Lithium ION Energy Shares Victory Nickel Update

Lithium ION Energy Shares Victory Nickel Update

Lithium Ion Energy Limited (TSXV: ION) (OTCQB: IONGF) (FSE: ZA4 ) ("ION" or the "Company") is pleased to announce an update on the Victory Nickel Project in Mongolia, following the exploration joint venture that was entered into with Aranjin Resources Ltd. ("Aranjin") (TSXV: ARJN), in February 2022.

HIGHLIGHTS

  • A strategic alliance was announced in February 2022, between ION and Aranjin, allowing both companies to grant one another reciprocal exploration rights to their respective exploration licences within Mongolia;
  • This agreement followed an exciting Copper and Nickel discovery, "Victory Nickel Project" at the center of Ion Energy's Baavhai Uul licence; and
  • ION's 20% interest and Aranjin Resources' 80% ownership of the Victory Nickel Project in Mongolia, has now been formalized.

Ali Haji, CEO & Director of Lithium Ion Energy, stated, "We are extremely pleased to be able to formalize our agreement with Aranjin, realizing the upside of the Victory Nickel deposit by carving out the discovery from the large Baavhai Uul licence enabling Aranjin to immediately begin to unearth value, while ION continues to have a 20% carried interest in the project and all Lithium rights therein."

Victory Nickel Project - Mongolia

Further to the announcement on February 1, 2022, Lithium Ion Energy has now formalized its 20% ownership interest in the Victory Nickel Project further to the announcement on February 1, 2022. The Joint Venture arrangement consisted of the Company and Aranjin Resources granting one another reciprocal exploration rights on their respective exploration licences within Mongolia. ION and Aranjin granted each other a reciprocal right to explore one another's properties, with Aranjin earning an 80% interest and ION earning a 20% interest in all base metal projects discovered on ION's properties, and ION earning an 80% interest and Aranjin earning a 20% interest in all lithium projects discovered on Aranjin's properties, subject to existing royalties.

Following exploration work by both parties in 2022 and 2023, the parties agreed to formally separate their ownership of the Baavhai Uul project previously wholly owned by ION to largely mirror the business arrangement set out in the Joint Venture Agreement. The split of the Baavhai Uul licence is pending approval by the Mineral Resource and Petroleum Authority of Mongolia. Under the Joint Venture, Aranjin will own 80% of the Victory Nickel project and relinquish rights to the remainder of the licence comprising the Baavhai Uul project. Ion Energy will retain a 20% free carried interest in the Victory Nickel Project until commercial production as well as retain all lithium rights to the Victory Nickel Project.

About Lithium ion energy ltd.

Lithium iion energy ltd. (TSXV: ION) (OTCQB: IONGF) (FSE: ZA4) is committed to exploring and developing high quality lithium resources in strategic jurisdictions. ION's flagship, 81,000+ hectare Baavhai Uul lithium brine project represents the largest and first lithium brine exploration licence award in Mongolia. ION also holds the 29,000+ hectare Urgakh Naran highly prospective lithium brine licence in Dorngovi Province in Mongolia. With the acquisition of the Bliss Lake and Little Nahani projects in NWT, Canada, ION will have significantly enhanced its lithium asset and jurisdiction profile. ION is well-poised to be a key player in the clean energy revolution, positioned well to service the world's increased demand for lithium. Information about the Company is available on its website, www.ionenergy.ca, or under its profile on SEDAR+ at www.sedarplus.ca.

For further information:

COMPANY CONTACT: Ali Haji, ali@ionenergy.ca, 647-871-4571

MEDIA CONTACT: Siloni Waraich, siloni@ionenergy.ca, 416-432-4920

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

Cautionary Note Regarding Forward-Looking Information

Information set forth in this news release contains forward-looking statements. Forward-looking statements include estimates and statements that describe the Company's future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Forward-looking statements may be identified by such terms as "believes", "anticipates", "expects", "estimates", "may", "could", "would", "will", or "plan". Since forward-looking statements are based on assumptions and address future events and conditions, by their very nature they involve inherent risks and uncertainties. Although these statements are based on information currently available to the Company, the Company provides no assurance that actual results will meet management's expectations. Risks, uncertainties and other factors involved with forward-looking information could cause actual events, results, performance, prospects and opportunities to differ materially from those expressed or implied by such forward-looking information. Forward-looking information in this news release includes, but is not limited to, the Company's objectives, goals or future plans, and statements, and the prospectivity of its exploration property portfolio for lithium mineralization. Important factors that could cause actual results to differ materially from Ion Energy's expectations include, among others, uncertainties relating to availability and costs of financing needed in the future, changes in equity markets, risks related to international operations, the actual results of current exploration activities, and delays in the development of projects. There can be no assurance that forward-looking statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/183462

News Provided by Newsfile via QuoteMedia

ION:CA
Lithium ION Energy

Lithium ION Energy Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Lithium ION Energy (TSXV:ION)

Lithium ION Energy


Keep reading...Show less
Lithium ION Energy Announces Completion of Debt Settlement

Lithium ION Energy Announces Completion of Debt Settlement

Lithium ION Energy Ltd. (TSXV: ION) (OTCQB: IONGF) (FSE: ZA4) ("ION" or the "Company") further to the announcement of March 13, 2024, confirms that it has completed debt settlement agreements with certain arm's length and non-arm's length creditors. Pursuant to the debt settlement agreements, the Company has settled an aggregate amount of $98,419 in debt, in consideration for which it will issue an aggregate of 393,675 common shares (the "Shares") of the Company at a deemed price of $0.25 per Share.

All Shares issued in relation to these debt settlements will be subject to a hold period expiring four months and one day after the date the Shares are issued, in accordance with applicable securities laws and the policies of the TSXV.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Lithium ION Energy Announces Warrant Extension

Lithium ION Energy Announces Warrant Extension

Lithium ION Energy Ltd (TSXV: ION) (OTCQB: IONGF) (FSE: ZA4) ("ION" or the "Company") announces today that it intends to extend the expiry date of an aggregate 11,500,000 outstanding common share purchase warrants of the Company (the "April Warrants") by 12 months to April 12, 2025 and an aggregate 4,000,000 outstanding common share purchase warrants of the Company (the "July Warrants" and collectively with the April Warrants, the "Warrants") by 12 months to July 20, 2025 (collectively with the extension of April Warrants, the "Extension").

The April Warrants were issued pursuant to a public offering which closed on April 13, 2021 and are set to expire on April 12, 2024. The April Warrants were issued pursuant to a warrant indenture dated April 13, 2021 between the Company and TSX Trust and each April Warrant entitles the holder thereof to acquire one common share of the Company at a price of CAD $0.70. The July Warrants were issued pursuant to a non-brokered private placement which closed on July 20, 2023 and are set to expire on July 20, 2024. Each July Warrant entitles the holder thereof to acquire one common share of the Company at a price of CAD $0.40.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Lithium ION Energy Announces Debt Settlement and Grant of Stock Options

Lithium ION Energy Announces Debt Settlement and Grant of Stock Options

Lithium ION Energy Limited (TSXV: ION) (OTCQB: IONGF) (FSE: ZA4) ("ION" or the "Company") announces that it has negotiated debt settlement agreements with certain arm's length and non-arm's length creditors. Pursuant to the debt settlement agreements, and subject to acceptance by the TSX Venture Exchange (the "TSXV"), the Company has settled an aggregate amount of $143,669 in debt, in consideration for which it will issue an aggregate of 606,675 common shares (the "Shares") of the Company at a deemed price of $0.24 per Share.

All Shares issued in relation to these debt settlements will be subject to a hold period expiring four months and one day after the date the Shares are issued, in accordance with applicable securities laws and the policies of the TSXV.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
TSX Venture Exchange Stock Maintenance Bulletins

TSX Venture Exchange Stock Maintenance Bulletins

TSX VENTURE COMPANIES

LITHIUM ion energy ltd. ("ION")
[formerly ion energy ltd. ("ION")]
BULLETIN TYPE: Name Change
BULLETIN DATE: August 30, 2023
TSX Venture Tier 2 Company

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
ION Energy Announces Corporate Update: Leadership Changes and Bliss Lake Agreement

ION Energy Announces Corporate Update: Leadership Changes and Bliss Lake Agreement

Ion Energy Limited (TSXV: ION) (OTCQB: IONGF) (FSE: 5YB) ("ION" or the "Company") is pleased to announce exciting leadership changes, as the Company continues on its rapid growth trajectory.

Robert Payment will be joining the Ion Energy team as Chief Financial Officer, as a seasoned CPA with 16 years of comprehensive experience spanning finance, reporting, regulatory compliance, public company administration, equity markets, and the financing of publicly traded companies. His career commenced in public practice focusing on the audit of public resource issuers, and since 2014 he has served as a CFO and consultant to a portfolio of companies listed on both the TSX Venture Exchange and the Canadian Securities Exchange (CSE).

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Victory is Pleased to Announce the Appointment of Gary Musil to the Company's Board of Directors and a Private Placement

Victory is Pleased to Announce the Appointment of Gary Musil to the Company's Board of Directors and a Private Placement

Victory Battery Metals Corp. (CSE:VR)(OTC PINK:VRCFF)(FWB:VR6) welcomes Gary Musil as a director of the Company, effective July 1, 2024. Gary Musil has more than 35 years of management and financial consulting experience and has served as an officer and director on numerous public companies since 1988. This experience has resulted in his overseeing the financial aspects and expenditures on exploration projects in Peru, Chile, Eastern Europe (Slovak Republic), and British Columbia, Ontario, Quebec, Saskatchewan and New Brunswick (Canada). Prior to his public company work, he was employed for 15 years with Dickenson Mines Ltd. and Kam-Kotia Mines Ltd., as the Controller for their producing silverleadzinc mine in the interior of British Columbia

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Albemarle Announces Quarterly Common Stock Dividend

Albemarle Announces Quarterly Common Stock Dividend

The Board of Directors of Albemarle Corporation (NYSE: ALB) announces that it has declared a quarterly common stock dividend of $0.405 per share. The dividend, which has an annualized rate of $1.62 is payable Oct. 1, 2024 to shareholders of record at the close of business as of Sept. 13, 2024 . For 30 consecutive years, Albemarle has raised its dividend.

Albemarle Corp. Logo. (PRNewsFoto/Albemarle Corporation)

About Albemarle
Albemarle Corporation (NYSE: ALB) leads the world in transforming essential resources into critical ingredients for mobility, energy, connectivity and health. We partner to pioneer new ways to move, power, connect and protect with people and planet in mind. A reliable and high-quality global supply of lithium and bromine allows us to deliver advanced solutions for our customers. Learn more about how the people of Albemarle are enabling a more resilient world at Albemarle.com , LinkedIn and on X (formerly known as Twitter) @AlbemarleCorp .

Albemarle regularly posts information to www.albemarle.com , including notification of events, news, financial performance, investor presentations and webcasts, non-GAAP reconciliations, U.S. Securities and Exchange Commission filings and other information regarding the company, its businesses and the markets it serves.

Forward-Looking Statements

Some of the information presented in this press release, including, without limitation, information related to future dividends and results, and all other information relating to matters that are not historical facts may constitute forward- looking statements within the meaning of the Private Securities Litigation Reform Act of 1995. Actual results could differ materially from the views expressed. Factors that could cause actual results to differ materially from the outlook expressed or implied in any forward-looking statement include, without limitation: changes in economic and business conditions; adverse changes in liquidity or financial or operating performance; changes in the demand for our products or the end-user markets in which our products are sold and the other factors detailed from time to time in the reports we file with the U.S. Securities and Exchange Commission, including those described under "Risk Factors" in our Annual Report on Form 10-K and our Quarterly Reports on Form 10-Q. These forward-looking statements speak only as of the date of this press release. We assume no obligation to provide any revisions to any forward-looking statements should circumstances change, except as otherwise required by securities and other applicable laws.

Investor Relations Contact: Meredith Bandy , +1 (980) 999-5768, meredith.bandy@albemarle.com
Media Contact: Peter Smolowitz
, +1 (980) 308-6310, media@albemarle.com

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/albemarle-announces-quarterly-common-stock-dividend-302198618.html

SOURCE Albemarle Corporation

News Provided by PR Newswire via QuoteMedia

Keep reading...Show less
Altech Batteries Ltd  Update on CERENERGY ABS60 Battery-pack Prototypes

Altech Batteries Ltd Update on CERENERGY ABS60 Battery-pack Prototypes

Perth, Australia (ABN Newswire) - Altech Batteries Limited (ASX:ATC) (FRA:A3Y) (OTCMKTS:ALTHF) is pleased to provide an update on the production of its CERENERGY(R) ABS60 BatteryPack prototypes. All 240 cells for the first ABS60 BatteryPack Prototype have now been fabricated, assembled and initialized at Fraunhofer IKTS Hermsdorf's pilot plant.

Highlights

- Prototype production is progressing well

- All CERENERGY(R) cells for the first 60 KWh Prototype completed

- Cell contacting system manufacturing finished and delivered

- Improved cell electrode design showing excellent results

- Cell quality tests by Fraunhofer delivering better than expected capacity

- Welding of cells to cell contacting system underway

- Completed modules will be mounted into ABS60 BatteryPack next week

To validate a homogeneous cathode material distribution, all cells were cycled through several testing stations at Fraunhofer IKTS Hermsdorf and Arnstadt.

IMPROVED CELL ELECTRODE DESIGN

During the fabrication of the two 60kWh CERENERGY(R) ABS60 BatteryPack prototypes, the Altech and Fraunhofer team made several design improvements to the cell's positive probe. These enhancements aimed to boost the cell's energy capacity and reduce the nickel content. The "V2" design of the positive probe allows for slightly faster charging and discharging while lowering the unit costs of the battery. Testing revealed that most cells had higher-than-expected energy capacities, an outstanding result that strongly supports the chosen electrode design. With all cells manufactured according to the series design and optimized processes, the best cells to date have been completed. The table below demonstrates that all the cells are meeting the expected specifications.

CELL CONTACTING SYSTEM COMPLETED

The Cell Contacting System (CCS) has undergone stringent testing and has now been completed and delivered by key supplier Hofer AG. The CCS was delivered to Fraunhofer IKTS in Dresden, where all parts of the modules will be collected to assemble each of the five modules. Each module contains 48 cells, that are currently being welded to the CCS by an external service provider.

After welding is completed, the ABS60 BatteryPack with its 60 kWh capacity can be completely assembled.

MODULE WELDING TRIALS

To guarantee the most time-efficient welding, a unique tool was designed and built at Xenon, which is responsible for welding and quality control across the 120 MWh battery plant. After completing the welding tool, it was shipped to an external laboratory, accompanied by a test module and several trial cells. The aim was to determine the best working parameters and to proof the handling of certain parts of the module.

The trials were successfully finished.

CELL MANUFACTURING PROGRESSING WELL

All 240 cells for the first ABS60 BatteryPack Prototype have been assembled and initialised at Fraunhofer IKTS, Hermsdorf. To validate a homogeneous cathode material distribution, all cells were cycled through several testing stations at Fraunhofer IKTS Hermsdorf and Arnstadt.

INTERIM CELL TESTING

At Fraunhofer IKTS in Hermsdorf, all cells were scanned using a unique X-ray microtomography device that enables the ability to look inside cells after they are hermetically closed. This is required to ensure the most homogeneous material distribution inside the cells as well as the best possible alignment of cell components e.g. electrode. The results have been excellent to date. Another quality assurance procedure involved cycling cells to ensure the electrical requirements and parameters are operating as designed.

MODULE WELDING AND BATTERYPACK ASSEMBLY

After every cell passed all quality checks, the modules containing the cells were shipped to the laboratory for welding onto the CCS. By using the predetermined parameters for welding, all modules have been successfully welded. After completion, the modules will be shipped to Fraunhofer IKTS, Dresden, where all five modules will then be mounted into the ABS60 BatteryPack and the first Prototype will be completed.

This will enable testing and demonstration to potential customers, to prove individual use cases for each customer.

ABOUT THE ABS60 - BATTERYPACK

The 60kWh Altech Battery Pack consists of five 12kWh modules with 48 cells each, mounted on top of each other and sealed in a thermal isolated stainless steel hood housing. The Battery management system is mounted at the base. To maintain thermal self-sufficiency, an insulation hood was designed, where the required heat of the system can be maintained inside the BatteryPack as long as possible, although the outer surface only has ambient temperature. This was achieved by using vacuum insulation. The base of each module is designed to accommodate folklift transport for easy mounting into the GridPack.

Commenting on the progress, MD and CEO Iggy Tan stated "Altech's team in Germany, together with its joint venture partner Fraunhofer, and with the assistance of key suppliers, have made excellent progress on the fabrication of two 60kWh CERENERGY(R) ABS60 BatteryPack prototypes. All components for the first BatteryPack have now been fabricated. Altech is now completing the welding of the cells to the Cell Contacting System, after which the five completed battery modules will be delivered to Fraunhofer IKTS in Dresden, where all five modules will be mounted into the ABS60 BatteryPack and the first ABS60 Prototype will be completed. The BatteryPack will then be available for testing and demonstration to potential customers, thereby assisting Altech in securing offtake and finance for the 120MWh CERENERGY(R) battery plant to be constructed on Altech's land in Germany".

*To view tables and figures, please visit:
https://abnnewswire.net/lnk/O449B2I4



About Altech Batteries Ltd:

Altech Batteries Limited (ASX:ATC) (FRA:A3Y) is a specialty battery technology company that has a joint venture agreement with world leading German battery institute Fraunhofer IKTS ("Fraunhofer") to commercialise the revolutionary CERENERGY(R) Sodium Alumina Solid State (SAS) Battery. CERENERGY(R) batteries are the game-changing alternative to lithium-ion batteries. CERENERGY(R) batteries are fire and explosion-proof; have a life span of more than 15 years and operate in extreme cold and desert climates. The battery technology uses table salt and is lithium-free; cobalt-free; graphite-free; and copper-free, eliminating exposure to critical metal price rises and supply chain concerns.

The joint venture is commercialising its CERENERGY(R) battery, with plans to construct a 100MWh production facility on Altech's land in Saxony, Germany. The facility intends to produce CERENERGY(R) battery modules to provide grid storage solutions to the market.

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Nevada Sunrise Initiates Data Review to Develop New Drill Targets at the Coronado Copper Project, Nevada

Nevada Sunrise Initiates Data Review to Develop New Drill Targets at the Coronado Copper Project, Nevada

Nevada Sunrise Metals Corporation (TSXV: NEV) (OTCBB: NVSGF) ("Nevada Sunrise" or the "Company") is pleased to announce that the Company has initiated a geological and geophysical data review on its Coronado Copper Project (" Coronado ", or the " Project ") located in Pershing County, Nevada approximately 48 kilometers (30 miles) southeast of Winnemucca . The purpose of the Coronado data review is to identify new, shallow drill targets in an area of the Project where historical drilling in 1976 identified high-grade copper mineralization.

Highlights of the Coronado Copper Project

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
NextSource Materials Appoints Jaco Crouse as Chief Financial Officer

NextSource Materials Appoints Jaco Crouse as Chief Financial Officer

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or the "Company") announces the appointment of Jaco Crouse as Chief Financial Officer (CFO) of the Company as part of its global growth strategy

Mr. Crouse today replaces Marc Johnson who has served as CFO since October 2015. Mr. Johnson will continue to provide consulting services to the Company to assist with the smooth transition of this role. The Board of Directors of the Company would like to thank Mr. Johnson for his service to the Company over the years and wishes him well in his future endeavours.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
Nevada Sunrise Signs Indicative Term Sheet to Sell Remaining Interest in the Kinsley Mountain Gold Project, Nevada

Nevada Sunrise Signs Indicative Term Sheet to Sell Remaining Interest in the Kinsley Mountain Gold Project, Nevada

Nevada Sunrise Metals Corp. (TSXV: NEV) (OTCBB: NVSGF) ("Nevada Sunrise" or the "Company") announced today that it has signed a non-binding, indicative term sheet with CopAur Minerals Inc. (" CopAur ") for CopAur to acquire Nevada Sunrise's remaining ownership interest in the Kinsley Mountain Gold Project in Nevada (" Kinsley Mountain "). If the transaction is completed, CopAur will own 100% of Kinsley Mountain .

Nevada Sunrise Metals Corporation Logo (CNW Group/Nevada Sunrise Metals Corporation)

The indicative term sheet outlines a potential transaction whereby CopAur would acquire Nevada Sunrises' 18.74% ownership interest in Kinsley Mountain in consideration of the payment of CDN$475,000 and the issuance of 1,000,000 common shares of CopAur (the "Shares"). The Shares would be deposited in escrow and released in successive releases of 250,000 Shares once every calendar quarter commencing after expiry of the four-month statutory hold period following the closing date. The terms of the transaction are indicative and the final terms are subject to the negotiation and completion of a definitive agreement on terms acceptable to Nevada Sunrise and CopAur. The transaction is subject to a number of conditions including CopAur arranging a financing in the amount of a minimum of CDN$475,000 , completion of satisfactory due diligence, and the fulfilment of various closing conditions, including acceptance by the TSX Venture Exchange.

About Kinsley Mountain

Kinsley Mountain was a historical past producer that yielded 138,000 ounces of near-surface, open-pit oxide gold between 1995 and 1999, and currently hosts a compliant National Instrument 43-101 mineral resource. A technical report on Kinsley Mountain entitled "Technical Report of the Kinsley Project, Elko and White Pine Counties, Nevada, U.S.A. ", dated June 21, 2021 , with an effective date of May 5, 2021 , prepared by Michael M. Gustin and Gary L. Simmons , is available for review under New Placer Dome Gold Corp.'s issuer profile on sedarplus.ca

About Nevada Sunrise

Nevada Sunrise is a junior mineral exploration company with a strong technical team based in Vancouver, BC , Canada , that holds interests in lithium, gold and copper exploration projects located in the State of Nevada, USA .

Nevada Sunrise owns 100% interests in the Gemini, Jackson Wash and Badlands lithium projects, all of which are located in the Lida Valley in Esmeralda County, NV , and in the Pelican lithium project in Saskatchewan, Canada . The Company owns Nevada Water Right Permit 86863, also located in the Lida Valley basin, near Gold Point, NV.

Nevada Sunrise has the right to earn a 100% interest in the Coronado Copper Project , located approximately 48 kilometers (30 miles) southeast of Winnemucca, NV.

The Company owns an 18.74% interest in the Kinsley Mountain Gold Project near Wendover, NV , in a joint venture with CopAur, which is now the subject of a potential transaction between Nevada Sunrise and CopAur.

FORWARD LOOKING STATEMENTS

This release may contain forward–looking statements. Forward looking statements are statements that are not historical facts and are generally, but not always, identified by the words "expects", "plans", "anticipates", "believes", "intends", "estimates", "projects", "potential" and similar expressions, or that events or conditions "will", "would", "may", "could" or "should" occur and include disclosure of anticipated exploration activities. Although the Company believes the expectations expressed in such forward–looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results may differ materially from those in forward looking statements. Forward–looking statements are based on the beliefs, estimates and opinions of the Company's management on the date such statements were made. The Company expressly disclaims any intention or obligation to update or revise any forward–looking statements whether as a result of new information, future events or otherwise.

Such factors include, among others, risks related to: the completion of the potential transaction with CopAur Minerals Inc. for the purchase of the Company's remaining participating interest in the Kinsley Mountain Gold Project joint venture; reliance on technical information provided by third parties on any of our exploration properties; changes in project parameters as plans continue to be refined; current economic conditions; future prices of commodities; possible variations in grade or recovery rates; failure of equipment or processes to operate as anticipated; the failure of contracted parties to perform; labor disputes and other risks of the mining industry; delays due to pandemic; delays in obtaining governmental approvals, financing or in the completion of exploration, as well as those factors discussed in the section entitled "Risk Factors" in the Company's Management Discussion and Analysis for the Six Months Ending March 31 , 2024,  which is available under Company's SEDAR profile at www.sedar.com .

Although Nevada Sunrise has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking information, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that such information will prove to be accurate as actual results and future events could differ materially from those anticipated in such statements. Nevada Sunrise disclaims any intention or obligation to update or revise any forward-looking information, whether as a result of new information, future events or otherwise. Accordingly, readers should not place undue reliance on forward-looking information.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SOURCE Nevada Sunrise Metals Corporation

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/July2024/08/c5338.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Lithium ION Energy

Lithium ION Energy Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×