
July 17, 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 73% complete as of 30 June 2022. Significant equipment arrivals over the last month include the remaining mill equipment, secondary and tertiary cone crushers, and the remaining LNG tanks. The completion of the installation of 16,000 solar panels also delivers another significant construction milestone.
Managing Director, Tony James commented, “Construction activities are rapidly progressing with concrete poured at 2,378m3 (95% complete) and structural steel installation already up to 237 tonnes (42% complete). Arrival of key overseas supplied equipment being the remaining mill equipment, secondary and tertiary cone crushers, and LNG tanks has certainly reduced risk and energised the remaining work programs.
Decline mining delays occurred over 12 days in June, when the decline intercepted an un-grouted drill hole, which produced water, requiring an increase in pumping capacity. This was quickly rectified, and the mine plans were updated to keep the mining schedule aligned with the plant construction and commissioning timeframe. Underground grade control drilling continued in June in preparation for ore mining as planned”.
Figure 1 – Abra mine construction site (photo: 28 June 2022)
Update on Abra Project progress
Overall progress continues to remain in line for Project completion followed by first commercial production in Q1 CY2023. The processing plant engineering, procurement and construction has reached 79% complete. Remaining items on the key equipment order list shown in Table 1 which are currently not received are the flotation cells and the regrind mill. The flotation cells are completed and are waiting shipping from China and the regrind mill is currently shipping from Germany and is expected in Melbourne by 12th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. The arrival of key items since the last update has enabled GR Engineering to consolidate their remaining work schedules and plans.
Mine decline development was delayed in June for 12 days when the west decline intercepted an un-grouted diamond drill hole forcing an upgrade in the mine dewatering capacity. A total of 128m was developed prior to the delay, taking the west decline down to 1,357mRL which is 44m vertically above the orebody. During the delay the mine installed its primary ventilation fan on the surface and upgraded the underground power reticulation. Once this work was completed, the hole was plugged, and mining resumed.
A revised mining plan has been completed and put in place to ensure that following this development delay, mining targets remain in line with the plant completion and commissioning timeframe.
In surface bulk earthworks, good progress was made on the tailing’s storage facility (“TSF”) during June. The final works package associated with the remaining non-processing infrastructure is progressing as planned.
Owners' costs and contingencies remain within budget.
Figure 2 - Progress of the Abra underground mine development to the 1 July (yellow).
Click here for the full ASX Release
This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
INN Article Notification
The Conversation (0)
12 September 2022
Galena Mining
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
19 May
Prince Reports 27.43 Metres Grading 93.7 g/t Silver, 12.0% Mn, 2.29% Pb and 2.48% Zn at Its Prince Silver Project in Nevada;
Mobilizes Third RC Drill Rig to Accelerate Ongoing 9,000-metre Drill Program
Prince Silver Corp. (CSE: PRNC) (OTCQX: PRNCF) (FSE: T130) ("Prince Silver" or the "Company") is pleased to announce additional assay results from its ongoing 9,000-metre reverse circulation ("RC") drilling program at the Company's Prince Silver Project ("Prince" or the "Prince Project"),... Keep Reading...
14 May
Elemental Secures Panuco Silver-Gold Royalty in US$239 Million Vizsla Deal
Elemental Royalty (TSX:ELE,NASDAQ:ELE) has inked a US$239 million deal to acquire Vizsla Royalties (TSXV:VROY,OTCQX:VROYF), securing long-life exposure to the Panuco silver-gold project. The acquisition grants Elemental an uncapped 2 to 3.5 percent net smelter return royalty on the Mexico-based... Keep Reading...
07 May
Record Silver Price a Key Q1 Tailwind for Miners
Following an unprecedented first quarter that saw silver prices break into triple digits before sharply correcting, the sector’s top producers registered massive cash generation and bolstered balance sheets. Silver achieved a historic milestone early in the first quarter, surging past US$100 an... Keep Reading...
05 May
Silver Stocks: 5 Biggest Silver-mining Companies in 2026
Silver mining companies are being supported by a silver price bull run in 2026. After climbing through 2025, silver broke its all-time high set in 1980 in October before reaching a new high of US$121.62 per ounce on January 29.The factors driving the metal's rise remain, most notably tightening... Keep Reading...
30 April
Lynette Zang: Silver Fuse, Gold Anchor — This Currency Lifecycle is Ending
Lynette Zang, founder and CEO of Zang International, explains what gold and silver are saying about the world today, noting that while spot prices for the precious metals are down, they are on track to eventually assume their true fundamental value. "What I really want people to understand is... Keep Reading...
Latest News
Interactive Chart
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00







