Galena Mining

Activities Report for Quarter Ended 31 March 2022

GALENA MINING LTDLTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ending 31 March 2022 (the “Quarter”), primarily focused on construction of its 60%-owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


HIGHLIGHTS:

  • Abra Project 58% complete at end of the March Quarter (19% of Abra construction works were completed during the March Quarter). Project focus remains on underground access to the Abra orebody and completion of the processing plant and power station.
  • Underground development achieved 694m advance during the Quarter remaining ahead of schedule with the decline reaching 1,395mRL. The decline is 82m above the orebody and 155m below the surface.
  • Overall processing plant construction has reached 61% complete. Plant engineering and drafting work is 95% complete and site construction work is 35% complete.
  • Contracts have been awarded for the remaining non-processing surface infrastructure work representing only 10% of the remaining project capex of $97.8M.
  • Power supply company Contract Power have commenced site works associated with the Abra power station (build, own, operate contract).
  • US$35M additional debt drawdown was completed under the Taurus Debt Facilities, leaving US$45M remaining undrawn.
  • Cash balance at Quarter-end A$60.0M.

ABRA BASE METALS MINE (60%-OWNED)

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL”), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted and under construction. First production of its high-value, high-grade lead- silver concentrate is currently scheduled for the first quarter of 2023 calendar-year.

Project construction / development

During the Quarter Abra Project construction works continued, passing the half-way to completion mark as the Quarter progressed.


Abra construction works conducted during the Quarter were comprised of site civil and earthworks, underground mine development, processing plant construction and ongoing front- end engineering design and procurement, including:

  • Underground mining – During the Quarter, underground development continued to progress ahead of schedule, with a further 694 metres of development being completed. As at Quarter-end, total development reached 1,134 metres consisting of 885 metres of decline development and 249 metres of other lateral development. The decline reached 1,395mRL, 82 metres above the Abra orebody and 155 metres below the surface. During the Quarter the first raise bore hole (4.5m) was successfully completed for development of the mine’s primary ventilation infrastructure. The ventilation shaft is one of 3 surface holes that will be completed to provide underground ventilation as the mine progresses.


Click here for the full ASX Release

This article includes content from GALENA MINING LTD. , licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
The Conversation (0)
Stock market tickers with various numbers in red and green; text reads: "mergers and acquisitions."

Silver Sector M&A Hits US$14.3 Billion As Miners Hunt for Growth

After five years of stagnant dealmaking, the silver mining sector underwent an aggressive US$14.3 billion consolidation wave since 2024. Data compiled by Metals Focus shows that announced transaction values surged from a negligible US$244 million over the preceding five-year window to US$14.3... Keep Reading...
Steve Penny, gold and silver bars.

Steve Penny: Silver at Key Inflection Point, What's Next for Price?

Steve Penny, founder of SilverChartist.com, shares his outlook for silver and gold, saying that while he expects much higher prices in the long term, the near and even medium term could bring more sideways movement for the precious metals. Penny also shares his current approach to oil, uranium... Keep Reading...
A rough metallic rock with a shiny silver surface sits on a blurred brown background.

Silver Storm Ships First Concentrate from La Parrilla

Silver Storm Mining (TSXV:SVRS,OTCQB:SVRSF) dispatched its first commercial shipment of lead-silver and zinc concentrates from the La Parrilla mine in Mexico, marking the complex's official return to commercial production.The initial batch of ore through La Parrilla’s sulphide circuit yielded a... Keep Reading...
Silver bars on a rising stock market graph.

Silver Miners Post Record Q2 Output Despite Volatility

Silver prices fell more than 22 percent in the second quarter of 2026, as high volatility and macroeconomic pressures pulled the metal down from its earlier heights.However, top miners insulated their balance sheets by turning to production, driving record throughputs and strong operational... Keep Reading...
Shawn Khunkhun

Shawn Khunkhun: Silver, Gold in Pre-Mania Phase, Here's What Comes Next

Shawn Khunkhun of Contango Silver & Gold (TSX:CTGO,NYSEAMERICAN:CTGO) shares his thoughts on the outlook for silver, saying that while he expects higher prices long term, the white metal could still go lower than where it is today. "Could we see US$40 (per ounce) silver, could we see US$50... Keep Reading...
Silver bar surrounded by shiny silver nuggets on a black background.

Top 5 Canadian Silver Stocks in 2026

Silver achieved a triple-digit price in the first quarter of 2026, drawing attention to silver-mining companies.During January, the silver price reached an all-time high of US$121.62 per ounce. Although prices came down significantly in the second quarter, silver still remains above its previous... Keep Reading...

Interactive Chart

Latest Press Releases

Related News