Activities Report for Quarter Ended 30 June 2021

Highlights

  • Final investment decision (FID) made to complete full development of Abra Mine, with first production scheduled for Q1 CY2023
  • Cash balance as at Quarter-end A$96.2M following final A$40M investment tranche received from Abra Joint Venture partner, Toho Zinc of Japan, and first US$30M drawn under the Taurus Project Debt Facilities
  • Early stage / enabling construction works continued during the Quarter with a further 2% of the Project being completed, taking cumulative Project completion to 17%
  • Achievement of 2020 Abra drilling objectives announced together with updated Mineral Resource estimate
  • Managing Director role transitioned to Mr Tony James, a Mining Engineer with considerable project development and operational experience in Western Australia

GALENA MINING LTD. ("Galena" or the "Company") (ASX: G1A) reports on its activities for the quarter ending 30 June 2021 (the "Quarter"), largely focused on advancing its 60%-owned Abra Base Metals Project ("Abra" or the "Project") located in the Gascoyne region of Western Australia.

Click here for the full press release

G1A:AU
The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Klondike Silver Announces Private Placement

Klondike Silver Announces Private Placement

Klondike Silver Corp. (the “Company”) (TSX.V: KS) The Company announces that it is raising up to $1,500,000 through a non-brokered private placement (the “Offering”) of up to 30,000,000 units at a price of $0.05 per unit. Each unit will consist of one common share and one share purchase warrant, with each warrant exercisable for a period of 5 years from the closing at a price of $0.05 per share in year one and two then $0.08 per share in years three, four and five. All Units are subject to a four-month hold period from the date of issuance. Commissions may be paid on a portion of the funds raised. The Offering is subject to TSX Venture Exchange ("TSXV") final acceptance.

Keep reading...Show less

Endeavour Silver Announces First Drawdown on The Terronera Senior Secured Debt Facility

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to announce the first drawdown of $60 million of the $120 million senior secured debt facility (the " Debt Facility ") for the development of the Terronera Mine in Jalisco state, Mexico. The debt facility is provided by Société Générale and ING Bank N.V. and closed last year (see news release dated October 10, 2023 ). All references to dollars ($) in this news release are in United States dollars.

Construction of the Terronera mine is well underway and remains on track and has satisfied all conditions precedent to first draw. Key terms of the Debt Facility remain consistent with those previously announced in the Company's news release dated April 18, 2023 and the hedge contract terms have now been executed, further reducing financial risk in the project. The key terms of these contracts are as follows:

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Pan American Silver to Announce First Quarter 2024 Unaudited Results and Host Annual General and Special Meeting of Shareholders on May 8

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) (" Pan American ") will announce its unaudited results for the first quarter of 2024 after market close on Wednesday, May 8, 2024. Pan American will also be holding its Annual General and Special Meeting of shareholders (the "Shareholders Meeting") the same day at 3:00 pm PT.

First Quarter 2024 Unaudited Results Conference Call and Webcast

News Provided by Business Wire via QuoteMedia

Keep reading...Show less

Endeavour Silver Delivers Strong Production in Q1 2024

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to report first quarter 2024 production of 1,460,006 silver ounces (oz) and 10,133 gold oz, for silver equivalent (1) ("AgEq") production of 2.3 million oz.

"Across our portfolio, the operations performed largely in-line with our expectations to deliver our annual production guidance of 8.1- 8.8 million silver equivalent ounces in 2024," commented Dan Dickson, Chief Executive Officer. "The infrastructure upgrades in pumping and ventilation have stabilized production at Guanacevi, and the impact from these improvements is being realized by our strong start to the year. Gold and silver prices have strengthened considerably, which will improve future revenues. I look forward to building upon the success of this quarter."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Rows of silver bars with two lying on top of them.

ASX Silver Stocks: 5 Biggest Companies in 2024

As a precious metal, silver is often compared to gold, and similarly holds an important role in the production of jewellery and as a safe-haven investment. However, silver also has increasing industrial uses.

In addition to its applications in jewellery and silverware, the white metal is becoming important for its use in the energy transition, specifically for its conductive capacity, which makes it particularly useful in the production of photovoltaic panels. It also has a wide array of uses in the production of electronics, automobiles, medicine and photography.

Despite its important role, silver is still largely a secondary metal, being mined as a by-product of lead, gold, zinc and copper. There are, however, several Australian companies that have put silver first.

Keep reading...Show less
Fireweed Metals (TSXV:FWZ)

Fireweed Metals


Keep reading...Show less
{{ sections }}

Latest Press Releases

Related News

Ă—