Coelacanth Energy Inc. Announces Operations Update

Coelacanth Energy Inc. Announces Operations Update

Coelacanth Energy Inc. (TSXV: CEI) ("Coelacanth" or the "Company") announces that it has completed and tested 4 additional wells at its Two Rivers East Project including 3 Lower Montney Wells and 1 Upper Montney well on the 5-19 pad.

LOWER MONTNEY

The 3 new Lower Montney wells (F5-19, G5-19, H5-19) were drilled with an average horizontal length of 3,285 metres and completed with approximately 2.5 tons of sand per horizontal metre. The wells were placed on test for clean-up for an average of 7 days until a stabilized rate was achieved. The test rates noted below are based on the final 24 hours of each test.

The average rate achieved for the 3 new Lower Montney wells was 1,624 boepd per well comprised of 989 bbls per day of 41 API light sweet oil and 3.8 mmcf/d of liquids-rich gas. The rates per well are outlined in the table below:

Well Oil - bbls/d Gas - mmcf/d Total - boe/d % Light Oil
F5-19 1,061 3.2 1,595 67
G5-19 900 4.0 1,573 57
H5-19 1,007 4.2 1,703 59
Average 989 3.8 1,624 61

 

The overall rates and more specifically the oil rates were materially higher than the previous 3 wells on the pad (C5-19, D5-19 and E5-19) that achieved an average test rate of 1,338 boepd including 729 bbls/d of light oil and 3.7 mmcf/d of gas (see press release dated January 18, 2024 for more information including per well test results and initial production rates). Although the 3 new Lower Montney wells were drilled with slightly longer lateral lengths and the completion design was slightly modified in an attempt to increase the overall oil production, the tests have exceeded expectations.

UPPER MONTNEY

The Upper Montney well (B5-19) was drilled with a horizontal length of 2,647 metres and completed with approximately 2.5 tons of sand per horizontal metre. The well flowed on cleanup for 6 days and achieved a rate of 1,136 boepd comprised of 271 bbls/d of 40 API light oil and 5.2 mmcf/d of liquids-rich gas. In comparison to the Lower Montney Wells noted above, the B5-19 was 20% shorter in horizontal length and had 42% less frac stages leaving room for future optimization.

Management is very pleased with the B5-19 test result particularly the potential impact on Coelacanth's development inventory over its 150-section contiguous Montney land block. The Upper Montney is extensively mapped over Coelacanth's lands, but the impact of this test is amplified given it is a 10-mile step-out from Coelacanth's Two Rivers West project and 5 miles from the nearest competitor well.

INFRASTRUCTURE & TAKEAWAY

As previously disclosed, Coelacanth has secured long-term takeaway and processing for up to 60 mmcf/d of gas and is in process of constructing the required facilities and pipelines to handle the 5-19 and subsequent pads. Initial testing and start-up of the facility is anticipated for late April 2025.

Overall, Coelacanth believes this was a very significant second step in its development that has materially expanded the development fairway of the Upper Montney as well as increased the productivity of the Lower Montney that was already established as productive.

FOR FURTHER INFORMATION PLEASE CONTACT:

Coelacanth Energy Inc.
2110, 530 - 8th Ave SW
Calgary, Alberta T2P 3S8
Phone: 403-705-4525
www.coelacanth.ca

Mr. Robert J. Zakresky
President and Chief Executive Officer

Mr. Nolan Chicoine
Vice President, Finance and Chief Financial Officer

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

Oil and Gas Terms

The Company uses the following frequently recurring oil and gas industry terms in the news release:

Liquids
Bbls
Barrels
Bbls/d  Barrels per day
NGLs  Natural gas liquids (includes condensate, pentane, butane, propane, and ethane)
   
Natural Gas
Mcf
Thousands of cubic feet
Mcf/d  Thousands of cubic feet per day
MMcf/d  Millions of cubic feet per day
   
Oil Equivalent
Boe  Barrels of oil equivalent
Boe/d  Barrels of oil equivalent per day

 

Disclosure provided herein in respect of a boe may be misleading, particularly if used in isolation. A boe conversion rate of six thousand cubic feet of natural gas to one barrel of oil equivalent has been used for the calculation of boe amounts in the news release. This boe conversion rate is based on an energy equivalency conversion method primarily applicable at the burner tip and does not represent a value equivalency at the wellhead.

Product Types

The Company uses the following references to sales volumes in the news release:

Natural gas refers to shale gas
Oil refers to tight oil
NGLs refers to butane, propane and pentanes combined
Liquids refers to tight oil and NGLs combined
Oil equivalent refers to the total oil equivalent of shale gas, tight oil, and NGLs combined, using the conversion rate of six thousand cubic feet of shale gas to one barrel of oil equivalent as described above.

Forward-Looking Information

This news release contains forward-looking statements and forward-looking information within the meaning of applicable securities laws. The use of any of the words "expect", "anticipate", "continue", "estimate", "may", "will", "should", "believe", "intends", "forecast", "plans", "guidance" and similar expressions are intended to identify forward-looking statements or information.

More particularly and without limitation, this document contains forward-looking statements and information relating to the Company's oil, NGLs and natural gas production and capital programs. The forward-looking statements and information are based on certain key expectations and assumptions made by the Company, including expectations and assumptions relating to prevailing commodity prices and exchange rates, applicable royalty rates and tax laws, future well production rates, the performance of existing wells, the success of drilling new wells, the availability of capital to undertake planned activities and the availability and cost of labor and services.

Although the Company believes that the expectations reflected in such forward-looking statements and information are reasonable, it can give no assurance that such expectations will prove to be correct. Since forward-looking statements and information address future events and conditions, by their very nature they involve inherent risks and uncertainties. Actual results may differ materially from those currently anticipated due to a number of factors and risks. These include, but are not limited to, the risks associated with the oil and gas industry in general such as operational risks in development, exploration and production, delays or changes in plans with respect to exploration or development projects or capital expenditures, the uncertainty of estimates and projections relating to production rates, costs and expenses, commodity price and exchange rate fluctuations, marketing and transportation, environmental risks, competition, the ability to access sufficient capital from internal and external sources and changes in tax, royalty and environmental legislation. The forward-looking statements and information contained in this document are made as of the date hereof for the purpose of providing the readers with the Company's expectations for the coming year. The forward-looking statements and information may not be appropriate for other purposes. The Company undertakes no obligation to update publicly or revise any forward-looking statements or information, whether as a result of new information, future events or otherwise, unless so required by applicable securities laws.

Test Results and Initial Production Rates

The B5-19 Upper Montney well was production tested for 6.3 days and produced at an average rate of 92 bbl/d oil and 2,100 mcf/d gas (net of load fluid and energizing fluid) over that period which includes the initial cleanup where only load water was being recovered. At the end of the test, flowing wellhead pressure and production rates were stable.

The F5-19 Lower Montney well was production tested for 4.9 days and produced at an average rate of 728 bbl/d oil and 1,607 mcf/d gas (net of load fluid and energizing fluid) over that period which includes the initial cleanup where only load water was being recovered. At the end of the test, flowing wellhead pressure and production rates were stable.

The G5-19 Lower Montney well was production tested for 7.1 days and produced at an average rate of 415 bbl/d oil and 1,489 mcf/d gas (net of load fluid and energizing fluid) over that period which includes the initial cleanup where only load water was being recovered. At the end of the test, flowing wellhead pressure and production rates were stable.

The H5-19 Basal Montney well was production tested for 8.1 days and produced at an average rate of 411 bbl/d oil and 1,166 mcf/d gas (net of load fluid and energizing fluid) over that period which includes the initial cleanup where only load water was being recovered. At the end of the test, flowing wellhead pressure was stable and production was starting to decline.

A pressure transient analysis or well-test interpretation has not been carried out on these four wells and thus certain of the test results provided herein should be considered to be preliminary until such analysis or interpretation has been completed. Test results and initial production rates disclosed herein, particularly those short in duration, may not necessarily be indicative of long-term performance or of ultimate recovery.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/232259

News Provided by Newsfile via QuoteMedia

CEI:CC
Coelacanth Energy

Coelacanth Energy Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Coelacanth Energy (TSXV:CEI)

Coelacanth Energy

Light oil & Natural gas exploration and production in the prolific Montney region in British Columbia

Light oil & Natural gas exploration and production in the prolific Montney region in British Columbia Keep Reading...
Coelacanth Announces Q3 2025 Financial and Operating Results

Coelacanth Announces Q3 2025 Financial and Operating Results

Coelacanth Energy Inc. (TSXV: CEI,OTC:CEIEF) ("Coelacanth" or the "Company") is pleased to announce its financial and operating results for the three and nine months ended September 30, 2025. All dollar figures are Canadian dollars unless otherwise noted. HIGHLIGHTS Increased oil and natural gas... Keep Reading...
Coelacanth Energy Inc. Announces Increased Bank Credit Facility and Provides Operations Update

Coelacanth Energy Inc. Announces Increased Bank Credit Facility and Provides Operations Update

Coelacanth Energy Inc. (TSXV: CEI,OTC:CEIEF) ("Coelacanth" or the "Company") is pleased to provide the following update: BANK CREDIT FACILITYCoelacanth has signed an agreement to increase its bank credit facility from $52 million to $80 million with closing expected in mid-November. The Company... Keep Reading...
Coelacanth Energy Inc. Engages ICP Securities Inc. for Automated Market Making Services

Coelacanth Energy Inc. Engages ICP Securities Inc. for Automated Market Making Services

Coelacanth Energy Inc. (TSXV: CEI,OTC:CEIEF) ("Coelacanth" or the "Company") is pleased to announce that it has engaged the services of ICP Securities Inc. ("ICP") to provide automated market making services, including use of its proprietary algorithm, ICP Premiumâ„¢, in compliance with the... Keep Reading...
Coelacanth Energy Inc. Announces Operations Update, Revised Reserve Report and Initial Resource Report

Coelacanth Energy Inc. Announces Operations Update, Revised Reserve Report and Initial Resource Report

Coelacanth Energy Inc. (TSXV: CEI,OTC:CEIEF) ("Coelacanth" or the "Company") has provided an Operations Update, Reserve Report, and Resource Report. OPERATIONS UPDATE Coelacanth completed and commissioned its new battery facility in early June and subsequently started to systematically place the... Keep Reading...
Coelacanth Announces Q2 2025 Financial and Operating Results

Coelacanth Announces Q2 2025 Financial and Operating Results

Coelacanth Energy Inc. (TSXV: CEI,OTC:CEIEF) ("Coelacanth" or the "Company") is pleased to announce its financial and operating results for the three and six months ended June 30, 2025. All dollar figures are Canadian dollars unless otherwise noted. FINANCIAL RESULTS Three Months Ended Six... Keep Reading...
Angkor Resources Confirms Mussel Basin Target on Block VIII Oil & Gas License, Cambodia

Angkor Resources Confirms Mussel Basin Target on Block VIII Oil & Gas License, Cambodia

(TheNewswire) GRANDE PRAIRIE, ALBERTA TheNewswire - (Dec. 4, 2025): Angkor Resources Corp. (TSXV: ANK,OTC:ANKOF) ("ANGKOR" OR "THE COMPANY") announces Mussel Basin as a fourth target for exploratory drilling based on data processing of the seismic program. After identifying three significant... Keep Reading...
Charbone tiendra un webinaire d'information sur l'entreprise le 16 decembre et engage Red Cloud comme teneur de marche

Charbone tiendra un webinaire d'information sur l'entreprise le 16 decembre et engage Red Cloud comme teneur de marche

(TheNewswire) Brossard, Quebec, le 4 décembre 2025 TheNewswire - CORPORATION CHARBONE (TSXV: CH,OTC:CHHYF; OTCQB: CHHYF; FSE: K47) (« CHARBONE » ou la « Société »), un producteur et distributeur nord-américain spécialisé dans l'hydrogène propre Ultra Haute Pureté (« UHP ») et les gaz industriels... Keep Reading...
Charbone to Host Corporate Update Webinar December 16th and Engages Red Cloud as Market Maker

Charbone to Host Corporate Update Webinar December 16th and Engages Red Cloud as Market Maker

(TheNewswire) Brossard, Quebec, December 4 2025 TheNewswire - CHARBONE CORPORATION (TSXV: CH,OTC:CHHYF; OTCQB: CHHYF; FSE: K47) (" CHARBONE " or the " Company "), a North American producer and distributor specializing in clean Ultra High Purity (" UHP ") hydrogen and strategic industrial gases,... Keep Reading...
Oil barrels and pumpjack with stock market graph overlay.

Rising US-Venezuela Tensions, CPC Shutdown Push Oil Prices Higher

Oil prices climbed higher on Monday (December 1) as an escalation in US-Venezuela tensions reached a fever pitch, offsetting weeks of losses driven by oversupply expectations. The shift also came after the Caspian Pipeline Consortium (CPC), a key transit route that carries about 1 percent of... Keep Reading...
Map with a red pin marking a location in northern Alberta, Canada.

Canada-Alberta Pact: Boosting Oil Exports and Clean Energy

Canada and Alberta have sealed a wide-ranging deal that links deep emissions cuts with a long-term push to grow oil and gas output through new export pipelines and fast-track clean energy infrastructure.Prime Minister Mark Carney and Alberta Premier Danielle Smith signed the memorandum of... Keep Reading...
Coelacanth Energy

Coelacanth Energy Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News