
April 27, 2022
GALENA MINING LTDLTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ending 31 March 2022 (the “Quarter”), primarily focused on construction of its 60%-owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.
HIGHLIGHTS:
- Abra Project 58% complete at end of the March Quarter (19% of Abra construction works were completed during the March Quarter). Project focus remains on underground access to the Abra orebody and completion of the processing plant and power station.
- Underground development achieved 694m advance during the Quarter remaining ahead of schedule with the decline reaching 1,395mRL. The decline is 82m above the orebody and 155m below the surface.
- Overall processing plant construction has reached 61% complete. Plant engineering and drafting work is 95% complete and site construction work is 35% complete.
- Contracts have been awarded for the remaining non-processing surface infrastructure work representing only 10% of the remaining project capex of $97.8M.
- Power supply company Contract Power have commenced site works associated with the Abra power station (build, own, operate contract).
- US$35M additional debt drawdown was completed under the Taurus Debt Facilities, leaving US$45M remaining undrawn.
- Cash balance at Quarter-end A$60.0M.
ABRA BASE METALS MINE (60%-OWNED)
Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL”), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.
Abra is fully permitted and under construction. First production of its high-value, high-grade lead- silver concentrate is currently scheduled for the first quarter of 2023 calendar-year.
Project construction / development
During the Quarter Abra Project construction works continued, passing the half-way to completion mark as the Quarter progressed.
Abra construction works conducted during the Quarter were comprised of site civil and earthworks, underground mine development, processing plant construction and ongoing front- end engineering design and procurement, including:
- Underground mining – During the Quarter, underground development continued to progress ahead of schedule, with a further 694 metres of development being completed. As at Quarter-end, total development reached 1,134 metres consisting of 885 metres of decline development and 249 metres of other lateral development. The decline reached 1,395mRL, 82 metres above the Abra orebody and 155 metres below the surface. During the Quarter the first raise bore hole (4.5m) was successfully completed for development of the mine’s primary ventilation infrastructure. The ventilation shaft is one of 3 surface holes that will be completed to provide underground ventilation as the mine progresses.
Click here for the full ASX Release
This article includes content from GALENA MINING LTD. , licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.G1A:AU
INN Article Notification
The Conversation (0)
12 September 2022
Galena Mining
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
07 May
Record Silver Price a Key Q1 Tailwind for Miners
Following an unprecedented first quarter that saw silver prices break into triple digits before sharply correcting, the sector’s top producers registered massive cash generation and bolstered balance sheets. Silver achieved a historic milestone early in the first quarter, surging past US$100 an... Keep Reading...
05 May
Silver Stocks: 5 Biggest Silver-mining Companies in 2026
Silver mining companies are being supported by a silver price bull run in 2026. After climbing through 2025, silver broke its all-time high set in 1980 in October before reaching a new high of US$121.62 per ounce on January 29.The factors driving the metal's rise remain, most notably tightening... Keep Reading...
30 April
Lynette Zang: Silver Fuse, Gold Anchor — This Currency Lifecycle is Ending
Lynette Zang, founder and CEO of Zang International, explains what gold and silver are saying about the world today, noting that while spot prices for the precious metals are down, they are on track to eventually assume their true fundamental value. "What I really want people to understand is... Keep Reading...
29 April
ASX Silver Stocks: 5 Biggest Companies in 2026
Investor interest in primary silver-mining stocks is high in 2026 alongside the silver price, which rose to new records of AU$171.85 and US$121.82 in late January.Silver's recent performance is supported by its dual role as a precious and industrial metal.Economic and geopolitical uncertainty in... Keep Reading...
21 April
Silver Institute: Sustained Supply Deficit Exposes Market to Squeezes
The global silver market is entering its sixth consecutive year of a supply deficit, but the underlying mechanics of the shortage have fundamentally shifted. According to the Silver Institute’s latest World Silver Survey, produced alongside London-based consultancy Metals Focus, the market will... Keep Reading...
Latest News
Interactive Chart
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00







