Element 25 Limited

March 2024 Quarterly Report

Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to present its Quarterly Activities and Cash Flow Report.


Butcherbird Manganese Operations, Western Australia

  • Detailed design, planning and procurement commences for Stage 2 Expansion Project to expand Butcherbird manganese ore production to 1.1 million tonnes per annum in line with a Feasibility Study (FS) completed in January 20241.
  • Northern Australia Infrastructure Facility (NAIF) completes a strategic assessment of Butcherbird Stage 2 Expansion Project.
  • Expansion Project is now proceeding with the detailed due diligence phase of NAIF’s assessment process.
  • Manganese ore prices increasing, potentially in response to the South 32 Limited (S32) production disruption at Groote Eylandt. S32 is now estimating a repair timeline of ~12 months2.

Battery Grade High Purity Manganese (HPMSM) Development – Louisiana, USA

  • E25 progresses engineering development, permitting, logistics and project financing via offtake and funding agreements for HPMSM facility in USA.
  • Air Permit public meeting successfully completed paving the way for the formal issuance of the permit.

BUTCHERBIRD OPERATIONS

Expansion Plans

In January 2024, Element 25 Limited (E25, the Company) released a Feasibility Study (FS) on the proposed expansion of its 100%-owned Butcherbird Manganese Operations in Western Australia (WA) to target manganese concentrate production of 1.1 million tonnes per annum (Mtpa). The FS demonstrated strong economics with robust economic returns and rapid capital payback.

Expansion of the processing facility at Butcherbird is an important step in providing feedstock for the Company’s planned battery grade high purity manganese sulphate monohydrate (HPMSM) project to be built in Louisiana, USA in partnership with General Motors LLC and Stellantis NV3.

E25 is now, via a dedicated owners team supported by selected external contractors and consultants, advancing detailed design, planning and procurement activities for the Stage 2 expansion in parallel with financing.

Figure 1. Butcherbird Expansion Project Feasibility Study Summary4.

In parallel with expansion activities, the Company suspended Butcherbird’s current production operations, aiming to reduce operational cash outflows and re-focus resources and available cash on implementing the expansion plan outlined in the FS.

50,540mt of manganese concentrate was shipped on 27 January 2024. Approximately 15,000mt of manganese concentrate was subsequently transported to Port Hedland and will form part of a shipment scheduled to be loaded in early May 2024 (estimated). Stockpiles have now been depleted in line with care and maintenance activities on site, with haulage winding back and ultimately ceasing in early March 2024.

The current schedule anticipates operations to recommence in approximately 11 months following project financing being secured, when E25 plans to increase annual production to 1.1 million tonnes per annum of manganese oxide concentrate. Further detail and an updated schedule will be provided as the project team works through front-end engineering and design (FEED) activities.

Northern Australia Infrastructure Facility Strategic Assessment

During the quarter, the Northern Australia Infrastructure Facility (NAIF successfully completed a strategic assessment of the Butcherbird Stage 2 Expansion Project. The Expansion Project is now proceeding to the detailed due diligence phase of the NAIF assessment process.


Click here for the full ASX Release

This article includes content from Element 25 Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

E25:AU
The Conversation (0)
Miramar Resources

Goldfields Exploration Update

Miramar Resources Limited (ASX:M2R, “Miramar” or “the Company”) is pleased to provide an update on gold exploration activities within the Company’s strategic Eastern Goldfields project portfolio.

Keep reading...Show less
Manganese highlighted on periodic table.

Element 25 Increases MRE for Butcherbird Manganese Mine

Manganese-focused producer Element 25 (ASX:E25,OTCQX:ELMTF) provided an update to the mineral resource estimate for its Butcherbird manganese operations earlier this week.

The company recently completed an infill drilling program at the site, which targeted known mineralisation within granted mining lease M52/1074, where Butcherbird Stage 1 mining and processing operations are located.

Element 25 reported a 142 percent increase in measured and indicated resources, which now total 130 million tonnes at 10.23 percent manganese. Additionally, the site hosts a total resource of 274 million tonnes at 10 percent manganese, marking a 6 percent increase from its 263 million tonne resource estimate from April 2019.

Keep reading...Show less
Files labelled "funding," "projects" and "grants."

Element 25 Chosen for US$166 Million Grant from US Department of Energy

Element 25 (ASX:E25,OTCQX:ELMTF) has been selected to receive a US$166 million grant from the US Department of Energy, the company said in an announcement on Tuesday (September 24).

The funds will come from the Battery Materials Processing Grant Program, and will be used for the construction of the company’s proposed battery-grade high-purity manganese sulphate monohydrate (HPMSM) facility in Louisiana.

The Battery Materials Processing Grant Program has a US$3 billion budget to distribute grants for endeavours that will help ensure that the US has a viable battery materials processing industry.

Keep reading...Show less
Element 25 Limited

E25’s High-Purity Manganese Project Selected for US$166M Grant Under U.S. DoE Grant Program

Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to announce it has been selected for award negotiations for a US$166 million grant from the U.S. Department of Energy (DoE) under the Battery Materials Processing Grant Programme. This funding will support the construction of its proposed battery-grade high-purity manganese sulphate monohydrate (HPMSM) facility in Louisiana, USA. The grant award is in addition to the US$115 million already committed by offtake partners General Motors LLC (GM) and Stellantis N.V. (Stellantis).

Keep reading...Show less
Piece of manganese.

Trek Metals to Sell Pilbara-based Hendeka Manganese Project to AEFI

Trek Metals (ASX:TKM) announced on Tuesday (September 10) that it has signed a binding option and acquisition agreement to sell its Hendeka manganese project to private US-based company Advanced Energy Fuels (AEFI).

Under the agreement, AEFI has the option to acquire the project as part of a proposed US listing by paying AU$450,000 in cash; it will also issue Trek 8 million shares once it lists, or an amount of shares equal to not less than 20 percent of its total issued capital on a fully diluted basis. The maximum value of the shares will be AU$4 million.

In addition, AEFI will make certain payments, and will solely fund AU$2 million worth of exploration. Other conditions include an option fee of AU$50,000, AU$25,000 of which has already been paid by AEFI.

Keep reading...Show less
Manganese and hematite with an EU flag and text that says "5 Top Canadian Mining Stocks This Week."

Top 5 Canadian Mining Stocks This Week: Euro Manganese Climbs on EU Application

Welcome to the Investing News Network's weekly look at the best-performing Canadian mining stocks on the TSX and TSX Venture Exchange, starting with a round-up of Canadian and US data impacting the resource sector.

The S&P/TSX Venture Composite Index (INDEXTSI:JX) lost 10.12 points this week to close at 567.91. Meanwhile, the S&P/TSX Composite Index (INDEXTSI:OSPTX) was up by 60.1 points to finish at 23,346.18.

Statistics Canada shared real GDP figures on Friday (August 30) for the second quarter of 2024. The data shows the GDP saw a 0.5 percent quarterly gain in Q2, building on a 0.4 percent increase in the first quarter of the year.

Keep reading...Show less
Manganese ore.

Euro Manganese Enters 7 Year Offtake Deal with Wildcat Discovery

Euro Manganese (ASX:EMN,TSXV:EMN,OTCQB:EUMNF) has entered an offtake term sheet with Wildcat Discovery for the sale of high-purity manganese product from its Chvaletice project in the Czech Republic.

The deal, dated August 15 and announced on Monday (August 19), is non-binding and subject to Wildcat completing its planned cathode materials plant in the US. It has an initial term of seven years with the potential for renewal.

Euro Manganese said the news is a major milestone for itself, as well as the west's battery supply chain. President and CEO Dr. Matthew James added that the agreement accounts for a "significant percentage" of Chvaletice's output.

Keep reading...Show less

Latest Press Releases

Related News

×