Galena Mining

Abra Construction 63% Complete At End of April

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 63% complete on 30 April 2022. Construction achievements during the month include completion of the first 1,000m of decline development and the commencement of the mining the first underground diamond drill chamber. Both GR Engineering Services Ltd. (“GR Engineering”) and Contract Power Australia Pty. Ltd. have made excellent progress at the processing plant and the power station sites.


Managing Director, Tony James commented, “During April we were fortunate to have only 10 COVID-19 isolation cases on site, which has had limited impact on construction works. It’s a credit to the site team on how they have navigated the pandemic-related challenges to date. By the end of April, the decline has reached the 1,380mRL level which is now 67m vertically above the orebody. It's also pleasing to see the development of the first underground diamond drilling drives.

At the processing plant a total of 1,527m3 (61%) of concrete has been poured on track to reach overall design volume of 2,500m3 on schedule. The construction of the fine ore bin is nearing completion and structural steel arriving on site is being installed".

Figure 1 – Lifting of the primary jaw crusher and fine ore bin top into position.

Figure 2 – Shows work progress on site from November 2021 through to April 2022.

Update on Abra Project progress

Overall progress continues to remain in line with Project schedule for the production critical areas of mining and processing. The processing plant engineering, procurement and construction has reached 68% complete by project spend. Underground development continues to be ahead of plan and the first underground drilling drives have been mined. In bulk earthworks, the tailings storage facility (“TSF”) work was suspended whilst a technical review was completed on the proposed TSF design, investigating the material suitability and availability for dam wall construction. A revised TSF has been designed and works have been awarded and for resumption in the second half of May for completion well in advance of plant commissioning. The final works package associated with the remaining non-processing infrastructure, which is not production critical has been finalised and that work has commenced. This includes the remaining buildings and the drill-core processing and storage facility. Owners' costs and contingencies remain under budget.

Click here for the full ASX Release

This article includes content from GALENA MINING LTD. (ASX: G1A), licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
The Conversation (0)
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Silver bars on blue grid background with fluctuating line graph.

Pan American Silver Gets Green Light for US$2.1 Billion MAG Silver Deal

Pan American Silver (TSX:PAAS,NYSE:PAAS) is set to close its US$2.1 billion acquisition of MAG Silver (TSX:MAG,NYSEAMERICAN:MAG) after receiving final clearance from Mexico’s Federal Economic Competition Commission, cementing one of the year’s largest transactions in the sector.

The approval clears the way for the all-cash-and-stock deal to be completed on or about September 4 of this year, the companies announced on Monday (August 25).

Under the terms of the arrangement, MAG shareholders will receive either US$20.54 in cash per share or the default consideration of US$0.0001 in cash plus 0.755 of a Pan American share for each MAG share held.

Keep reading...Show less
Prismo Metals (CSE:PRIZ)

Prismo Metals


Keep reading...Show less
Silver Dollar Exercises Option on Government Gulch Portion of Ranger-Page Project

Silver Dollar Exercises Option on Government Gulch Portion of Ranger-Page Project

The Ranger-Page Project is in the Coeur d'Alene Mining District that ranks among the world's top producers of silver, lead and zinc

Silver Dollar Resources Inc. (CSE: SLV,OTC:SLVDF) (OTCQX: SLVDF) (FSE: 4YW) ("Silver Dollar" or the "Company") is pleased to announce that, further to its new release of August 7, 2024, it has completed the exercise of its option to acquire an initial 75% interest in the Government Gulch portion of the Ranger-Page Project located in Shoshone County, Idaho, USA

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Silver bars on a financial chart background with upward trend lines.

Silver Miners Deliver Record Q2 Earnings as Price Breaks Out

Top silver miners around the world delivered a slate of strong second quarter earnings reports as a mixture of higher metals prices and production gains boosted results across the sector.

The silver price has broken decisively above the US$35 per ounce level, rising to levels not seen in over a decade. Its run has been fueled by a structural supply deficit and robust industrial demand.

Analysts also note that silver is finally beginning to catch up with gold — the gold-silver ratio has narrowed from April’s peak of 105 to around 94, signaling the white metal's relative strength.

Keep reading...Show less
Globe made of silver metal showing North America and South America.

Top 10 Silver-producing Countries

There are many factors to consider when investing in silver-focused stocks, including the silver price outlook, the company's management team and whether its assets are in one of the top silver-producing countries.

Location can be key, and knowing the top silver-producing countries can help investors made sound decisions. For example, high silver production in a particular nation might indicate mining-friendly laws or high-grade deposits.

So which country produces the most silver? In 2024, Mexico was once again the world’s leading silver-producing country, followed by China and Peru.

Keep reading...Show less
Anteros Metals (CSE:ANT)

Anteros Metals


Keep reading...Show less

Latest Press Releases

Related News

×