Hombre Muerto West  Phase 1 Construction Update - Nanofiltration Plant Delivered to Site

Hombre Muerto West Phase 1 Construction Update - Nanofiltration Plant Delivered to Site

Highlights:

  • Nanofiltration plant successfully delivered to HMW site

  • Galan and Authium teams have commenced on-site assembly. Assembly expected to be completed over the coming weeks

  • Evaporation (sylvinite) ponds for Phase 1 operations completed

  • Overall Phase 1 construction now approximately 85% complete

  • First processed brine expected early Q2 2026. First lithium chloride concentrate targeted in H1 2026

PERTH, AU / ACCESS Newswire / February 15, 2026 / Galan Lithium Limited (ASX:GLN,OTC:GLNLF) (Galan or the Company) is pleased to provide an update on construction progress at its 100% owned Hombre Muerto West (HMW) Project in Catamarca Province, Argentina.

Commenting from the HMW site Galan's Managing Director, Juan Pablo (JP) Vargas de la Vega, said:

"Our HMW site team is very excited at the arrival of the nanofiltration plant. Over the past 2 years we have accumulated a lithium brine inventory of around 9,500 tonnes (LCE) in the HMW ponds. In the short term we plan to complete the nanofiltration plant assembly and commissioning, which will allow for the first processed lithium brine to be produced from HMW.

The nanofiltration plant has been designed, tested, constructed and transported on an accelerated project schedule. I would like to recognise Authium's and Galan's teams who have come together in a spirit of partnership to make this possible."

Nanofiltration Plant Delivered and Assembly Underway

The Company confirms that the nanofiltration plant for Phase 1 operations has successfully arrived at the HMW project site.

Galan's technical team, together with specialists from Authium Limited (Authium), have commenced on-site assembly of the plant. Installation and assembly activities are expected to continue over the coming weeks, after which commissioning activities will begin.

The nanofiltration plant is a key component of Galan's processing flowsheet and will enable the efficient treatment of brine as part of the Phase 1 production process.

Sylvinite Ponds Completed

Construction of the sylvinite ponds required for the commencement of Phase 1 operations has now been completed. These ponds have been designed to accelerate the evaporation of processed brine, which leads to quicker production of lithium chloride concentrate and product sales for Galan.

Following Galan's successful capital raising in January 2026, construction work on the evaporation ponds will continue after the nanofiltration plant has been commissioned, to allow for the expanded production rate of 5,200 tpa LCE.

Key Upcoming Milestones

Overall construction of Phase 1 at Hombre Muerto West is now approximately 85% complete, reflecting continued strong progress across processing infrastructure, evaporation ponds and supporting site facilities. As we execute the last phase of construction activities at HMW important milestones will include:

  • the completion of nanofiltration plant assembly;

  • commissioning and testing of brine processing systems;

  • first processed brine (targeted in the first half of 2026); and

  • first lithium chloride concentrate production (targeted in the first half of 2026).

The Galan Board has authorised this release.

For further information contact:

COMPANY
Juan Pablo ("JP") Vargas de la Vega
Managing Director
jp@galanlithium.com.au
+ 61 8 9214 2150

MEDIA
Matt Worner
Vector Advisors
mworner@vectoradvisors.au
+61 429 522 924

SOURCE: Galan Lithium Limited



View the original press release on ACCESS Newswire

News Provided by ACCESS Newswire via QuoteMedia

GLN:AU
The Conversation (0)
Galan Lithium

Galan Lithium

Developing high-grade lithium brine projects in Argentina

Developing high-grade lithium brine projects in Argentina Keep Reading...
Successful Due Diligence Ends - $20M Placement To Proceed

Successful Due Diligence Ends - $20M Placement To Proceed

Galan Lithium (GLN:AU) has announced Successful Due Diligence Ends - $20m Placement To ProceedDownload the PDF here. Keep Reading...
Final At-The-Market Raise for 2025

Final At-The-Market Raise for 2025

Galan Lithium (GLN:AU) has announced Final At-The-Market Raise for 2025Download the PDF here. Keep Reading...
Quarterly Activities and Cash Flow Report

Quarterly Activities and Cash Flow Report

Galan Lithium (GLN:AU) has announced Quarterly Activities and Cash Flow ReportDownload the PDF here. Keep Reading...
Incentive Regime for HMW Project in Argentina

Incentive Regime for HMW Project in Argentina

Galan Lithium (GLN:AU) has announced Incentive Regime for HMW Project in ArgentinaDownload the PDF here. Keep Reading...
Trading Halt

Trading Halt

Galan Lithium (GLN:AU) has announced Trading HaltDownload the PDF here. Keep Reading...
Outstanding Silver Lead & Zinc Flotation Recoveries

Outstanding Silver Lead & Zinc Flotation Recoveries

Rapid Critical Metals (RCM:AU) has announced Outstanding Silver Lead & Zinc Flotation RecoveriesDownload the PDF here. Keep Reading...
SAGA Metals Completes Acquisition of Wolverine Heavy Rare Earth Element Project in Labrador-REE Mineralized Potential Similar to Strange Lake and Tanbreez

SAGA Metals Completes Acquisition of Wolverine Heavy Rare Earth Element Project in Labrador-REE Mineralized Potential Similar to Strange Lake and Tanbreez

Saga Metals Corp. (TSXV: SAGA,OTC:SAGMF) (OTCQB: SAGMF) (FSE: 20H) ("SAGA" or the "Company"), a North American exploration company focused on critical mineral discoveries, is pleased to announce that, further to its news release dated April 14, 2026, it has closed the previously announced... Keep Reading...
Lithium Argentina to Release Second Quarter 2026 Results on August 11, 2026

Lithium Argentina to Release Second Quarter 2026 Results on August 11, 2026

Lithium Argentina AG ("Lithium Argentina" or the "Company") (TSX: LAR) (NYSE: LAR) will release its second quarter 2026 earnings results before market open on Tuesday, August 11, 2026. The Company will hold a webcast and conference call to discuss its second quarter 2026 results on Tuesday,... Keep Reading...
Homerun Resources Inc. Confirms Optimized +4N Purification Plant Pathway and Advances CAPEX Configurations for the SME High-Purity Silica

Homerun Resources Inc. Confirms Optimized +4N Purification Plant Pathway and Advances CAPEX Configurations for the SME High-Purity Silica

Homerun Resources Inc. (TSXV: HMR,OTC:HMRFF) (OTCQB: HMRFF) ("Homerun" or the "Company") is pleased to provide an update on Phase 2 of its Three-Phase Integrated Purification Platform for the Santa Maria Eterna ("SME") silica sand district in Belmonte, Bahia, Brazil, following completion of the... Keep Reading...
Homerun Resources Inc. Announces up to $15 Million Convertible Security Financing with Lind Partners Under Engagements with Benchmark/Stonex

Homerun Resources Inc. Announces up to $15 Million Convertible Security Financing with Lind Partners Under Engagements with Benchmark/Stonex

HIGHLIGHTSC$15 million financing with The Lind Partners: C$2.0 million initial tranche plus up to C$13.0 million of optional follow-on capital24-month initial tranche term with six-month repayment holiday and monthly repayments thereafterFixed conversion price of C$0.66 (10% premium to... Keep Reading...
Nevada Sunrise Closes First Tranche of Private Placement

Nevada Sunrise Closes First Tranche of Private Placement

Nevada Sunrise Metals Corporation (TSXV: NEV,OTC:NVSGF) (OTC Pink: NVSGF) ("Nevada Sunrise" or the "Company") announced today that it has closed the first tranche of its non-brokered private placement as announced on June 8, 2026 in the amount of 34,536,282 units (the "Units") at a price of... Keep Reading...

Interactive Chart

Latest Press Releases

Related News