
July 17, 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 73% complete as of 30 June 2022. Significant equipment arrivals over the last month include the remaining mill equipment, secondary and tertiary cone crushers, and the remaining LNG tanks. The completion of the installation of 16,000 solar panels also delivers another significant construction milestone.
Managing Director, Tony James commented, “Construction activities are rapidly progressing with concrete poured at 2,378m3 (95% complete) and structural steel installation already up to 237 tonnes (42% complete). Arrival of key overseas supplied equipment being the remaining mill equipment, secondary and tertiary cone crushers, and LNG tanks has certainly reduced risk and energised the remaining work programs.
Decline mining delays occurred over 12 days in June, when the decline intercepted an un-grouted drill hole, which produced water, requiring an increase in pumping capacity. This was quickly rectified, and the mine plans were updated to keep the mining schedule aligned with the plant construction and commissioning timeframe. Underground grade control drilling continued in June in preparation for ore mining as planned”.
Figure 1 – Abra mine construction site (photo: 28 June 2022)
Update on Abra Project progress
Overall progress continues to remain in line for Project completion followed by first commercial production in Q1 CY2023. The processing plant engineering, procurement and construction has reached 79% complete. Remaining items on the key equipment order list shown in Table 1 which are currently not received are the flotation cells and the regrind mill. The flotation cells are completed and are waiting shipping from China and the regrind mill is currently shipping from Germany and is expected in Melbourne by 12th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. The arrival of key items since the last update has enabled GR Engineering to consolidate their remaining work schedules and plans.
Mine decline development was delayed in June for 12 days when the west decline intercepted an un-grouted diamond drill hole forcing an upgrade in the mine dewatering capacity. A total of 128m was developed prior to the delay, taking the west decline down to 1,357mRL which is 44m vertically above the orebody. During the delay the mine installed its primary ventilation fan on the surface and upgraded the underground power reticulation. Once this work was completed, the hole was plugged, and mining resumed.
A revised mining plan has been completed and put in place to ensure that following this development delay, mining targets remain in line with the plant completion and commissioning timeframe.
In surface bulk earthworks, good progress was made on the tailing’s storage facility (“TSF”) during June. The final works package associated with the remaining non-processing infrastructure is progressing as planned.
Owners' costs and contingencies remain within budget.
Figure 2 - Progress of the Abra underground mine development to the 1 July (yellow).
Click here for the full ASX Release
This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
Alert Options
No alert set
INN Article Notification
Alert Option
You will be notified when this event occurs. No additional settings needed.
The Conversation (0)
23 July
Silver Miners Post Record Q2 Output Despite Volatility
Silver prices fell more than 22 percent in the second quarter of 2026, as high volatility and macroeconomic pressures pulled the metal down from its earlier heights.However, top miners insulated their balance sheets by turning to production, driving record throughputs and strong operational... Keep Reading...
22 July
Shawn Khunkhun: Silver, Gold in Pre-Mania Phase, Here's What Comes Next
Shawn Khunkhun of Contango Silver & Gold (TSX:CTGO,NYSEAMERICAN:CTGO) shares his thoughts on the outlook for silver, saying that while he expects higher prices long term, the white metal could still go lower than where it is today. "Could we see US$40 (per ounce) silver, could we see US$50... Keep Reading...
21 July
Top 5 Canadian Silver Stocks in 2026
Silver achieved a triple-digit price in the first quarter of 2026, drawing attention to silver-mining companies.During January, the silver price reached an all-time high of US$121.62 per ounce. Although prices came down significantly in the second quarter, silver still remains above its previous... Keep Reading...
08 July
First Majestic Offloads San Martin Mine in US$90 Million Deal
First Majestic Silver (TSX:AG,NYSE:AG) has agreed to sell its past-producing San Martin silver mine in Mexico for US$90 million in cash, furthering the company’s push to monetize non-core assets held on care and maintenance.The perimeter of the sale includes the Jalisco group of properties,... Keep Reading...
03 July
Silver Price Trends: Q2 2026 Review and Forecast
In the second quarter of 2026, silver retreated significantly from the triple-digit prices reached in January.The silver market is facing extreme volatility from the geopolitical and economic uncertainty surrounding the Iran war, the inflationary energy shock, a stronger US dollar and shifting... Keep Reading...
18 June
Brixton Metals Launches Drilling Campaign at Langis Project
Brixton Metals (TSXV:BBB) has launched a 60,000-meter drilling campaign at its Langis silver-cobalt-nickel project in northeastern Ontario, Canada. The company said in an announcement that the drill campaign is “the largest in the history of the project.”In an interview with VRIC Media, CEO Gary... Keep Reading...
Latest News
Interactive Chart
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00







