exchange rate of 1.35 in 2024 and 1.33 in 2025 onwards. Sustaining cash costs incorporates all costs included in cash costs plus sustaining capital expenditures, capitalized stripping, payments on capital leases, royalties and accretion and amortization of decommissioning obligations, and excludes discretionary capitalized stripping.

Mineral Reserve and Resource Estimates

The mine plan is based on a revised resource model and was constructed using the same methods applied at the Constancia, Copper World and Mason deposits. The mineral reserve estimates total 367 million tonnes at a copper grade of 0.25% and a gold grade of 0.12 grams per tonne, supporting a 21-year mine life. An additional 140 million tonnes of measured and indicated resources at 0.21% copper and 0.10 grams per tonne gold and 370 million tonnes of inferred resources at 0.25% copper and 0.13 grams per tonne gold, exclusive of mineral reserves, provide significant upside potential for reserve conversion and extending mine life. Infill drilling is planned for 2024 to target reserve conversion.

The current mineral reserve and resource estimates for Copper Mountain (effective as of December 1, 2023) are summarized below.

Copper Mountain Mine
Mineral Reserve and Resource Estimates 1 ,2,3,4
Tonnes Cu Grade
(%)
Au Grade
(g/t)
Ag Grade
(g/t)
CuEq Grade
(%)
Reserves
Proven 195,037,000 0.27 0.12 0.78 0.35
Probable 171,943,000 0.22 0.11 0.59 0.30
Total proven and probable 366,980,000 0.25 0.12 0.69 0.33
Resources
Measured 41,198,000 0.21 0.09 0.73 0.27
Indicated 96,615,000 0.21 0.11 0.68 0.29
Total measured and indicated 137,814,000 0.21 0.10 0.69 0.28
Inferred 371,319,000 0.25 0.13 0.61 0.34

Note: totals may not add up correctly due to rounding.
1 Mineral resource estimates are exclusive of mineral reserves. Mineral resources are not mineral reserves as they do not have demonstrated economic viability.
2 Mineral reserve estimates have been calculated using assumed long-term metal prices of $3.75 per pound copper, $1,650 per ounce gold and $22.00 per ounce silver. Mineral resource estimates have been calculated using assumed long-term metal prices of $4.00 per pound copper, $1,650 per ounce gold and $22.00 per ounce silver.
3 Mineral resource estimates tonnes and grades constrained to a Lerch Grossman revenue factor 1 pit shell.
4 Mineral reserves have an effective date of December 1, 2023, but were generated excluding the measured and indicated mineral resource estimates planned to be mined and milled in the month of December 2023. Mineral reserves are reported using an NSR cut-off value of $5.67 that meet a minimum 0.10% Cu grade.

Consistent with the expectations disclosed in the company's news release on November 7, 2023, the 2023 mineral reserve and mineral resource estimates are consistent with historical estimates published by CMMC until 2019, after adjusting for mining depletion and a re-classification of some of the indicated mineral resources to the inferred category, as well as incorporating high grade resources added through exploration since 2019. Hudbay's new 2023 resource estimates are closely aligned with production with both tonnage and grade reconciling positively within 3% to 4% of the credited mine production by the mill over the past three years.

Project Optimization and Upside Opportunities

There are several opportunities to further increase production, improve costs and extend mine life for Copper Mountain. While these opportunities have not been considered in the technical report as they are not yet at the level of required engineering, the company is advancing studies to evaluate the potential for these to be reflected in future mine plans.

  • Conversion of Inferred Resources to Reserves – there is a significant amount of high-grade mineralization in the inferred category that has the potential to be converted to reserves, which would increase production, improve head grades over the next 10 years and extend mine life beyond 21 years. The company has plans for infill drilling in 2024 to target reserve conversion.
  • Lower Stripping Costs – the company will carry out additional geotechnical investigations and pit slope stability tests in the area of Pit 3 to identify opportunities to maximize the use of double benching and reduce waste stripping that is currently classified as discretionary.
  • Evaluation of Mining Technologies – Hudbay will pursue technology trade-offs between trolley assist haul trucks and conveying systems for ore and waste movement in an effort to reduce mining costs, improve mining productivity, and reduce greenhouse gas emissions.
  • Continued Process Optimization – Hudbay continues to conduct metallurgical testing and simulations to optimize mill throughput and recoveries.
  • Renewable Diesel – Hudbay is evaluating the application of renewable diesel at Copper Mountain, which has the potential to reduce costs, lower greenhouse gas emissions and be eligible for additional federal tax credits under Canada's Clean Fuel Regulations .
  • Green Opportunities – the company plans to install a mast to collect wind data to be able to evaluate the potential for site renewable energy generation. This initiative is in addition to the existing net-zero initiatives already underway, including trolley assist haulage and a new electric shovel, which favourably position Copper Mountain in the lowest quartile of the greenhouse gas emissions curve for copper mines.

Non-IFRS Financial Performance Measures

Cash cost and sustaining cash cost per pound of copper produced are shown because the company believes they help investors and management assess the performance of its operations, including the margin generated by the operations and the company. Unit operating costs are shown because these measures are used by the company as a key performance indicator to assess the performance of its mining and processing operations. These measures do not have a meaning prescribed by IFRS and are therefore unlikely to be comparable to similar measures presented by other issuers. These measures should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS and are not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate these measures differently. For further details on these measures, please refer to page 45 of Hudbay's management's discussion and analysis for the period ended September 30, 2023 available on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov.

Cautionary Note Regarding NI 43-101

The scientific and technical information contained in this news release has been approved by Olivier Tavchandjian, P. Geo, Hudbay's Senior Vice-President, Exploration and Technical Services. Mr. Tavchandjian is a qualified person pursuant to Canadian Securities Administrators' National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101").

A copy of the NI 43-101 technical report will be made available on Hudbay's SEDAR+ profile at www.sedarplus.ca and on Hudbay's EDGAR profile at www.sec.gov . This technical report is the current technical report in respect of the Copper Mountain mine and shall supersede and replace all prior technical reports relating to the Copper Mountain mine.

Cautionary Note to United States Investors

This news release has been prepared in accordance with the requirements of the securities laws in effect in Canada, which differ from the requirements of United States securities laws. Canadian reporting requirements for disclosure of mineral properties are governed NI 43-101.

For this reason, information contained in this news release in respect of the Copper Mountain mine may not be comparable to similar information made public by United States companies subject to the reporting and disclosure requirements under the United States federal securities laws and the rules and regulations thereunder. For further information on the differences between the disclosure requirements for mineral properties under the United States federal securities laws and NI 43-101, please refer to the company's annual information form, a copy of which has been filed under Hudbay's profile on SEDAR+ at www.sedarplus.ca and the company's Form 40-F, a copy of which has been filed under Hudbay's profile on EDGAR at www.sec.gov.

Cautionary Note Regarding Forward-Looking Information

This news release contains forward-looking information within the meaning of applicable Canadian and United States securities legislation. All information contained in this news release, other than statements of current and historical fact, is forward-looking information. Often, but not always, forward-looking information can be identified by the use of words such as "plans", "expects", "budget", "guidance", "scheduled", "estimates", "forecasts", "strategy", "target", "intends", "objective", "goal", "understands", "anticipates" and "believes" (and variations of these or similar words) and statements that certain actions, events or results "may", "could", "would", "should", "might" "occur" or "be achieved" or "will be taken" (and variations of these or similar expressions). All of the forward-looking information in this news release is qualified by this cautionary note.

Forward-looking information includes, but is not limited to, production, operating cost, capital cost and cash cost estimates, project design, including processing and tailings facilities, metal recoveries, mine life and production rates for the Copper Mountain mine, the potential to further enhance the economics of the project and optimize the design, the impact and effects of Hudbay's optimization and stabilization initiatives, statements regarding permitting matters, the relationships with the First Nations groups, local communities of interest, regulatory agencies and other key stakeholders, the expectations and plans for New Ingerbelle, the renegotiation of the participation agreements with the Upper Similkameen Indian Band and Lower Similkameen Indian Band, the costs associated with planned stripping, and the conceptual mine closure and reclamation plan. Forward-looking information is not, and cannot be, a guarantee of future results or events. Forward-looking information is based on, among other things, opinions, assumptions, estimates and analyses that, while considered reasonable by the company at the date the forward-looking information is provided, inherently are subject to significant risks, uncertainties, contingencies and other factors that may cause actual results and events to be materially different from those expressed or implied by the forward-looking information.

The material factors or assumptions that Hudbay identified and were applied by the company in drawing conclusions or making forecasts or projections set out in the forward-looking information include, but are not limited to:

  • the company's ability to stabilize and optimize the Copper Mountain mine operations;
  • the success of exploration and development activities at the Copper Mountain mine, including New Ingerbelle;
  • the accuracy of geological, mining and metallurgical estimates;
  • anticipated metals prices and the costs of production;
  • the supply and demand for metals Hudbay produces;
  • the supply and availability of all forms of energy and fuels at reasonable prices;
  • no significant unanticipated operational or technical difficulties;
  • the availability of additional financing, if needed;
  • the availability of personnel for the company's exploration, development and operational projects and ongoing employee relations;
  • maintaining applicable and necessary permits;
  • maintaining good relations with the First Nations groups, local communities of interest, regulatory agencies and other key stakeholders, including the neighbouring communities and local governments in British Columbia;
  • no significant unanticipated challenges with stakeholders at the Copper Mountain mine;
  • no significant unanticipated events or changes relating to regulatory, environmental, health and safety matters;
  • no contests over title to Hudbay's properties, including as a result of rights or claimed rights of Indigenous peoples or challenges to the validity of its unpatented mining claims;
  • no offtake commitments in respect of production from the Copper Mountain mine, other than those contemplated herein;
  • certain tax matters, including, but not limited to the mining tax regime in British Columbia; and
  • no significant and continuing adverse changes in general economic conditions or conditions in the financial markets (including commodity prices and foreign exchange rates).

The risks, uncertainties, contingencies and other factors that may cause actual results to differ materially from those expressed or implied by the forward-looking information may include, but are not limited to, risks generally associated with the mining industry and the current geopolitical environment, such as economic factors (including future commodity prices, currency and interest rate fluctuations, energy and consumable prices, supply chain constraints and general cost escalation in the current inflationary environment), risks related to product delivery and financing, risks related to the ability for the company to successfully maintain all applicable and necessary permits, risks related to changes in government and government policy, risks related to changes in law, risks in respect of community relations, including but not limited to the relationships with First Nations groups, local communities of interest, regulatory agencies and other key stakeholders, risks related to contracts that were entered into in respect of the Copper Mountain mine, including but not limited to the renegotiation of the participation agreements with the Upper Similkameen Indian Band and Lower Similkameen Indian Band, risks related to the conceptual mine closure and reclamation plan, uncertainties related to the geology, continuity, grade and estimates of mineral reserves and resources, and the potential for variations in grade and recovery rates, as well as the risks discussed under the heading "Risk Factors" in the company's most recent annual information form and under the heading "Financial Risk Management" in the company's most recent management's discussion and analysis.

Should one or more risk, uncertainty, contingency or other factor materialize or should any factor or assumption prove incorrect, actual results could vary materially from those expressed or implied in the forward-looking information. Accordingly, you should not place undue reliance on forward-looking information. The company does not assume any obligation to update or revise any forward-looking information after the date of this news release or to explain any material difference between subsequent actual events and any forward-looking information, except as required by applicable law.

About Hudbay

Hudbay (TSX, NYSE: HBM) is a copper-focused mining company with three long-life operations and a world-class pipeline of copper growth projects in tier-one mining-friendly jurisdictions of Canada, Peru and the United States.

Hudbay's operating portfolio includes the Constancia mine in Cusco (Peru), the Snow Lake operations in Manitoba (Canada) and the Copper Mountain mine in British Columbia (Canada). Copper is the primary metal produced by the company, which is complemented by meaningful gold production. Hudbay's growth pipeline includes the Copper World project in Arizona, the Mason project in Nevada (United States), the Llaguen project in La Libertad (Peru) and several expansion and exploration opportunities near its existing operations.

The value Hudbay creates and the impact it has is embodied in its purpose statement: "We care about our people, our communities and our planet. Hudbay provides the metals the world needs. We work sustainably, transform lives and create better futures for communities." Hudbay's mission is to create sustainable value and strong returns by leveraging its core strengths in community relations, focused exploration, mine development and efficient operations.

For further information, please contact:

Candace Brûlé
Vice President, Investor Relations
(416) 814-4387
investor.relations@hudbay.com

______________________________

i Cash costs and sustaining cash costs are non-IFRS financial performance measures with no standardized definition under IFRS. For further details on why Hudbay believes cash costs are a useful performance indicator, please refer to the company's most recent Management's Discussion and Analysis for the period ended September 30, 2023.
i i Based on copper production from most recent technical reports for Hudbay's Constancia, Snow Lake and Copper Mountain operations.

Exhibit 1: Detailed Mine Plan Information

2024 2025 2026 2027 2028 2024-2028 Avg. 2029-2033 Avg. 2034-2038 Avg. 2039-2043 Avg. LOM
Total
Mining
Ore mined tonnes
(000s)
18,983 22,363 14,020 20,710 21,096 19,434 20,411 18,460 4,180 312,425
Waste mined tonnes
(000s)
82,832 91,637 86,480 63,290 48,904 74,629 47,589 44,940 6,154 866,559
Strip ratio waste: ore 4.36 4.10 6.17 3.06 2.32 3.84 2.33 2.43 1.47 2.77
Processing
Ore milled tonnes
(000s)
15,008 16,425 17,520 18,250 18,300 17,101 18,260 18,260 18,260 366,980
Daily ore milled tonnes
per day
41,118 45,000 48,000 50,000 50,137 46,851 50,027 50,027 50,027 47,877
Cu grade % 0.30% 0.29% 0.33% 0.32% 0.36% 0.32   % 0.27   % 0.24   % 0.17   % 0.25   %
Au grade g/t 0.07 0.10 0.07 0.11 0.12 0.10 0.16 0.15 0.07 0.12
Ag grade g/t 1.12 0.90 1.27 1.07 1.17 1.11 0.60 0.54 0.55 0.69
Cu recovery % 82.5% 84.0% 84.0% 85.6% 85.5% 84.5   % 86.7   % 86.4   % 85.1   % 85.7   %
Au recovery % 65.0% 65.0% 65.0% 67.9% 67.8% 66.5   % 69.6   % 69.0   % 66.0   % 68.3   %
Ag recovery % 70.0% 70.0% 70.0% 69.2% 69.2% 69.6   % 66.5   % 67.1   % 69.7   % 68.5   %
Contained Metal in Concentrate
Cu production tonnes (000s) 37 40 49 50 56 47 43 39 26 783
Au production ounces
(000s)
21 36 26 44 47 35 64 60 26 935
Ag production ounces
(000s)
378 334 500 434 477 425 235 213 226 5,590
Capital Expenditures (US$ millions) 1
Sustaining capital $46 $63 $50 $45 $36 $   48 $   27 $   22 $   13 $   549
Capitalized stripping $17 $59 $41 $14 $57 $   38 $   41 $   33 - $   558
Sustaining capital (after capitalized stripping) $   63 $   122 $   91 $   59 $   94 $   86 $   67 $   55 $   13 $   1,106
Discretionary capitalized stripping 2 $22 $42 $21 - - $   17 - - - $   85
Growth project capital $3 $41 $69 $6 $7 $   25 - - - $   126
Total capital expenditures $   88 $   205 $   181 $   65 $   101 $   128 $   67 $   55 $   13 $   1,317
Unit Operating Costs (C$ per tonne milled) 3
Mining 4 $15.30 $16.33 $13.84 $12.06 $11.92 $   13.78 $   11.73 $   11.32 $   4.82 $   10.21
Milling $7.41 $6.77 $5.94 $5.70 $5.69 $   6.25 $   5.70 $   5.70 $   5.70 $   5.85
G&A $1.48 $1.35 $1.27 $1.22 $1.18 $   1.29 $   1.17 $   1.14 $   0.87 $   1.13
Total operating costs (before cap. stripping) $24.19 $24.45 $21.05 $18.98 $18.79 $   21.32 $   18.60 $   18.16 $   11.39 $   17.19
Total operating costs (after cap. stripping) $   20.68 $   16.27 $   16.31 $   17.96 $   14.61 $   17.06 $   15.64 $   15.73 $   11.39 $   14.86
Cash Costs and Sustaining Cash Costs (US$/lb Cu)
Copper production million lbs 81.6 87.9 108.4 110.6 124.0 102.5 95.1 85.1 58.4 1,726.4
Cash costs 3, 5 $   2.69 $   1.89 $   1.89 $   1.90 $   1.36 $   1.89 $   1.53 $   1.75 $   2.31 $   1.84
Sustaining cash costs 3, 5 (excl. discretionary stripping) $   3.49 $   3.40 $   2.74 $   2.45 $   2.13 $   2.76 $   2.26 $   2.46 $   2.58 $   2.53
Sustaining cash costs 3, 5 (incl. discretionary stripping) $3.77 $3.87 $2.94 $2.45 $2.13 $   2.93 $   2.26 $   2.46 $   2.58 $   2.58

Note: LOM refers to life-of-mine total.
1 Sustaining capital includes capitalized lease payments.
2 Discretionary capitalized stripping relates to a portion of accelerated stripping activities over 2024-2026 to access higher grade ore but could be reduced or deferred to a later date based on further geotechnical evaluation and other considerations.
3 Cash costs, sustaining cash costs and unit operating costs are non-IFRS financial performance measures with no standardized definition under IFRS. For further details on why Hudbay believes cash costs and unit operating costs are useful performance indicators, please refer to the company's most recent Management's Discussion and Analysis for the period ended September 30, 2023.
4 Mining cost before the impact of capitalized stripping.
5 By-product credits calculated using the following commodity prices and foreign exchange assumptions: gold price of $1,940 per ounce for 2024, $1,900 per ounce for 2025, $1,800 per ounce for 2026, $1,764 per ounce for 2027, $1,725 per ounce for 2028 and $1,700 per ounce long-term; silver price of $24.00 per ounce for 2024, 2025 and 2026, $23.75 per ounce for 2027, $23.38 per ounce for 2028 and $23.00 per ounce long-term; C$/US$ exchange rate of 1.35 in 2024 and 1.33 in 2025 onwards. Sustaining cash costs incorporates all costs included in cash cost plus sustaining capital expenditures, capitalized stripping, payments on capital leases, royalties and accretion and amortization of decommissioning obligations.

Figure 1: Copper Mountain Mine Location
The Copper Mountain mine is located in British Columbia, Canada, 21 kilometres by road south of the town of Princeton and 304 kilometres by road east of Vancouver.

Figure 1: Copper Mountain Mine Location

Available at https://www.globenewswire.com/NewsRoom/AttachmentNg/e822c7fb-00aa-4c30-8c98-8b3f68b55a39

Figure 2: Copper Mountain Site Layout
The operations consist of the Copper Mountain pit, the New Ingerbelle pit, an ore processing plant, a waste rock facility, a tailings management facility and other associated site infrastructure that support the operations.

Figure 2: Copper Mountain Site Layout

Available at https://www.globenewswire.com/NewsRoom/AttachmentNg/671dfc0b-4a83-49bf-82e5-6ad4bd77bf22

Figure 3: Hudbay Consolidated Production Profile Graph
Copper Mountain is a meaningful contributor to Hudbay's consolidated copper production profile. The impact is significant after 2025 with increases of up to 50% in annual copper production to maintain the 150,000 tonnes per year level.

Figure 3: Hudbay Consolidated Production Profile Graph

Available at https://www.globenewswire.com/NewsRoom/AttachmentNg/b13833be-78f8-4be5-aee6-87ada5b461d2

Source: Based on Hudbay previously issued copper production guidance for 2023 to 2025. Copper production in the years 2026 to 2028 is sourced from Hudbay's Constancia NI 43-101 technical report dated March 2021, Snow Lake NI 43-101 technical report dated March 2021 and Copper Mountain NI 43-101 technical report dated December 4, 2023. Production profile excludes potential future production from the Copper World project.

Figure 4: Copper Mountain Mine Performance
Hudbay's mine plan incorporates accelerated stripping activities to help mitigate the impacts of substantially reduced stripping undertaken by Copper Mountain over the past four years. The accelerated stripping is expected to enable access to higher grade ore and improve the efficiency of the mine. Hudbay expects sustained improvements in mill throughput to achieve the design capacity of 45,000 tonnes per day and an expansion to the permitted limit of 50,000 tonnes per day in 2027.

Figure 4: Copper Mountain Mine Performance

Available at https://www.globenewswire.com/NewsRoom/AttachmentNg/38cbcc94-60a9-4c7e-ba43-b61e0bc46986

Source: CMMC historical annual disclosure for the years 2018 to 2022 and Hudbay's Copper Mountain NI 43-101 technical report dated December 4, 2023 for the years 2024 to 2028.


Primary Logo

News Provided by GlobeNewswire via QuoteMedia

HBM:CA,HBM
The Conversation (0)
NOVA ROYALTY COMPLETES ACQUISITION OF ROYALTY ON HUDBAY'S COPPER WORLD AND ROSEMONT COPPER PROJECTS

NOVA ROYALTY COMPLETES ACQUISITION OF ROYALTY ON HUDBAY'S COPPER WORLD AND ROSEMONT COPPER PROJECTS

TSXV: NOVR  
OTCQB: NOVRF

(All dollar amounts are in United States Dollars unless otherwise indicated)

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

Manitoba Mining Sector to See Boost from Global Lithium Demand

While other materials have seen unstable markets in the last year, demand for lithium has continued to rise in order to meet the demands of the lithium-ion battery market.

According to a recent CBC article, one of the jurisdictions that is seeing an uptick in lithium exploration activity is Manitoba’s Snow Lake region. Snow Lake sits 200 kilometers east of Flin Flon, another area in the province that is well known for lithium production. Companies like Snow Lake Resources and Far Resources (CSE:FAT) are leading the charge in exploring the Snow Lake region, showing a glimmer of hope and promise as the province faces ongoing employment challenges in its mining sector. This follows decisions from both Hudbay Minerals (TSX:HBM,NYSE:HBM) and Vale (NYSE:VALE) to reduce their activities in Manitoba.

Keep reading...Show less
Copper wire.

Lobo Tiggre: Copper is My Highest-Confidence Trade for 2025 — Here's Why

Lobo Tiggre, CEO of IndependentSpeculator.com, gave the Investing News Network his updated thoughts on the US economy, as well as his outlook for gold, silver and uranium in 2025.

However, he said his highest-confidence trade for next year is copper.

"I think that it's easier to see — and highly likely to see — copper moving higher next year," Tiggre explained.

Keep reading...Show less
Large chunk of copper.

29Metals Shares Feasibility Study and Final Investment Decision for Gossan Valley Project

29Metals (ASX:29M) has announced a feasibility study and final investment decision for the Gossan Valley project at its Golden Grove volcanic-hosted massive sulphide mine in Western Australia.

The feasibility study is an update to the 2022 version of the document. It outlines production of 4,000 tonnes of copper and 20,000 tonnes of zinc annually at Gossan Valley over an initial mine life of seven years.

CEO James Palmer said the development of Gossan Valley is the "next logical development option" when it comes to moving forward at Golden Grove, which was first discovered in 1971.

Keep reading...Show less
Somerset Minerals Logo

Acquisition of High-Grade Copper Project Adjacent to White Cliff Minerals

Somerset Minerals Ltd (“Somerset” or the “Company”) (ASX:SMM) is pleased to advise that it has entered into a conditional agreement to acquire 100% of the issued capital of Sentinel Resources Pty Ltd (“Sentinel”), which, through its local subsidiary, holds the Coppermine Project (the “Project”) in Nunavut, Canada.

Importantly, the Coppermine Project hosts 1,055 km2 of the prospective Copper Creek Formation basalts, and is interpreted to include the strike extensions to White Cliff’s high priory targets of Vision, Stark, Thor and Rocket (Figure 2 & 3), with the prospectivity of the wider project area also supported by extensive surface sampling and historic exploration (Table 1). Importantly, Somerset holds the ground entirely around and along strike from White Cliff’s recently acquired Danvers prospect which contains a non-JORC or NI 43-101 resource of 4.16Mt @ 2.96% Cu.

Keep reading...Show less
US$100 bills.

Lundin Mining to Divest Neves-Corvo and Zinkgruvan Operations for US$1.52 Billion

Lundin Mining (TSX:LUN,OTC Pink:LUNMF) has entered a definitive agreement to sell its Neves-Corvo operation in Portugal and Zinkgruvan operation in Sweden to Boliden (STO:BOL) for up to US$1.52 billion.

The sale, announced by the company on Monday (December 9), will see Boliden acquire full ownership of Somincor, the company operating Neves-Corvo, as well as Zinkgruvan Mining Aktiebolag and its associated entities.

Lundin expects to receive upfront cash consideration of US$1.37 billion at closing, based on financial conditions as of August 31, 2024. Interest will accrue at 5 percent annually until the closing date.

Keep reading...Show less

Lundin Mining Announces Sale of Neves-Corvo and Zinkgruvan for Total Consideration of up to $1.52 Billion

Lundin Mining logo (CNW Group/Lundin Mining Corporation)

TSX: LUN) (Nasdaq Stockholm: LUMI) Lundin Mining Corporation ("Lundin Mining" or the "Company") announces today it has signed a definitive agreement to sell its Neves-Corvo operation in Portugal and Zinkgruvan operation in Sweden to Boliden AB (OM: BOL) ("Boliden") for up to $1.52 billion in total consideration (the "Transaction"). Unless otherwise stated, all numbers are presented in United States dollars.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Business handshake.

Rio Tinto and Sumitomo Partner to Advance Winu Copper-Gold Project

Rio Tinto (ASX:RIO,NYSE:RIO,LSE:RIO) has signed a term sheet with Sumitomo Metal Mining (TSE:5713) for a joint venture to advance the Winu copper-gold project in Western Australia.

The partnership, announced on Wednesday (December 4), seeks to develop both companies’ exploration initiatives.

Sumitomo will acquire a 30 percent equity stake in the Winu project for US$399 million, including an initial payment of US$195 million and US$204 million in deferred considerations tied to project milestones and other conditions.

Keep reading...Show less

Latest Press Releases

Related News

×