Ta Khoa Nickel Project Test Work Update

Ta Khoa Nickel Project Test Work Update

Blackstone Minerals Limited “Blackstone” or the “Company”) is pleased to provide an update on our ongoing metallurgical test work programmes for both the Ta Khoa Nickel Project (“TKN” or “Upstream Project”) and the Ta Khoa Refinery Project (“TKR” or “Downstream Project”) during their respective Definitive Feasibility Study (“DFS”) phases.



Figure 1: Cobalt solvent extractionFigure 1: Cobalt solvent extraction

In October 2021, Blackstone announced the appointment of Tier 1 engineering, minerals processing and metallurgical consultants Wood and ALS to perform critical roles in the delivery of the TKR DFS. With the support of Wood’s expertise in hydrometallurgical flowsheet development and ALS’ expertise in metallurgical laboratory testing and continuous integrated flowsheet piloting, Blackstone is pleased to announce the following test work updates:

  • Completion of bench test work program: The hydrometallurgical bench test work program successfully confirmed the improved DFS process flowsheet. The data collected during the bench test work program has been used to update the TKR plant design criteria.
  • Design, procurement, and assembly of piloting equipment: Extensive work has been completed between Blackstone, Wood and ALS to develop a pilot campaign that is fit for purpose and aligns with the DFS flowsheet.
  • Successful commissioning of piloting equipment: ALS has successfully assembled the TKR flowsheet and commissioned all unit operations from mixed hydroxide precipitate (“MHP”) re-leach through to the production of battery grade metal sulphates. The pressure oxidation (“POX”) leach flowsheet will be commissioned by end of August 2022.
  • Successful operation of MHP to metal sulphate from third party MHP: Blackstone has successfully piloted the TKR flowsheet, confirming our ability to process third-party MHP to battery grade metal sulphates.

Click here for the full ASX Release

This article includes content from Blackstone Minerals Limited , licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

BSX:AU
Blackstone Minerals

Blackstone Minerals Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Blackstone Minerals

Blackstone Minerals


Keep reading...Show less
Centaurus Metals

Jaguar Nickel Sulphide Project – Feasibility Study

Positive Feasibility Study Demonstrates Strong Economics And Clear Pathway To Develop A Sustainable, Long-Life And Low-Cost Nickel Sulphide Project In Northern Brazil

Centaurus Metals (ASX Code: CTM) is pleased to announce the completion of a positive Feasibility Study (FS) for the development of its 100%-owned Jaguar Nickel Sulphide Project in the Carajás Mineral Province of northern Brazil, which highlights strong economics from an initial concentrate-only project delivering a long-life production profile at first quartile operating costs.

Keep reading...Show less
Electric car plugged into charging station.

Surge in EV Market Drives Demand for High-density Battery Materials

The electric vehicle (EV) sector is growing, spurring the market for battery materials.

As lithium-ion batteries reach their capacity limit, demand is expanding for other raw materials to manufacture high-density batteries, particularly nickel. This metal boasts a wide range of physical properties that make it ideal for the green energy market — plus it’s an affordable component looked to for next-generation as well as existing products.

Demand for nickel for use in EVs is expected to increase tenfold from 2019 to 2030. Since nickel is also used to generate geothermal energy, hydrogen, hydro, wind and solar power, it’s emerging as a key component in green energy.

Keep reading...Show less
Blackstone Minerals

Blackstone Receives A$1 Million R&D Refund Advance

Blackstone Minerals Limited (ASX: BSX) (“Blackstone” or the “Company”) is pleased to announce that it has received A$1 million as an advance from research & development (“R&D”) lending fund backed by Asymmetric Innovation Finance (“Asymmetric”) and Fiftyone Capital ("Fiftyone"), on Blackstone’s future 2024 refundable tax offset for R&D expenditure.

Keep reading...Show less
Pivotal Metals

First Two Step-out Holes Extend High Grades at Horden Lake

Pivotal Metals Limited (ASX:PVT) (‘Pivotal’ or the ‘Company’) is pleased to provide the assay results of two further drill holes from its 2024 diamond drill program completed at its 100% owned Horden Lake Project in Quebec, Canada.

Keep reading...Show less
Ontario map.

Wyloo to Build Canada’s First Battery Materials Processing Facility in Sudbury

Privately owned critical materials company Wyloo announced on May 29 that it has secured a parcel of land in Sudbury, Ontario, to construct Canada’s first downstream battery materials processing facility.

The project is geared at bridging a gap in the conversion of raw materials to battery-grade chemicals for Canada’s electric vehicle (EV) supply chain, while also reducing the country's reliance on imports.

Construction is anticipated to align with the development of Wyloo’s Eagle’s Nest mine in Northern Ontario’s Ring of Fire region, with mine construction expected to commence in 2027 and the facility to follow thereafter.

Keep reading...Show less
Grid Battery Metals (TSXV:CELL)

Grid Battery Metals


Keep reading...Show less