Galena Mining

Abra Construction 63% Complete At End of April

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 63% complete on 30 April 2022. Construction achievements during the month include completion of the first 1,000m of decline development and the commencement of the mining the first underground diamond drill chamber. Both GR Engineering Services Ltd. (“GR Engineering”) and Contract Power Australia Pty. Ltd. have made excellent progress at the processing plant and the power station sites.


Managing Director, Tony James commented, “During April we were fortunate to have only 10 COVID-19 isolation cases on site, which has had limited impact on construction works. It’s a credit to the site team on how they have navigated the pandemic-related challenges to date. By the end of April, the decline has reached the 1,380mRL level which is now 67m vertically above the orebody. It's also pleasing to see the development of the first underground diamond drilling drives.

At the processing plant a total of 1,527m3 (61%) of concrete has been poured on track to reach overall design volume of 2,500m3 on schedule. The construction of the fine ore bin is nearing completion and structural steel arriving on site is being installed".

Figure 1 – Lifting of the primary jaw crusher and fine ore bin top into position.

Figure 2 – Shows work progress on site from November 2021 through to April 2022.

Update on Abra Project progress

Overall progress continues to remain in line with Project schedule for the production critical areas of mining and processing. The processing plant engineering, procurement and construction has reached 68% complete by project spend. Underground development continues to be ahead of plan and the first underground drilling drives have been mined. In bulk earthworks, the tailings storage facility (“TSF”) work was suspended whilst a technical review was completed on the proposed TSF design, investigating the material suitability and availability for dam wall construction. A revised TSF has been designed and works have been awarded and for resumption in the second half of May for completion well in advance of plant commissioning. The final works package associated with the remaining non-processing infrastructure, which is not production critical has been finalised and that work has commenced. This includes the remaining buildings and the drill-core processing and storage facility. Owners' costs and contingencies remain under budget.

Click here for the full ASX Release

This article includes content from GALENA MINING LTD. (ASX: G1A), licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
The Conversation (0)

Galena Mining

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion... Keep Reading...
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November... Keep Reading...
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station... Keep Reading...
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western... Keep Reading...
Silver bars in front of newspaper showing high price performance.

What Was the Highest Price for Silver?

Like its sister metal gold, silver has been attracting renewed attention as a safe-haven asset. Although silver continues to exhibit its hallmark volatility, a silver bull market is well underway in 2025. Experts are optimistic about the future, and as the silver price's momentum continues in... Keep Reading...
Silver bars, stock market chart, green upward arrow, "Weekly Editor's Picks" text overlay.

Editor's Picks: Silver Price Keeps Running, Breaks All-time High Again

The silver price was on the rise once again this week — it surged past the US$67 per ounce level on Friday (December 19), hitting a new record before pulling back.As for gold, it spent much of the period around the US$4,330 per ounce level, although it rose as high as US$4,360 on Thursday... Keep Reading...
Adam Wooldridge, CEO of Cobre

Cobre Uncovers "Higher-grade" Copper at Cosmos Target, Assay Results Expected February 2026

Cobre (ASX:CBE) has completed a drilling program at its Cosmos target in Botswana, where the company has uncovered a higher-grade mineralised zone compared to nearby Comet target, according to CEO Adam Wooldridge. “What's really come through as being very interesting at the Cosmos target is the... Keep Reading...
Silver bars on a graph background with a rising line chart.

First Majestic to Sell Del Toro Silver Mine to Sierra Madre in US$60 Million Deal

First Majestic Silver (TSX:AG,NYSE:AG) has agreed to sell its Del Toro silver mine in Mexico to Sierra Madre Gold and Silver (TSXV:SM,OTCQX:SMDRF) in a transaction valued at up to US$60 million.The Vancouver-based miner said on Wednesday (December 17) that it has entered into a definitive... Keep Reading...

Interactive Chart

Latest Press Releases

Related News