Galena Makes Final Investment Decision for Abra

GALENA MINING LTD. (ASX:G1A) announces that Abra Mining Pty Limited ("AMPL"), the joint-venture company for the Abra Base Metals Project ("Abra" or the "Project") has made the final investment decision ("FID") to complete the full development of Abra, with first production of its high-value, high-grade lead-silver concentrate scheduled for the first quarter of 2023 calendar year. The FID decision has been made following the satisfaction of key conditions to draw in excess of US$30 million under the Taurus Debt Facilities.



HIGHLIGHTS:

  • Final investment decision (FID) made to complete full development of Abra Base Metals Project, with first production scheduled for Q1 CY2023
  • Underground decline development and on-site plant construction expected to commence Q3 CY2021 and Q4 CY2021 respectively
  • Remaining project works funded by US$110M Taurus Debt Facilities, final A$40M Toho equity tranche to be received, and existing cash
  • A$40M Toho equity plus US$30M initial drawdown under Taurus Debt Facilities expected to be received within 3-4 weeks
  • Continued strong support from Project partner and 40% off-taker, Toho Zinc of Japan
  • Managing Director role to transition to Tony James, a Mining Engineer with considerable senior underground development and operational experience

Galena is also pleased to announce that with Abra's accelerated progress towards production, its transitioning the Managing Director role to Anthony (Tony) James. Mr James is a Mining Engineer with considerable senior underground operational and development experience. The Company's current Managing Director, Alex Molyneux will remain a Director with responsibility for key corporate development initiatives and strategic relationships.


Managing Director, Alex Molyneux commented, "I'm ecstatic that everything is now in place and we've been able to make the final investment decision for Abra. Galena is now poised to join the ranks of high margin Australian producers, benefitting from buoyant base metals markets. I'd particularly like to thank our hard-working team who have achieved so many project milestones to get to this point and will soon be joined by approximately 260 more colleagues over the construction phase."


Commenting on the management transition, Chairman, Adrian Byass said, "As a board we've worked as a team to prioritise the needs of our flagship Abra Base Metals Project. Alex and Tony have worked hand-in-hand to date to achieve significant technical and corporate milestones, and with Abra moving to production I'm pleased we can make a transition that moves our senior mining engineering capability to the fore. We thank Alex for his significant contributions thus far and wish Tony every success going forward."


Abra Base Metals Project and schedule


Abra is poised to join the ranks of high margin Australian base metals producers. The Project is 17% complete as at 31 May 2021, based on A$27.4 million of Project works which were pulled forward and executed ahead of FID. Completed Project works include: construction and commissioning of a 280-unit mine site village; mining of the box-cut; box-cut ground support works; installation of production water infrastructure (bores, pumps and water reticulation); installation of site communications; and various site clearing, roadworks and civil works. As a result, Abra is largely prepared for the deployment of key contractors for the construction of the plant and ancillary infrastructure, and deployment of the underground mining contractor.


In addition, 90% of contracts (by value) covering the Project's remaining full development works are executed or awarded, further advancing on the completion of permitting, native title arrangements and offtake achieved in 2019. Among the key contracts, an engineering, procurement and construction contract has been executed with GR Engineering Services Limited for the supply of Abra's 1.2 million tonne per annum lead sulphide flotation process plant and ancillary infrastructure under a guaranteed maximum price arrangement to the value of approximately A$75 million. The underground mining services contract has been awarded to a tier one Australian mining contractor.


Under the current Project schedule, procurement of certain long-lead time items will take place immediately. The underground mining contractor is expected to initiate the portal and decline development in the 3rd quarter of 2021 calendar year and physical on-site plant construction is expected to commence in the 4th quarter of 2021 calendar year. First production of Abra's high- value, high-grade lead-silver concentrate is scheduled for the first quarter of 2023 calendar year.


Funding package


The FID decision has been made following the satisfaction of certain key conditions to draw in excess of US$30 million under the Taurus Debt Facilities (see Galena ASX announcement of 12 November 2020 for more information on the terms of the Taurus Debt Facilities).


Remaining project development works are funded by more than A$200 million of funds, sourced from:

  • US$110 million of Taurus Debt Facilities (equivalent to A$142 million at current exchange rates), made up of:
    • US$100 million Project Finance Facility; and
    • US$10 million Cost Overrun Facility;
  • A$40 million final equity investment tranche from Galena's project partner, Toho Zinc Co., Ltd. ("Toho"); and
  • the Company's existing cash resources (A$20.0 million as at 31 May 2021).
Toho has also confirmed their final A$40 million AMPL equity investment tranche is expected to be contributed within the next three to four weeks. Toho has been a strong, flexible and supportive partner for the Abra Project, since its overall A$90 million investment was implemented in April 2019, and the A$50 million investment received to date has been used to prepare the Abra site and advance early project works. Toho is the leading producer of lead in Japan and has entered into a binding offtake agreement to purchase 40% of Abra's production for an initial period of 10- years from the commencement of production.



The Company has also made an initial drawdown request under the Project Finance Facility of US$30 million, which is expected to be received by the end of June. The Taurus Debt Facilities are secured against Abra Project assets and over the shares that each of Galena and Toho own in AMPL, and drawdowns remain subject to satisfaction of customary conditions precedent.


Management transition


With Abra's accelerated progress towards production, Galena is transitioning its Managing Director role to currently serving Non-Executive Director Anthony (Tony) James. Mr James is a Mining Engineer with considerable senior underground operational and development experience. He joined Galena's board in October 2018 and has been actively involved in Abra Project development initiatives, having also served on the board of directors of AMPL since the establishment of the active joint-venture with Toho in 2019.


The Company's current Managing Director, Alex Molyneux will remain a Director with responsibility for corporate development initiatives and strategic relationships. Since commencing as Managing Director in August 2018, Galena made a full transition from exploration to a company capable of building and operating a successful base metals mine. Under his guidance, Abra passed through: outstanding pre-Feasibility and Feasibility Studies; completed permitting, native title arrangements and offtake; executed major project contracts; and completed 17% of construction activities. However, Mr Molyneux's key contribution has been to assemble approximately A$300 million in development funding from a mixture of strategic equity (Toho Investment Agreement and the investment in Galena by Mr Timothy Andrew Roberts' Warburton Portfolio Pty Ltd), debt (Taurus Debt Facilities) and public equity.


Mr James has been actively involved in both technical and corporate initiatives for the Company since the second half of 2018. Prior to Galena, Mr James' experience includes having previously worked as Managing Director of various ASX-listed companies, including: Carbine Resources; Atherton Resources; and Mutiny Gold. At Atherton Resources he achieved a favourable outcome for shareholders which culminated in a cash takeover by Auctus Minerals. At Mutiny Gold he led the implementation of a revised development strategy for the Deflector copper-gold deposit in WA prior to the merger of that company with Doray Minerals. Currently, Mr James serves as a Non- Executive Director of Apollo Consolidated, Wiluna Mining and Medallion Metals. Prior to Mr James' Managing Director and Non-Executive Director roles, he held a number of senior executive positions with international gold producer Alacer Gold, including President of its Australian operations. He also played a key role in Avoca Resources' initial growth and success, leading the feasibility, development and operation of its Higginsville Gold Mine.



Click here for the full press release.

G1A:AU
The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Boab Metals

Boab Metals Secures Funding for Sorby Hills Project: A Promising Investment Opportunity

Description

In a game-changing move, Boab Metals (ASX:BML) has locked in crucial funding for its Sorby Hills Project, a significant lead-silver resource nestled in Australia. This financial boost not only fortifies the company's position but also lessens its dependence on equity markets. It's a pivotal stride towards the project's Final Investment Decision (FID), which is on the horizon for late 2025.

Keep reading...Show less
Silver bars, silver bull and stock chart.

Silver Price Forecast: Top Trends for the Silver Market in 2025

The silver price reached highs not seen since 2012 this past year, supported by an ongoing deficit and increasing interest from investors as geopolitical concerns prompted safe-haven buying.

The white metal reached its highest point for the year in October, breaking through US$34 per ounce on the back of a shifting post-pandemic landscape and geopolitical tensions. However, Donald Trump's victory in the US presidential election just a few weeks later buoyed bond yields and the US dollar while weighing on silver and gold.

What will 2025 hold for silver? As the new year approaches, investors are closely watching how Trump's policies and actions could impact the precious metal, along with supply and demand trends in the space.

Keep reading...Show less

First Majestic Provides Update Regarding Gatos Silver's Joint Venture with Dowa Metals & Mining Co., Ltd.

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") announces that Gatos Silver, Inc. ("Gatos") has advised the Company that it has amended and restated its agreements (the "Amended Agreements") with Dowa Metals & Mining Co., Ltd. ("Dowa") regarding the Los Gatos Joint Venture (the "LGJV"). The Amended Agreements, which become effective on January 1, 2025, expand Gatos' management rights within the LGJV and allow for the financial statements of the LGJV to be fully consolidated. For copies of the Amended Agreements, please see the Form 8-K filed by Gatos under its EDGAR profile at www.sec.govedgar. The Amended Agreements do not affect the respective ownership interests of Gatos and Dowa in the LGJV, which remain unchanged at 70% and 30%, respectively. Concurrent with this news release, the Company has filed a material change report dated December 19, 2024 (the "December Material Change Report") under its SEDAR+ profile at www.sedarplus.com, with further details of the Amended Agreements.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Silver bar beside several silver coins.

Silver Price 2024 Year-End Review

The silver price put on a strong performance in 2024, hitting highs not seen in over a decade.

Despite some volatility, factors like increasing industrial demand, safe-haven buying from investors and weakening mining supply all came together during the year to support gains in the price.

All told, silver is up nearly 35 percent since the start of 2024, outperforming gold's 32 percent gain.

Keep reading...Show less

Guanaceví Mill Operating at Full Capacity After Trunnion Installation

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to announce the successful fabrication and installation of its primary ball mill trunnion at the Guanaceví mine.

Guanaceví processing resumed to full capacity this week after the trunnion failure in August (see news release dated August 19 here ). After a 15-week period of operating at a reduced capacity averaging 620 tonnes per day (tpd), the newly fabricated trunnion was installed on November 30 with alignment testing occurring over the ensuing two weeks, restoring the plant to its designed capacity of 1,200 tpd. The total cost of fabrication and installation was just over US$400,000.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Silver bar and metal.

5 Best-performing Canadian Silver Stocks of 2024

Silver saw strong gains in 2024, breaching US$32 per ounce in H1 and then US$34 in October.

Silver’s dual function as a monetary and industrial metal offers great upside. Demand from energy transition sectors, especially for use in the production of solar panels, has created tight supply-and-demand forces.

Demand is already outpacing mine supply, making for a positive situation for silver-producing companies.

Keep reading...Show less