Baru Gold Advances Production Readiness -- Designs, Prepares for Construction of Automated Gold Production Plant

f

(TheNewswire)

September 30, 2025 TheNewswire - VANCOUVER, B.C. - Baru Gold Corp. (BARU: TSX.V | BARUF: OTCQB) ("Baru") and its subsidiary PT. Tambang Mas Sangihe ("TMS" or the "Company") are pleased to report progress in advancing its production readiness at the Sangihe Gold Project while awaiting approval for the upgrade to production operations.

The Company has successfully concluded a competitive bid and tender for the design and construction of an Electrowinning Elution Column Plant .

An Electrowinning Elution Column Plant is a modern gold recovery facility that automates the extraction of gold from leach solutions. Gold adsorbed onto resin is first separated in an elution column to produce a concentrated gold-bearing solution, which then passes through electrowinning cells where an electrical current deposits pure metallic gold onto cathodes. The process is fully automated, highly efficient, environmentally friendly, and delivers excellent recovery rates.

A leading Indonesian engineering and construction company was awarded the contract to design and assemble the plant, which will be manufactured locally in Indonesia. Producing the plant domestically supports the local economy while reducing costs and delivery times. The electrowinning system is inexpensive costing only a few hundred thousand dollars and can become fully operational within several months.

This strategic decision was led by Baru's Chief Operating Officer, Sri Darmawan , who brings over 30 years of experience working with some of the largest gold mining companies in North Sulawesi. His extensive knowledge of regional conditions, proven technologies for similar ore bodies, and understanding of local contractor capabilities was instrumental in selecting a cost-effective, high-quality solution.

Mr. Terrence Filbert, CEO of Baru Gold, commented, " We are making excellent progress as we prepare for the transition to production operations. While awaiting the remaining approvals for Production Operations, we are effectively using this time to lay the groundwork for rapid implementation . I am preparing for operational readiness while conserving capital, ensuring that once the necessary approvals are granted, the Company can commence gold production without delay.


Click Image To View Full Size
Finalized design of the planned Electrowinning Elution Column Plant with heap leach (HLP) in background. Forklift shown for scale

Key Highlights of the Production Plant Design

  • Local Supply Chain: Plant construction and manufacturing will be done within Indonesia, enabling short construction and delivery timeframes while supporting local industries and economy.
  • Scalable Output: Initial capacity to support production of 1,500 ounces of gold per month, with the ability to double output to 3,000 ounces.
  • Modular Growth: Each plant is modular in design, meaning individual plants can be expanded to increase output as needed.
  • Expandable Footprint: Multiple plants can be built across the mining area, giving Baru the ability to rapidly scale production capacity in step with ore extraction.
  • Operational Efficiency: The Modular Growth and Expandable Footprint design minimize upfront capital costs and allows for streamlined installation and commissioning.
  • Lower Operating Expenses: Electrowinning uses electricity to recover gold directly, eliminating the need for costly reagents.
  • Environmentally Friendly: By avoiding reagent-heavy processes, electrowinning reduces chemical consumption and waste generation, minimizing environmental impacts.

ABOUT SANGIHE GOLD PROJECT

The Sangihe Gold Project ("Sangihe") is located on the Indonesian island of Sangihe, off the northern coast of Sulawesi with a gold bearing area of approximately 25,000 ha. Sangihe has an existing National Instrument 43-101 report suitable for mining planning and production schedules for an area within the 65-ha area targeted for initial production. See the Company's " Independent Technical Report on the Updated Mineral Resource Estimates of the Binebase and Bawone Deposits, Sangihe Project, North Sulawesi, Indonesia " ( Mining Associates Pty Ltd , February 1st, 2025). Only 10% of the gold bearing area has been explored.

Readers are cautioned that mineral resources that are not mineral reserves do not have demonstrated economic viability. The Company intends to proceed to production without the benefit of first establishing mineral reserves supported by a feasibility study. The Company cautions readers that the any production decision made by the Company will not be based on a NI 43-101 feasibility study of mineral reserves that demonstrates economic and technical viability and as such, there may be involved increased uncertainty and various technological and economic risks

The Company's 70-percent interest in the Sangihe-mineral-tenement Contract of Work ("CoW") is held through PT. Tambang Mas Sangihe ("TMS"). The remaining 30-percent interest in TMS is held by other Indonesian corporations. The term of the Sangihe CoW agreement is 30 years upon commencement of the production phase of the project. Baru has met all the requirements of the Indonesian government and has been granted its environmental permit.

ABOUT Baru Gold CORP.

Baru Gold Corporation is a dynamic junior gold developer with NI 43-101 gold resources in Indonesia, one of the top ten gold producing countries in the world. Based in Indonesia and North America, Baru's team boasts extensive experience in starting and operating small-scale gold assets.

On behalf of the Board of Directors

Baru Gold CORP.

"Terry Filbert"

Terry Filbert

Chairman and Chief Executive Officer

info@barugold.com

604-684-2183

For investor contacts more information, please contact:

Kevin Shum

Investor Relations

kevin@jeminicapital.com

647-725-3888 ext. 702

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Certain statements in this News Release, which are not historical in nature, constitute "forward looking statements" within the meaning of that phrase under applicable Canadian securities law. These statements include, but are not limited to, statements or information concerning future work programs, results and timing of any work programs, the Company's performance or events as of the date hereof. These statements reflect management's current assumptions and expectations and by their nature are subject to certain underlying assumptions, known and unknown risks and uncertainties and other factors which may cause actual results, performance or events to be materially different from those expressed or implied by such forward looking statements. Those risks include the interpretation of drill results; the geology, grade and continuity of mineral deposits; the possibility that future exploration, development or mining results will not be consistent with our expectations; commodity and currency price fluctuation; failure to obtain adequate financing; regulatory, recovery rates, refinery costs, and other relevant conversion factors, permitting and licensing risks; general market and mining exploration risks and production and economic risks related to design and engineering, manufacturing, technological processes and test procedures and the risk that the project's output will not be salable at a price that will cover the project's operating and maintenance costs. Forward-looking statements should not be construed as investment advice. Readers should perform a detailed, independent investigation and analysis of the Company and are encouraged to seek independent professional advice before making any investment decision. Accordingly, readers should not place undue reliance on any forward-looking statement. Except as required by applicable securities laws, the Company disclaims any obligation to update or revise any forward looking statements to reflect events or changes in circumstances that occur after the date hereof.

Copyright (c) 2025 TheNewswire - All rights reserved.

News Provided by TheNewsWire via QuoteMedia

BARU:CC
The Conversation (0)
Centurion Announces Fully Subscribed $1,000,000 Private Placement

Centurion Announces Fully Subscribed $1,000,000 Private Placement

Centurion Minerals Ltd. (TSXV: CTN) ("Centurion", or the "Company") wishes to announce it has arranged a (fully subscribed) non-brokered private placement offering of 19,047,619 Units priced at $0.0525 for proceeds of $1,000,000.Each Unit consists of one common share and one common share... Keep Reading...
TomaGold Commences Audio-Frequency Magnetotelluric  Survey at its Berrigan Mine Project

TomaGold Commences Audio-Frequency Magnetotelluric Survey at its Berrigan Mine Project

Highlights Advanced AMT Survey Designed to Unlock District-Scale Discovery Potential The survey aims to better define the district's structural architecture, identify deep conductive corridors associated with mineralized systems such as those observed in the Main and Deep Zones at the Berrigan... Keep Reading...
Armory Mining Announces Debt Settlement

Armory Mining Announces Debt Settlement

(TheNewswire) Vancouver, B.C. TheNewswire - June 19, 2026 Armory Mining Corp. (CSE: ARMY) (OTC: RMRYF) (FRA: 2JS) (the "Company" or "Armory") a resource exploration company focused on the discovery and development of minerals critical to the energy, security and defence sectors, announces its... Keep Reading...
Goldgroup Commences 24,000 M Diamond Drilling Program at San Francisco Gold Project

Goldgroup Commences 24,000 M Diamond Drilling Program at San Francisco Gold Project

Key objectives are to update the resource model, optimize the mine plan, provide new structural data and other technical information in preparation for re-starting mining operationsGoldgroup Mining Inc. (TSXV: GGA,OTC:GGAZF) (OTCQX: GGAZF) (FSE: 55G0) ("Goldgroup" or the "Company") is pleased to... Keep Reading...
Brixton Metals Commences Drilling for Maiden Tailings Mineral Resource Estimate at the Langis Silver Project

Brixton Metals Commences Drilling for Maiden Tailings Mineral Resource Estimate at the Langis Silver Project

Brixton Metals Corporation (TSX-V: BBB, OTCQX: BBBXF) (the "Company" or "Brixton") is pleased to report that it has commenced a dedicated sonic-drilling campaign to define a potential initial Mineral Resource Estimate (MRE) from the historic tailings at its wholly owned Langis Silver Project,... Keep Reading...
Heliostar Set to Expand La Colorada with Strong Drill Results and Key Permits

Heliostar Set to Expand La Colorada with Strong Drill Results and Key Permits

HIGHLIGHTS: Veta Madre drilling:10.9 m grading 22.1 g/t gold from 187.7 m, including 1.3 m grading 174 g/t gold40.8 m grading 2.23 g/t gold from 51.3 m, including 17.45 m grading 4.55 g/t gold147.2 m grading 0.70 g/t gold from 32.65 m, including 10.7 m grading 1.98 g/t gold20.65 m grading 3.35... Keep Reading...

Interactive Chart

Latest Press Releases

Related News