 (TSX: LUN) (Nasdaq Stockholm: LUMI) Lundin Mining Corporation ("Lundin Mining" or the "Company") announces production results for the three and twelve months ended December 31, 2021 . The consolidated financial results for the year ended December 31, 2021 will be published on February 17, 2022 .

 

  Highlights  

 
  • Most recent 2021 annual production guidance was achieved for all metals. Production of 262,884 t of copper was above the midpoint of guidance and an increase of 14% over 2020. Zinc production of 143,797 t was above the midpoint of guidance and an increase over the prior year. Gold production of 167,000 oz exceeded annual guidance.
  •  
  • Candelaria copper production of 151,719 t achieved guidance and gold production of 91,000 oz exceeded guidance. Fourth quarter operations were particularly strong, producing 45,573 t of copper and 26,000 oz of gold, the most since the third quarter of 2017. With focus on operational practices, the positive trend of improvement in grade discrepancy continued progressively each month in the fourth quarter and averaged approximately 4%.
  •  
  • Chapada copper production of 52,019 t exceeded guidance and gold production of 76,000 oz achieved the top end of annual guidance. The state of Goiás and regions around Chapada have experienced greater than typical precipitation during the rainy season in 2022. Chapada is managing the rainfall well and continues to operate safely.
  •  
  • Eagle achieved strong and consistent operating performance again in 2021. Nickel production of 18,353 t and copper production of 18,419 t both achieved annual guidance.
  •  
  • Neves-Corvo copper production of 37,941 t achieved the top end of annual guidance and zinc production of 66,031 t was within 1kt of guidance. Fourth quarter operations were the strongest of the year. Construction of the Zinc Expansion Project (ZEP), to double current zinc production capacity and improve per unit operating cost, was substantially completed at the end of 2021 with the commencement of commissioning of the mine materials handling system and the expanded zinc processing plant.
  •  
  • Zinkgruvan production of 77,766 t of zinc exceeded annual production guidance.
  •  
  • Continuing the trend of annual improvement, Lundin Mining achieved a new best-ever Total Recordable Injury Frequency (TRIF) rate in 2021 with a rate of 0.54 per 200,000 person hours worked. This excellent safety result was realized during a year that saw an increase in our operational activities, particularly project related activities at the Neves-Corvo ZEP, and during a period of continuing stressors and distractions stemming from the ongoing COVID-19 pandemic.
  •  

  Summary of 2021 Production  

 
 
                                                                                                                                                                                                                                         
 
 
 

   Q4 2021   

 

   Production   

 
 
 

   Full Year 2021   

 

   Production   

 
 
 

   2021 Production   

 

   Guidance   1    

 
 
 

   Copper (t)   

 
 
 
 
 
 
 
 
 
 
 
 
 
 

  Candelaria (100% basis)  

 
 

  45,573  

 
 
 

  151,719  

 
 
 

  150,000  

 
 

  -  

 
 

  155,000  

 
 
 
 

  Chapada  

 
 

  14,870  

 
 
 

  52,019  

 
 
 

  48,000  

 
 

  -  

 
 

  50,000  

 
 
 
 

  Eagle  

 
 

  3,636  

 
 
 

  18,419  

 
 
 

  18,000  

 
 

  -  

 
 

  20,000  

 
 
 
 

  Neves-Corvo  

 
 

  12,100  

 
 
 

  37,941  

 
 
 

  36,000  

 
 

  -  

 
 

  38,000  

 
 
 
 

  Zinkgruvan  

 
 

  817  

 
 
 

  2,786  

 
 
 

  3,000  

 
 

  -  

 
 

  4,000  

 
 
 
 

   Total Copper   

 
 

   76,996   

 
 
 

   262,884   

 

 
 

   255,000   

 
 

   -   

 
 

   267,000   

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

   Zinc (t)   

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

  Neves-Corvo  

 
 

  18,750  

 
 
 

  66,031  

 
 
 

  67,000  

 
 

  -  

 
 

  70,000  

 
 
 
 

  Zinkgruvan  

 
 

  18,080  

 
 
 

  77,766  

 
 
 

  73,000  

 
 

  -  

 
 

  76,000  

 
 
 
 

   Total Zinc   

 
 

   36,830   

 
 
 

   143,797   

 
 
 

   140,000   

 
 

   -   

 
 

   146,000   

 
 
 
 
 
 
 
 
 
 
 
 
 

   Gold (oz)   

 
 
 
 
 
 
 
 
 
 
 

  Candelaria (100% basis)  

 
 

  26,000  

 
 
 

  91,000  

 
 
 

  85,000  

 
 

  -  

 
 

  90,000  

 
 
 
 

  Chapada  

 
 

  20,000  

 
 
 

  76,000  

 
 
 

  73,000  

 
 

  -  

 
 

  76,000  

 
 
 
 

   Total Gold   

 
 

   46,000   

 
 
 

   167,000   

 
 
 

   158,000   

 
 

   -   

 
 

   166,000   

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

   Nickel (t)   

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

  Eagle  

 
 

  4,101  

 
 
 

  18,353  

 
 
 

  18,000  

 
 

  -  

 
 

  20,000  

 
 
 
 

   Total Nickel   

 
 

   4,101   

 
 
 

   18,353   

 
 
 

   18,000   

 
 

   -   

 
 

   20,000   

 
 
 
 

  Fourth Quarter and Full Year 2021 Results Date  

 

Results for the fourth quarter and full year ended December 31, 2021 will be published on Thursday February 17, 2022.

 

The Company will hold a telephone conference call and webcast at 08:00 ET , 14:00 CET on Friday February 18, 2022. Conference call details are provided below. Please call in 10 minutes before the conference starts.

 

Call-in number for the conference call ( North America ): +1 647 788 4922
Call-in number for the conference call (North America Toll Free): +1 877 223 4471
Call-in number for the conference call ( Sweden ): 02 00 123 522

 

To view the live webcast presentation, please log on using this direct link: https://onlinexperiences.com/Launch/QReg/ShowUUID=5FC47C1B-ED4D-4F01-B238-3CEBD68F4298 .

 

The presentation slideshow will also be available in PDF format on the Lundin Mining website www.lundinmining.com before the conference call.

 

A replay of the telephone conference will be available after the completion of the call until March 18, 2022.

 
 
  
 

  _____________________________________  

 
 

   1 Guidance as most recently disclosed in the Company's Management Discussion and Analysis for the three and nine months ended September 30, 2021.  

 
 
 

Call-in numbers for the replay are ( North America ): +1 800 585 8367 or +1 416 621 4642

 

The passcode for the replay is: 8270928

 

A replay of the webcast will be available by clicking on the direct link above.

 

  About Lundin Mining  

 

Lundin Mining is a diversified Canadian base metals mining company with operations in Brazil , Chile , Portugal , Sweden and the United States of America , primarily producing copper, zinc, gold and nickel.

 

The information in this release is subject to the disclosure requirements of Lundin Mining under the EU Market Abuse Regulation. The information was submitted for publication, through the agency of the contact persons set out below on January 14, 2022 at 02:00 Eastern Time .

 

  Cautionary Statement on Forward-Looking Information  

 

  Certain of the statements made and information contained herein is "forward-looking information" within the meaning of applicable Canadian securities laws. All statements other than statements of historical facts included in this document constitute forward-looking information, including but not limited to statements regarding the Company's plans, prospects and business strategies; the Company's guidance on the timing and amount of future production and its expectations regarding the results of operations; expected costs; permitting requirements and timelines; timing and possible outcome of pending litigation; the results of any Preliminary Economic Assessment, Feasibility Study, or Mineral Resource and Mineral Reserve estimations, life of mine estimates, and mine and mine closure plans; anticipated market prices of metals, currency exchange rates, and interest rates; the development and implementation of the Company's Responsible Mining Management System; the Company's ability to comply with contractual and permitting or other regulatory requirements; anticipated exploration and development activities at the Company's projects; and the Company's integration of acquisitions and any anticipated benefits thereof. Words such as "believe", "expect", "anticipate", "contemplate", "target", "plan", "goal", "aim", "intend", "continue", "budget", "estimate", "may", "will", "can", "could", "should", "schedule" and similar expressions identify forward-looking statements.  

 

  Forward-looking information is necessarily based upon various estimates and assumptions including, without limitation, the expectations and beliefs of management, including that the Company can access financing, appropriate equipment and sufficient labor; assumed and future price of copper, nickel, zinc, gold and other metals; anticipated costs; ability to achieve goals; the prompt and effective integration of acquisitions; that the political environment in which the Company operates will continue to support the development and operation of mining projects; and assumptions related to the factors set forth below. While these factors and assumptions are considered reasonable by Lundin Mining as at the date of this document in light of management's experience and perception of current conditions and expected developments, these statements are inherently subject to significant business, economic and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking statements and undue reliance should not be placed on such statements and information. Such factors include, but are not limited to: risks inherent in mining including but not limited to risks to the environment, industrial accidents, catastrophic equipment failures, unusual or unexpected geological formations or unstable ground conditions, and natural phenomena such as earthquakes, flooding or unusually severe weather; uninsurable risks; global financial conditions and inflation; changes in the Company's share price, and volatility in the equity markets in general; volatility and fluctuations in metal and commodity prices; the threat associated with outbreaks of viruses and infectious diseases, including the COVID-19 virus; changing taxation regimes; reliance on a single asset; delays or the inability to obtain, retain or comply with permits; risks related to negative publicity with respect to the Company or the mining industry in general; health and safety risks; exploration, development or mining results not being consistent with the Company's expectations; unavailable or inaccessible infrastructure and risks related to ageing infrastructure; actual ore mined and/or metal recoveries varying from Mineral Resource and Mineral Reserve estimates, estimates of grade, tonnage, dilution, mine plans and metallurgical and other characteristics; risks associated with the estimation of Mineral Resources and Mineral Reserves and the geology, grade and continuity of mineral deposits including but not limited to models relating thereto; ore processing efficiency; community and stakeholder opposition; information technology and cybersecurity risks; potential for the allegation of fraud and corruption involving the Company, its customers, suppliers or employees, or the allegation of improper or discriminatory employment practices, or human rights violations; regulatory investigations, enforcement, sanctions and/or related or other litigation; uncertain political and economic environments, including in Brazil and Chile ; risks associated with the structural stability of waste rock dumps or tailings storage facilities; estimates of future production and operations; estimates of operating, cash and all-in sustaining cost estimates; civil disruption in Chile ; the potential for and effects of labor disputes or other unanticipated difficulties with or shortages of labor or interruptions in production; risks related to the environmental regulation and environmental impact of the Company's operations and products and management thereof; exchange rate fluctuations; reliance on third parties and consultants in foreign jurisdictions; climate change; risks relating to attracting and retaining of highly skilled employees; compliance with environmental, health and safety laws; counterparty and credit risks and customer concentration; litigation; risks inherent in and/or associated with operating in foreign countries and emerging markets; risks related to mine closure activities and closed and historical sites; changes in laws, regulations or policies including but not limited to those related to mining regimes, permitting and approvals, environmental and tailings management, labor, trade relations, and transportation; internal controls; challenges or defects in title; the estimation of asset carrying values; historical environmental liabilities and ongoing reclamation obligations; the price and availability of key operating supplies or services; competition; indebtedness; compliance with foreign laws; existence of significant shareholders; liquidity risks and limited financial resources; funding requirements and availability of financing; enforcing legal rights in foreign jurisdictions; dilution; risks relating to dividends; risks associated with acquisitions and related integration efforts, including the ability to achieve anticipated benefits, unanticipated difficulties or expenditures relating to integration and diversion of management time on integration; activist shareholders and proxy solicitation matters; and other risks and uncertainties, including but not limited to those described in the "Risk and Uncertainties" section of the Annual Information Form and the "Managing Risks" section of the Company's MD&A for the year ended December 31, 2020 , which are available on SEDAR at www.sedar.com under the Company's profile. All of the forward-looking statements made in this document are qualified by these cautionary statements. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated, forecast or intended and readers are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking information. Accordingly, there can be no assurance that forward-looking information will prove to be accurate and forward-looking information is not a guarantee of future performance. Readers are advised not to place undue reliance on forward-looking information. The forward-looking information contained herein speaks only as of the date of this document. The Company disclaims any intention or obligation to update or revise forward    looking information or to explain any material difference between such and subsequent actual events, except as required by applicable law.  

 
 

  Lundin Mining Announces 2021 Production Guidance Achieved for All Metals; Fourth Quarter and Full Year 2021 Results to be Released February 17, 2022 (CNW Group/Lundin Mining Corporation) 

 
 
 
 

SOURCE Lundin Mining Corporation

 

 

 

 Cision View original content to download multimedia: https://www.newswire.ca/en/releases/archive/January2022/14/c0481.html  

 
 

News Provided by Canada Newswire via QuoteMedia

LUN:CA,LUNMF
The Conversation (0)
Loyal Metals Limited

Loyal to Acquire the High-Grade Highway Reward Copper Gold Mine

Loyal Metals Limited (ASX:LLM) (Loyal, LLM, or the Company) is pleased to announce that it has acquired a binding option to purchase the Highway Reward Copper Gold Mine in Queensland, Australia, one of the highest-grade copper mines worldwide, with past production totalling 3.65 million tonnes at 5.7% Cu and 260,000 tonnes at 4.5 g/t Au 1-9. This acquisition is the first step in Loyal’s 2025 Strategic Plan to broaden its critical minerals portfolio into copper. No exploration has been conducted on the mining leases since mining ceased in July 2005, despite a ~680% increase in copper prices and a ~1,256% increase in gold prices since the 1997 feasibility study 3,4. With over $4.4 million in funding, Loyal is well-positioned to revisit the high-grade Highway Reward Copper Gold Mine by deploying modern exploration techniques11.

Keep reading...Show less
Textured copper ribbons weave over a black background.

​Copper​ Market Hit by Major Supply Squeeze as LME Inventories Drop

One of the sharpest copper supply crunches in recent memory is rattling global commodities markets, as inventories at the London Metal Exchange (LME) plummet and the spot price soars.

Bloomberg reported that as of Monday (June 23), copper for immediate delivery was trading at a premium of US$345 per metric ton over three month futures, the widest spread since a record squeeze in 2021.

That dramatic price divergence reflects the market’s acute concerns over access to physical copper, with readily available inventories on the LME falling by around 80 percent this year alone.

Keep reading...Show less
Many copper bobbins and warehouse copper pipes.

Top 10 Copper-producing Companies

Copper miners with productive assets have much to gain as supply and demand tighten.

In May 2024, the copper price hit a new all-time high of US$10,954 per metric ton (MT) on the London Metal Exchange and US$5.20 per pound on the COMEX on the back of increasing demand and growing supply concerns.

Copper is one of the most important resources for the energy transition. However, in recent years, demand for the red metal has outpaced mining supply. While construction and electrical grids have long been major markets for copper, today the rise in demand for electric vehicles, EV charging infrastructure and energy storage applications are emerging drivers of copper consumption.

Another trend driving future copper demand is the rapid urbanization in the Global South, as rural populations migrate to cities, putting pressure on electricity grids.

Keep reading...Show less
White Cliff Minerals

John Hancock to join White Cliff Minerals Board

Astrotricha Capital SEZC appointed Advisors

White Cliff Minerals Limited (“WCN” or the “Company”) (ASX: WCN; OTCQB: WCMLF) is pleased to announce that John Hancock will join the Board of White Cliff Minerals effective 1 August 2025.

Keep reading...Show less
Gavel on books with "5 Top Canadian Mining Stocks This Week" text overlay.

Top 5 Canadian Mining Stocks This Week: Royalties Jumps 183 Percent on Legal Win

Welcome to the Investing News Network's weekly look at the best-performing Canadian mining stocks on the TSX, TSXV and CSE, starting with a round-up of Canadian and US news impacting the resource sector.

Friday (June 20) was the last day for the spring session of Canada’s parliament before its summer break.

On the agenda for the day was a vote on bill C-5, “The One Canadian Economy Act,” which was introduced on June 5.

Keep reading...Show less
Cyprium Metals

Nifty Copper Project Virtual Site Visit

Cyprium Metals Limited (ASX: CYM, OTC: CYPMF) (Cyprium or the Company) invites shareholders to join an investor webinar and live Q&A hosted by Executive Chairman Matt Fifield on Tuesday 24th June 2025. Investors will be guided on a virtual site visit of the Nifty Copper Complex showcasing the sulphide and heap leach resources and extensive brownfield infrastructure.

Keep reading...Show less

Latest Press Releases

Related News

×