
July 25, 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) advises that the announcement titled “Abra Initial Production Guidance” dated 21 July 2022 has been re- released to include additional information required by the ASX Listing Rules relating to the initial production guidance and other information contained therein.
HIGHLIGHTS
- Abra Project construction is now 75% complete – Galena confirms first concentrate production remains on-target for Q1 2023 and provides initial production targets based on latest mine plan
- CY2023 mill throughput expected to be 0.8-1.0Mtpa resulting in ramp-up year lead production of 53-68kt
- Following ramp-up, life of mine average annual production expected to average 93,000 tonnes of lead and 553,000 ounces of silver, with lead ‘C1’ direct cash cost of US$0.50/lb
- Plant processing throughput and mine plan increased to 1.3Mtpa in the current mine plan (vs. 1.2Mtpa in 2019 Feasibility Study)1
Galena is pleased to provide initial production guidance for its 60%owned Abra Base Metals Mine (“Abra” or the “Project”) having achieved the construction milestone of 75% complete. The guidance for the CY2023 ramp-up year and future life of mine averages are based on the most recently updated mine plan incorporating updated mine designs and the latest cost information.
Managing Director, Tony James commented, “With first concentrate production on target for the March 2023 quarter, we provide this update on near-term and life of mine plan and targets. During the construction period of the project, we have worked very closely with our partner Toho Zinc and our key service providers to reach the 75% build mark. For the remainder of 2022 we plan to safely complete the mine construction and commission Abra as a world-class lead-silver mine.”
The guidance provided today is based on the knowledge and confidence gained from additional drilling, Mineral Resource estimation, and advancing construction at Abra, and preparation for commissioning ahead of a planned safe and efficient start-up.
Grade control drilling commenced in June 2022 and ongoing drilling and evaluation over the next 3 months will likely offer further opportunity for additional optimisation of the mine plan.
The forecast life of mine production now averages 93,000tpa lead metal production and 553,000ozpa silver. An 8% increase in mine and mill production is offset by a 6% reduction in lead grade to produce slightly less metal in direct comparison to the 2019 Feasibility Study (“FS”)1. A suitable ramp up profile has been adopted for the CY2023 prior to reaching steady state production which is anticipated to occur in the December quarter 2023.
OVERVIEW OF KEY UPDATED MINE PLAN OUTCOMES
Abra is a globally significant lead-silver deposit, located in the Gascoyne region of Western Australia. The mine is under full construction and has reached 75% construction completion and will commence first concentrate production in March quarter CY2023. The Updated Mine Plan confirms the strong projected economic returns for the development of the Mine as a combined underground mine and conventional flotation concentrator to produce a high-value, high-grade lead-silver concentrate.
Click here for the full ASX Release
This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
The Conversation (0)
12 September 2022
Galena Mining
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
12 December 2022
Abra Construction At 97% Complete – First Ore Stockpiled For January Processing
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion... Keep Reading...
16 November 2022
Abra Construction At 92% Complete – Reaches First Ore Underground
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November... Keep Reading...
13 November 2022
Abra Mine Reaches Ore
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station... Keep Reading...
31 October 2022
Galena Mining Activities Report For Quarter Ended 30 September 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western... Keep Reading...
27 October
Prince Silver Corp Announces Closing of First Tranche of Private Placement Financing
Prince Silver Corp. ("Prince" or the "Company") (CSE:PRNC)(OTCQB:PRNCF) is pleased to announce that further to its news release dated September 24, 2025, the Company has closed the first tranche (the "First Tranche") of its previously announced non-brokered private placement financing for gross... Keep Reading...
24 October
Ed Steer: Silver Rally Now Unstoppable, Price to Hit Triple Digits
Ed Steer of Ed Steer's Gold and Silver Digest shares his thoughts on silver's run past US$50 per ounce, saying that in his view the bull market is just getting started. "One way or another we're going to run into a supply/demand brick wall, and when that day happens we could see triple-digit... Keep Reading...
22 October
Gianni Kovacevic: Silver, Oil to Break US$100, but This is the Real Speculation
Investor and author Gianni Kovacevic discusses silver's price pullback, saying that in the long term he sees the white metal reaching triple digits. He expects oil prices to reach that level too, but emphasized that he sees lithium as the truly contrarian play for the rest of 2025 and into next... Keep Reading...
21 October
BP Silver Finalizes Targets for Upcoming Drill Program at its Cosuño Silver Project, Bolivia
BP Silver Corp. (TSXV: BPAG) ("BP Silver" or the "Company") announces that it has finalized targets for initial drill testing and has selected Maldonado Exploraciones, a premier Bolivian drilling contractor, to carry out the upcoming drill program at its Cosuño Silver Project ("Cosuño") in... Keep Reading...
21 October
Silver Hammer Enters into Option Agreement to Acquire 100% Interest in a Strategic and Prospective Silver Project in the Silver Valley of Idaho
Silver Hammer Mining Corp. (CSE: HAMR) (the "Company" or "Silver Hammer") is pleased to announce it has entered into an option agreement (the "Option Agreement") on October 20, 2025 with Fahey Group Mines, Inc. ("Fahey"), pursuant to which the Company has been granted the right (the "Option") to... Keep Reading...
Latest News
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00






