Ivanhoe Mines Announces Kamoa-Kakula Achieved Record Copper Production of 35,856 Tonnes in May

Monthly copper production equivalent to annual production of approximately 430,000 tonnes

New daily ore milling record achieved at Kamoa-Kakula, equivalent to an annual rate of approximately 9.8 million tonnes

Phase 1 and 2 concentrators continue to operate at above-design copper recoveries

Phase 3 expansion and smelter advancing on schedule for first production in Q4 2024

Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng "Miles" Sun announced today that the Kamoa-Kakula Copper Complex in the Democratic Republic of Congo achieved a monthly production record of 35,856 tonnes of copper in concentrate during May.

Copper production during April was 34,826 tonnes of copper in concentrate, bringing quarter-to-date production to 70,682 tonnes.

A new daily milling record of 29,366 tonnes of ore was also achieved by the Phase 1 and 2 concentrators. This is equivalent to an annual milling rate of 9.8 million tonnes per annum (after accounting for availability). This record far exceeds the increased milling capacity of 9.2 million tonnes per annum following the debottlenecking program of the Phase 1 and 2 concentrators, which was completed in February 2023.

Average copper recoveries for the month were 87%, above the Phase 1 and 2 concentrator nameplate recovery rates.

Construction activities for the Phase 3 expansion, including the largest copper smelter in Africa, with a capacity of 500,000 tonnes of 99+%-pure copper anodes, are advancing on schedule for first production in the fourth quarter of 2024.

Watch a June 2023 video of operations and construction activities at Kamoa-Kakula: https://vimeo.com/833031454/fb6ea4e192

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3396/168745_9d56d74de4c7a95e_002.jpg

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/168745_9d56d74de4c7a95e_002full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3396/168745_9d56d74de4c7a95e_003.jpg

Concrete foundations for the two ball mills of the Phase 3 concentrator on the left, with foundations for the flotation cells on the right. The first batch of ball mill foundation steel is expected at site later this month. The first ball mill, supplied by CITIC Heavy Industries of Luoyang, China, also is expected to be delivered later this month.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/168745_9d56d74de4c7a95e_003full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3396/168745_9d56d74de4c7a95e_004.jpg

Concrete foundations for the Phase 3 concentrator tailings thickener. Over 60% of concrete has been poured to date and approximately 6,000 tonnes of the required 7,100 tonnes of structural steel have been fabricated, 50% of which has been shipped to site.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/168745_9d56d74de4c7a95e_004full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3396/168745_9d56d74de4c7a95e_005.jpg

Steel erection of Kamoa-Kakula's direct-to-blister flash furnace and the electric slag cleaning furnace. Overall smelter construction is now approximately 50% complete. Fabrication of the anode furnaces, ball mill and SAG mill, also manufactured by CITIC Heavy Industries, is complete with shipping expected imminently.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/168745_9d56d74de4c7a95e_005full.jpg

Cannot view this image? Visit: https://images.newsfilecorp.com/files/3396/168745_9d56d74de4c7a95e_006.jpg

Construction of new on-site accommodation. There are approximately 14,000 employees and contractors at site; approximately 97% of Kamoa's employees are Congolese.

To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/3396/168745_9d56d74de4c7a95e_006full.jpg

About Ivanhoe Mines

Ivanhoe Mines is a Canadian mining company focused on advancing its three principal projects in Southern Africa; the expansion of the Kamoa-Kakula Copper Complex in the DRC, the construction of the tier-one Platreef palladium-rhodium-platinum-nickel-copper-gold project in South Africa; and the restart of the historic ultra-high-grade Kipushi zinc-copper-germanium-silver mine, also in the DRC.

Ivanhoe Mines also is exploring for new copper discoveries across its circa 2,400km2 of 90-100% owned exploration licences in the Western Foreland, located adjacent to, or in close proximity to, the Kamoa-Kakula Copper Complex in the DRC.

Information contact

Investors

Vancouver: Matthew Keevil +1.604.558.1034

London: Tommy Horton +44 7866 913 207

Media

Tanya Todd +1.604.331.9834

Forward-looking statements

Certain statements in this news release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the company, its projects, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified using words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events, or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. These statements reflect the company's current expectations regarding future events, performance and results and speak only as of the date of this news release.

Such statements include without limitation, the timing and results of: (i) statements regarding Kamoa-Kakula's monthly copper production record being equivalent to annual production of approximately 430,000 tonnes; (ii) statements that Kamoa-Kakula's new daily mill throughput record is equivalent to an annual rate of approximately 9.8 million tonnes; (iii) statements that Kamoa-Kakula's Phase 3 expansion and smelter, which is the largest copper smelter in Africa with a capacity of 500,000 tonnes, are advancing on schedule for first production in Q4 2024; (iv) statements that the first batch of ball mill foundation steel and the first ball mill for Kamoa-Kakula's Phase 3 are expected to be delivered to site later this month; and (v) statements that Kamoa-Kakula's Phase 3 anode furnaces, ball mill and SAG mill are expected to be shipped imminently.

Furthermore, concerning this specific forward-looking information concerning the operation and development of the Kamoa-Kakula Copper Complex, the company has based its assumptions and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of related commodities; (vi) the availability of equipment and facilities necessary to complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and engineering problems; (ix) accidents or acts of sabotage or terrorism; (x) currency fluctuations; (xi) changes in regulations; (xii) the compliance by joint venture partners with terms of agreements; (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies; (xv) the ability to raise sufficient capital to develop such projects; (xvi) changes in project scope or design; (xvii) recoveries, mining rates and grade; (xviii) political factors; (xix) water inflow into the mine and its potential effect on mining operations; and (xx) the consistency and availability of electric power.

Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether such results will be achieved. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to, the factors discussed above and under the "Risk Factors" section in the company's MD&A for the three months ended March 31, 2023, and its Annual Information Form, and elsewhere in this news release, as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations.

Although the forward-looking statements contained in this news release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this news release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release.

The company's actual results could differ materially from those anticipated in these forward-looking statements as a result of the factors outlined in the "Risk Factors" section and elsewhere in the company's MD&A for the three months ended March 31, 2023, and its Annual Information Form.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/168745

News Provided by Newsfile via QuoteMedia

IVN:CA,IVPAF
The Conversation (0)

S&P Dow Jones Indices Announces Changes to the S&P/TSX Composite Index

The shareholders of Lundin Mining Corporation (TSX: LUN) together with BHP Group Limited and Filo Corp. (TSX: FIL) have agreed to the terms of a Plan of Arrangement resulting in the combination of the two companies. Each share of Filo Corp. will be exchanged for 2.3578 shares of Lundin Mining or C$33.00 cash subject to proration of a max cash of C$2,767 million and maximum share consideration of 92.1 million Lundin Mining shares.

In expectation of the arrangement closing, Filo Corp. will be removed from the S&P/TSX Composite Index prior to the open of trading on January 15, 2025 . The shares outstanding of Lundin Mining will be increased at the same time to reflect the issuance of shares.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

S&P Dow Jones Indices Announces Changes to the S&P/TSX Composite Index

The shareholders of Lundin Mining Corporation (TSX: LUN) together with BHP Group Limited and Filo Corp. (TSX: FIL) have agreed to the terms of a Plan of Arrangement resulting in the combination of the two companies. Each share of Filo Corp. will be exchanged for 2.3578 shares of Lundin Mining or C$33.00 cash subject to proration of a max cash of C$2,767 million and maximum share consideration of 92.1 million Lundin Mining shares.

In expectation of the arrangement closing, Filo Corp. will be removed from the S&P/TSX Composite Index prior to the open of trading on January 15, 2025 . The shares outstanding of Lundin Mining will be increased at the same time to reflect the issuance of shares.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
BHP headquarters.

BHP Reveals Cohort for Xplor 2025 Critical Minerals Program

Mining giant BHP (ASX:BHP,NYSE:BHP,LSE:BHP) introduced its Xplor 2025 cohort on Monday (January 6), choosing eight out of hundreds of applicants worldwide.

Under Xplor 2025’s terms, each of the companies is entitled to receive an equity-free grant of up to US$500,000 and access to a network of BHP and external industry experts to build out and accelerate their exploration concepts.

The selected companies and the countries they focus on are as follows:

Keep reading...Show less

Filo Sets Election Deadline and Announces Anticipated Closing Date in Connection with the Acquisition by BHP and Lundin Mining

Filo Corp. (TSX: FIL) (Nasdaq First North Growth Market: FIL) (OTCQX: FLMMF) (" Filo " or the " Company ") is pleased to announce that the deadline for registered shareholders (the " Registered Shareholders ") of the issued and outstanding common shares of Filo (the " Filo Shares ") and for holders of stock options of Filo (the " Optionholders ") to make elections in respect of the consideration receivable pursuant to the Arrangement (as defined below) is 5:00 P.M. (Toronto Time) on January 9, 2025 (the " Election Deadline "). PDF Version

The letter of transmittal and election form (the " Letter of Transmittal ") outlines the necessary documentation and information required to be sent to the depositary for the Arrangement, Computershare Investor Services Inc. (the " Depositary "), by each Registered Shareholder and Optionholder in order to receive the consideration to which they are entitled under the Arrangement, and make an election with respect to the form of consideration they wish to receive. For complete instructions, please refer to the Letter of Transmittal previously mailed to Registered Shareholders and Optionholders on December 12, 2024 and also available under Filo's profile on SEDAR+ at www.sedarplus.ca and on the Company's corporate website at http://filocorp.com/investors/corporate-filings/ .

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Business handshake.

Cygnus Metals and Doré Copper Complete Merger, Plan 2025 Drill Program at Chibougamau

Cygnus Metals and Doré Copper Mining said on Wednesday (January 1) that they have completed their merger.

The combined entity will be a critical minerals explorer and developer with two core assets in Québec, Canada.

Cygnus acquired all of the issued and outstanding common shares of Doré on Tuesday (December 31) through a Canadian statutory plan of arrangement, finalizing the deal. Cygnus shares are listed on the ASX under the symbol CY5, and are expected to start trading on the TSXV under the symbol CYG on or about Friday (January 3).

Keep reading...Show less
Copper ore.

Copper Price Forecast: Top Trends for Copper in 2025

Copper prices saw impressive gains in 2024, even breaking the US$5 per pound mark in May. However, the red metal's gains didn't last, and by the end of the year copper had retreated back to the US$4 range.

The start of 2025 could be eventful, with Donald Trump returning to the Oval Office, a new stimulus package coming into effect in China and a continued push for greener technologies around the world.

What will these factors mean for copper prices in the new year? Will they rise, or can investors expect the base metal to remain rangebound? Here's a look at what experts see coming for the important commodity.

Keep reading...Show less

Latest Press Releases

Related News

×