Ur-Energy Provides 2024 Q2 Update: Lost Creek and Shirley Basin

Ur-Energy Inc. (NYSE American:URG)(TSX:URE) (the "Company" or "Ur-Energy") provides the following 2024 Q2 updates on Lost Creek production operations and guidance, Shirley Basin construction, and our uranium sales contract book

John Cash, the Company's CEO and Chairman of the Board, stated, "We are pleased that continuing advances at Lost Creek resulted in increased production quarter-over-quarter. The Lost Creek drilling and construction teams have further refined their work plans to facilitate our schedule of bringing a new header house online each month. This progress enables the continuing increase in production flow which will allow us to achieve our production targets. Importantly, the production patterns continue to be receptive to our mining methods, exhibiting strong production grades.

"We are happy to see the level of construction activity on the ground at Shirley Basin as well as the progress on procurement, and detailed engineering and planning to facilitate our planned buildout. We look forward to bringing uranium in situ recovery back to its birthplace at Shirley Basin and solidifying Ur-Energy's position as the dominant producer in the Great Divide Basin and Shirley Basin Districts of Wyoming."

Lost Creek Production Operations

Lost Creek production is advancing with three header houses having come online in 2024 H1. During Q2 we captured approximately 70,679 pounds, dried and packaged 64,170 pounds and shipped 70,390 pounds U3O8. We are pleased with the notable increase in each of these production numbers compared with Q1 production. Notwithstanding these improvements, we are guiding to the lower side of our earlier 2024 production guidance of 550,000 to 650,000 pounds captured on IX resin.

At quarter end, our in-process inventory was approximately 86,204 pounds, our drummed inventory at Lost Creek was 21,570 pounds, and our finished inventory at the conversion facility was 74,625 pounds U3O8. Our next shipment to the conversion facility is scheduled for late July.

Header House (HH) 2-9 came online this week and HH2-10 is scheduled to come online mid-August. Our construction crew is now on track to meet its goal of routinely completing a new header house approximately every thirty days. Throughout Q2 we had 12 drill rigs working at Lost Creek; we anticipate additional drill rigs mobilizing to Lost Creek in coming weeks.

Fabrication of HH2-10 is complete and fabrication of HHs 2-11 through 2-13 is in progress in our Casper construction shop. We recently took delivery of and deployed two downhole geophysical logging trucks that were ordered in early 2023.

Our site workforce is stabilizing, with safety and task training advancing. We continue to effectively navigate ongoing supply chain issues through the implementation of our long lead-time purchasing program. The lead time for electrical transformers remains challenging but we have a sufficient number of header house transformers on the ground for at least the next year.

Shirley Basin Development

In Q1 we were pleased to announce plans to begin the buildout of our Shirley Basin in situ recovery facility in Carbon County, Wyoming. Installation of the monitor wells for the first mine unit is on schedule with 100 of the 123 planned wells piloted and 62 wells cased. After all monitor wells are installed, we will collect baseline water quality and perform hydrologic aquifer tests. The hydrologic confinement at Shirley Basin is well established. We currently have two drill rigs working at Shirley Basin and expect to add a third rig in coming weeks. When the monitor well program is complete, the three rigs will redeploy to Lost Creek until construction and development drilling begins at Shirley Basin in 2025 H1.

The existing south access road to the site has been upgraded to an all-season road. Materials are on-hand and construction will soon commence for the secondary 15kV electrical power line distribution to the mine site. Engineering design is underway for the refurbishment of the pre-existing substation that serviced historic Shirley Basin operations. The office building and a support building are in the design phase and construction is planned for this year. Steel has been rolled and welded for the 15 IX columns under construction at a fabrication facility in Casper. Long-lead items are advancing on schedule.

Uranium Sales and Cash Position

We sold 75,000 pounds U3O8 in Q2 at an average price of $61.65 per pound for proceeds of $4.6 million. The cost per pound sold was $41.69. The average gross profit per pound sold of $19.96 results in an average gross profit margin of approximately 32%.

In addition to the 75,000 pounds sold in Q2, we have received binding notices from our customers for the delivery of 495,000 pounds in the second half of this year for total sales of 570,000 pounds U3O8 in 2024. Including the revenue received during the quarter, we expect to realize revenues of $33.1 million from U3O8 sales in 2024.

Deliveries for 2025 are committed to three of our customers for a base amount of 700,000 pounds U3O8. Under these agreements, two of the three buyers may elect to flex up or down by as much as 10% of the annual base delivery quantity. We are pleased to have received notice from one of our purchasers of its election to flex up its 2025 purchases by 10%, such that we now anticipate we may deliver 730,000 pounds U3O8 into our term sales agreements in 2025. We have not received all delivery notices from our purchasers.

As previously disclosed, in April we signed the third of three new offtake agreements completed in 2024. The newest agreement calls for annual delivery commitments of up to 100,000 pounds U3O8 in 2026 through 2029, a portion of which is based upon production milestones. Pricing is a combination of escalated fixed price, well above anticipated all-in costs of production, and a market-related pricing component that is subject to an escalated floor and ceiling. We have provided notice to the buyer of satisfaction of the milestones related to the 2026 and 2027 deliveries.

At June 30, 2024, we had cash and cash equivalents of $61.3 million.

About Ur-Energy

Ur-Energy is a uranium mining company operating the Lost Creek in situ recovery uranium facility in south-central Wyoming. We have produced and packaged approximately 2.7 million pounds U3O8 from Lost Creek since the commencement of operations. Ur-Energy has all major permits and authorizations to begin construction at Shirley Basin, the Company's second in situ recovery uranium facility in Wyoming and is advancing Shirley Basin construction and development following the March 2024 'go' decision for the mine. We await the remaining regulatory authorization for the expansion of Lost Creek. Ur‑Energy is engaged in uranium mining, recovery and processing activities, including the acquisition, exploration, development, and operation of uranium mineral properties in the United States. The primary trading market for Ur‑Energy's common shares is on the NYSE American under the symbol "URG." Ur‑Energy's common shares also trade on the Toronto Stock Exchange under the symbol "URE." Ur-Energy's corporate office is in Littleton, Colorado and its registered office is in Ottawa, Ontario.

FOR FURTHER INFORMATION, PLEASE CONTACT

John W. Cash, Chairman, CEO and President
+1 720-981-4588, ext. 303
John.Cash@Ur-Energy.com

Cautionary Note Regarding Forward-Looking Information

This release may contain "forward-looking statements" within the meaning of applicable securities laws regarding events or conditions that may occur in the future (e.g., 2024 Lost Creek production and revenue guidance; our ability to maintain operations at Lost Creek in a safe and compliant fashion while increasing production levels; our ability to continue to refine production operations and increase production levels in a timely and cost-effective way, to meet our production projections for the year including the ability to routinely bring on new header houses; our ability to remain ahead of supply chain challenges in our procurement of equipment and supplies for Lost Creek and Shirley Basin; our ability to satisfy commitments into our sales contracts including satisfaction of milestones; and the timing and ability to complete build out of Shirley Basin as currently projected) and are based on current expectations that, while considered reasonable by management at this time, inherently involve a number of significant business, economic and competitive risks, uncertainties and contingencies. Generally, forward-looking statements can be identified by the use of forward-looking terminology such as "plans," "expects," "does not expect," "is expected," "is likely," "estimates," "intends," "anticipates," "does not anticipate," or "believes," or variations of the foregoing, or statements that certain actions, events or results "may," "could," "might" or "will be taken," "occur," "be achieved" or "have the potential to." All statements, other than statements of historical fact, are considered to be forward-looking statements. Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements express or implied by the forward-looking statements. Factors that could cause actual results to differ materially from any forward-looking statements include, but are not limited to, capital and other costs varying significantly from estimates; failure to establish estimated resources and reserves; the grade and recovery of ore which is mined varying from estimates; production rates, methods and amounts varying from estimates; delays in obtaining or failures to obtain required governmental, environmental or other project approvals; inflation; changes in exchange rates; fluctuations in commodity prices; supply chain disruptions; delays in development and other factors described in the public filings made by the Company at www.sedarplus.ca and www.sec.gov. Readers should not place undue reliance on forward-looking statements. The forward-looking statements contained herein are based on the beliefs, expectations and opinions of management as of the date hereof and Ur-Energy disclaims any intent or obligation to update them or revise them to reflect any change in circumstances or in management's beliefs, expectations or opinions that occur in the future.

SOURCE: Ur-Energy Inc.



View the original press release on accesswire.com

News Provided by ACCESSWIRE via QuoteMedia

URE:CA,URG
The Conversation (0)
  Boss Energy

2024 Infill Drilling on Satellite Uranium Growth Deposits Complete

Resource update underway in preparation for bringing significant satellite deposits into the mine plan

Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to announce the conclusion of a successful infill drilling program at the Gould's Dam and Jason's satellite deposits within its Honeymoon Uranium project in South Australia.

Keep reading...Show less

NexGen Achieves Major Permitting Milestone

  • The Canadian Nuclear Safety Commission ("CNSC") has notified NexGen of successful completion of final Federal technical review.
  • This is the key requirement to scheduling a Federal Commission Hearing date and subsequent Federal Project approval decision.
  • The Federal Environmental Assessment ("EA") and License represent the final major approval steps after having received Provincial EA approval in November 2023 .
  • In production, the Rook I Project is poised to make NexGen one of the world's largest and most environmentally conscious mining companies.

NexGen Energy Ltd. ("NexGen" or the "Company") (TSX: NXE) (NYSE: NXE) (ASX: NXG) is excited and proud to announce a major milestone in the Federal EA process for its 100%owned Rook I Project ("the Project"). The CNSC has provided NexGen formal confirmation that the Company has successfully addressed all information requests received as part of the Federal technical review. With completion of the CNSC technical review, the next and final steps in the Federal approval process include scheduling a Commission Hearing Date for the Project, subject to which the CNSC will render an approval decision on the Project.

NexGen Energy Ltd. Logo (CNW Group/NexGen Energy Ltd.)

This historic milestone marks a crucial step forward for the Project that has been undergoing Canada's robust and rigorous regulatory process since 2019. Completion of the Federal EA technical review stage follows the CNSC having deemed NexGen's Federal licence application sufficient in September 2023 , and receipt of Provincial EA approval in November 2023 . This development reinforces Canada's path to re-establish itself as the leader in global uranium supply and partner of choice.

Leigh Curyer, Chief Executive Officer, commented: "This exciting outcome is a testament to the exceptional efforts of our entire NexGen team, the collaborative support of our valued Indigenous Nation partners, and our transparent approach with the CNSC to ensure a robust and thorough review that meets the highest standards of environmental protection for the sustainable development of the Rook I Project. Since inception, our honest and innovative holistic approach to the successful development of this generational project has set new industry standards as to what is possible, whilst positively impacting all our valued stakeholders.

Together with the Clearwater River Dene Nation, Métis Nation – Saskatchewan Northern Region 2 and Métis Nation – Saskatchewan , Buffalo River Dene Nation, and Birch Narrows Dene Nation, we are construction ready to deliver transformative and unprecedented social, economic and environmental benefits to local communities, the Province of Saskatchewan, Canada , and the world.

We're not just developing a mine - we're building strong communities while shaping a sustainable and secure global energy future. With over $800 million in cash and liquid assets, we are ready pending a positive Commission decision with all activities required to immediately commence major site works in place."

NexGen is poised to propel Canada back to the forefront of global clean energy fuel production. The Rook I Project embodies NexGen's commitment to elite environmental performance, unprecedented community inclusion, and responsible alignment with global net-zero goals.

About NexGen

NexGen Energy is a Canadian company focused on delivering clean energy fuel for the future. The Company's flagship Rook I Project is being optimally developed into the largest, low-cost producing uranium mine globally, incorporating the most elite standards in environmental and social governance. The Rook I Project is supported by a NI 43-101 compliant Feasibility Study which outlines the elite environmental performance and industry leading economics. NexGen is led by a team of experienced uranium and mining industry professionals with expertise across the entire mining life cycle, including exploration, financing, project engineering and construction, operations, and closure. NexGen is leveraging its proven experience to deliver a Project that leads the entire mining industry socially, technically, and environmentally. The Project and prospective portfolio in northern Saskatchewan will provide generational long-term economic, environmental, and social benefits for Saskatchewan, Canada , and the world.

NexGen is listed on the Toronto Stock Exchange and the New York Stock Exchange under the ticker symbol "NXE," and on the Australian Securities Exchange under the ticker symbol "NXG," providing access to global investors to participate in NexGen's mission of solving three major global challenges in decarbonization, energy security, and access to power. The Company is headquartered in Vancouver, British Columbia , with its primary operations office in Saskatoon , Saskatchewan.

Cautionary Note to U.S. Investors

This news release includes Mineral Reserves and Mineral Resources classification terms that comply with reporting standards in Canada and the Mineral Reserves and the Mineral Resources estimates are made in accordance with NI 43-101. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. These standards differ from the requirements of the Securities and Exchange Commission ("SEC") set by the SEC's rules that are applicable to domestic United States reporting companies. Consequently, Mineral Reserves and Mineral Resources information included in this news release is not comparable to similar information that would generally be disclosed by domestic U.S. reporting companies subject to the reporting and disclosure requirements of the SEC Accordingly, information concerning mineral deposits set forth herein may not be comparable with information made public by companies that report in accordance with U.S. standards.

Forward-Looking Information

The information contained herein contains "forward-looking statements" within the meaning of applicable United States securities laws and regulations and "forward-looking information" within the meaning of applicable Canadian securities legislation. "Forward-looking information" includes, but is not limited to, statements with respect to estimates for CapEx, OpEx and a payback period of 12 months, the appointment of a lead lender group, the availability of financing for the Project, the advancement of detailed engineering and contract negotiations, bolstering the globe's uranium supply chains to meet the rising demand for nuclear energy, the timing and cost of reclamation, including as part of the UGTMF and after-tax free cash flow remaining materially consistent with the FS, Free Cash Flow, Payback Period and IRR relative to various uranium prices, the delivery of clean energy fuel for the future, the development of the largest low cost producing uranium mine globally and incorporating elite standards in environmental and social governance, delivering a project that leads the entire mining industry socially, technically and environmentally, providing generational long-term economic, environmental and social benefits for Saskatchewan, Canada and the world, planned exploration and development activities and budgets, the interpretation of drill results and other geological information, mineral reserve and resource estimates (to the extent they involve estimates of the mineralization that will be encountered if a project is developed), requirements for additional capital, capital costs, operating costs, cash flow estimates, production estimates, the future price of uranium and similar statements relating to the economics of a project, including the Rook I Project. Generally, forward-looking information and statements can be identified by the use of forward-looking terminology such as "plans", "expects", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates", or "believes" or the negative connotation thereof or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved" or the negative connotation thereof.

Forward-looking information and statements are based on NexGen's current expectations, beliefs, assumptions, estimates and forecasts about its business and the industry and markets in which it operates. Forward-looking information and statements are made based upon numerous assumptions, including, among others, that financing for the Project will be available in a timely manner and on terms acceptable to the Company, the results of planned exploration and development activities will be as anticipated and on time; the price of uranium; the cost of planned exploration and development activities; that, as plans continue to be refined for the development of the Rook I Project, there will be no changes in costs, engineering details or specifications that would materially adversely affect its viability; that financing will be available if and when needed and on reasonable terms; that third-party contractors, equipment, supplies and governmental and other approvals required to conduct NexGen's planned exploration and development activities will be available on reasonable terms and in a timely manner; that there will be no revocation of government approvals; that general business, economic, competitive, social and political conditions will not change in a material adverse manner; the assumptions underlying the Company's mineral reserve and resource estimates and updated/revised CapEx, OpEx, SusEx, and pay back period; assumptions made in the interpretation of drill results and other geological information; the ability to achieve production on the Rook I Project; and other estimates, assumptions and forecasts disclosed in the Feasibility Study for the Rook I Project. Although the assumptions made by the Company in providing forward-looking information or making forward-looking statements were considered reasonable by management at the time they were made, there can be no assurance that such assumptions will prove to be accurate.

Forward-looking information and statements also involve known and unknown risks and uncertainties and other factors, which may cause actual results, performances and achievements of NexGen to differ materially from any projections of results, performances and achievements of NexGen expressed or implied by such forward-looking information or statements, including, among others, negative operating cash flow and dependence on third-party financing, uncertainty of additional financing, the risk that pending assay results will not confirm previously announced preliminary results, the imprecision of mineral reserve and resource estimates, the price and appeal of alternate sources of energy, sustained low uranium prices, aboriginal title and consultation issues, development risks, climate change, uninsurable risks, reliance upon key management and other personnel, risks related to title to its properties, information security and cyber threats, failure to manage conflicts of interest, failure to obtain or maintain required permits and licences, changes in laws, regulations and policy, competition for resources, political and regulatory risks, general inflationary pressures, industry and economic factors that may affect the business, and other factors discussed or referred to in the Company's most recent Annual Information Form under "Risk Factors" and management's discussion and analysis under "Other Risks Factors" filed on SEDAR+ at www.sedarplus.ca and 40-F filed on Edgar at www.sec.gov   .

Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in the forward-looking information or statements or implied by forward-looking information or statements, there may be other factors that cause results not to be as anticipated, estimated or intended.

There can be no assurance that forward-looking information and statements will prove to be accurate, as actual results and future events could differ materially from those anticipated, estimated or intended. Accordingly, readers are cautioned not to place undue reliance on forward-looking information or statements due to the inherent uncertainty thereof. The Company undertakes no obligation to update or reissue forward-looking information as a result of new information or events except as required by applicable securities laws.

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/nexgen-achieves-major-permitting-milestone-302309673.html

SOURCE NexGen Energy Ltd.

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/November2024/19/c8458.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
The word "uranium" beside green up arrow.

Russia Restricts US Uranium Exports, Retaliating to American Ban

The Russian government has imposed temporary restrictions on enriched uranium exports to the US.

Announced on November 15, the move follows the US' decision toban imports of Russian uranium.

While the US legislation went into effect in August, it allows for waivers to address potential supply disruptions through 2027. The new Russian policy introduces uncertainty during this time period.

Keep reading...Show less

Foremost Clean Energy Announces Strategic Engagement with Red Cloud Financial Services

Foremost Clean Energy Ltd. ( NASDAQ: FMST ) ( CSE: FAT ) (" Foremost " or the " Company "), an emerging North American uranium and lithium exploration company, is pleased to announce today that it has entered into a strategic agreement (the " Agreement ") with Red Cloud Financial Services Inc. (" RCFS" or " Red Cloud "), an arms-length independent contractor, to provide promotional services, including advice on marketing, communications and social media activities. Under the engagement, Red Cloud will be paid a fee of $10,000 per month effective October 14, 2024, for a twelve-month term which automatically renews month-to-month thereafter unless either party provides written notice of termination to the other party thirty (30) days prior to the date of termination.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Nuclear reactors and a stock chart.

US Plans to Triple Nuclear Power Capacity by 2050

The Biden administration has announced a strategic roadmap to significantly expand the United States' nuclear energy capacity, setting a target to triple capacity by 2050.

In a new nine pillar framework, the Biden-Harris administration has laid out its plans to add 200 gigawatts (GW) of new nuclear energy through new reactor builds, reactivations and upgrades to existing facilities.

The initiative seeks to meet a growing demand for reliable, carbon-free power as the nation transitions away from fossil fuels and toward cleaner energy sources.

Keep reading...Show less
Red graph and arrow pointing down.

Paladin Cuts Uranium Production Forecast, Share Price Declines

Shares of Paladin Energy (ASX:PDN,OTCQX:PALAF) declined this week after the company shared an update on its Langer Heinrich mine and revised its 2025 fiscal year production guidance.

The company now expects the mine to produce 3 million to 3.6 million pounds of U3O8, lower than its earlier prediction of 4 million to 4.5 million pounds. According to Paladin, the drop is the result of lower-than-expected output in October, which was caused by water supply disruptions, as well as continued variability in stockpiled ore.

Production from Langer Heinrich amounted to 186,667 pounds during the month.

Keep reading...Show less