Hombre Muerto West Project Update

Hombre Muerto West Project Update

WEST PERTH, AU / ACCESS Newswire / September 23, 2026 / Galan Lithium Limited (ASX:GLN,OTC:GLNLF) (Galan or the Company) is pleased to provide the following update on the production ramp-up of its Hombre Muerto West (HMW) Phase 1 lithium chloride operation in Catamarca, Argentina.

Figure 1. Aerial view of HMW Phase 1 final evaporation ponds

Production Ramp-Up and First Sales

The ramp-up of the HMW Phase 1 operation continues to progress, with the productivity of the nanofiltration plant keeping pace with current site evaporation rates. First LiCl concentrate sales remain on track for delivery in Q4 CY2026. Galan is confident that, as the warmer seasonal conditions arrive over the coming months, the initial targeted throughput rate of 4ktpa LCE should be achieved in the first half of calendar year 2027.

Figure 2. LiCl concentrate pond following impurity removal.

Figure 3. Aerial view of the HMW site

The nanofiltration plant, which removes impurities from the HMW brine ahead of further concentration, continues to perform in line with piloting results and Company expectations. The plant has recorded over 3 months of data with a 98% or greater rejection of sulphate. Impurity separation and recoveries achieved to date support the upgrading of LiCl concentrate to up the targeted 6% Li content.

The Puna region in the Andes, where HMW is located, has endured one of the most severe winter periods in recent history with significant snowfall and wind. Notwithstanding, HMW operations have continued safely with minor periods where operations were suspended. To provide greater operational resiliency through future winters, Authium Limited plans to construct and mobilise to site an additional pressure vessel skid which would augment the existing Phase 1 plant capacity. Additionally, earthworks associated with the expansion of Phase 1 HMW to 5.2ktpa have commenced at site, with the higher production volumes expected to be realised in the second half of calendar year 2027.

Galan's Managing Director Juan Pablo Vargas de la Vega commented:

"We are pleased with the continued progress of the ramp-up at Hombre Muerto West. The nanofiltration plant is performing in line with our expectations, and the additional pressure vessel capacity being installed by Authium will further strengthen the plant's resilience. With productivity continuing to improve and warmer conditions approaching, we remain confident in reaching our initial 4ktpa throughput target and delivering first LiCl concentrate sales in the fourth quarter of this year."

For and on behalf of the Galan Board.

For further information contact:

COMPANY MEDIA
Juan Pablo ("JP") Vargas de la Vega Matt Worner
Managing Director Vector Advisors
jp@galanlithium.com.au mworner@vectoradvisors.au
+ 61 8 9214 2150 +61 429 522 924

SOURCE: Galan Lithium Limited



View the original press release on ACCESS Newswire

News Provided by ACCESS Newswire via QuoteMedia

GLN:AU
The Conversation (0)
Galan Lithium

Galan Lithium

Developing high-grade lithium brine projects in Argentina

Developing high-grade lithium brine projects in Argentina Keep Reading...
Successful Due Diligence Ends - $20M Placement To Proceed

Successful Due Diligence Ends - $20M Placement To Proceed

Galan Lithium (GLN:AU) has announced Successful Due Diligence Ends - $20m Placement To ProceedDownload the PDF here. Keep Reading...
Final At-The-Market Raise for 2025

Final At-The-Market Raise for 2025

Galan Lithium (GLN:AU) has announced Final At-The-Market Raise for 2025Download the PDF here. Keep Reading...
Quarterly Activities and Cash Flow Report

Quarterly Activities and Cash Flow Report

Galan Lithium (GLN:AU) has announced Quarterly Activities and Cash Flow ReportDownload the PDF here. Keep Reading...
Incentive Regime for HMW Project in Argentina

Incentive Regime for HMW Project in Argentina

Galan Lithium (GLN:AU) has announced Incentive Regime for HMW Project in ArgentinaDownload the PDF here. Keep Reading...
Trading Halt

Trading Halt

Galan Lithium (GLN:AU) has announced Trading HaltDownload the PDF here. Keep Reading...
SAGA Metals Reports Final Titanium, Vanadium and Iron Assays from MRE Drilling--Maiden Mineral Resource Estimate Imminent

SAGA Metals Reports Final Titanium, Vanadium and Iron Assays from MRE Drilling--Maiden Mineral Resource Estimate Imminent

MRE PROGRAM HIGHLIGHTS:22,432 METRES. 85 HOLES. DRILLING COMPLETE. SAGA's MRE drilling campaign completed in less then ten months across Trapper North, Transition and South zones.100% MINERALIZATION HIT RATE WITH BROAD OXIDE INTERCEPTS. Every MRE hole intersected oxide mineralization, with... Keep Reading...
SAGA Metals Reports Final Titanium, Vanadium and Iron Assays from MRE Drilling-Maiden Mineral Resource Estimate Imminent

SAGA Metals Reports Final Titanium, Vanadium and Iron Assays from MRE Drilling-Maiden Mineral Resource Estimate Imminent

MRE PROGRAM HIGHLIGHTS: 22,432 METRES. 85 HOLES. DRILLING COMPLETE. SAGA's MRE drilling campaign completed in less then ten months across Trapper North, Transition and South zones. 100% MINERALIZATION HIT RATE WITH BROAD OXIDE INTERCEPTS. Every MRE hole intersected oxide mineralization, with... Keep Reading...
Quarterly Activities/Appendix 5B Cash Flow Report

Quarterly Activities/Appendix 5B Cash Flow Report

QEM Limited (QEM:AU) has announced Quarterly Activities/Appendix 5B Cash Flow ReportDownload the PDF here. Keep Reading...
VanadiumCorp and Université de Sherbrooke Announce Publication of Peer-Reviewed Research on Lac Doré Vanadiferous Titanomagnetite

VanadiumCorp and Université de Sherbrooke Announce Publication of Peer-Reviewed Research on Lac Doré Vanadiferous Titanomagnetite

(TheNewswire) Vancouver, British Columbia TheNewswire October 13, 2026 Vanadiumcorp Resource Inc. (TSXV: VRB) (OTCQB: VRBFF) (FSE: NWN) ("VanadiumCorp" or the "Company") is pleased to announce the publication of a peer-reviewed scientific paper entitled "Mechanical Activation of Vanadiferous... Keep Reading...
Lithium Argentina to Release Third Quarter 2026 Results on November 10, 2026

Lithium Argentina to Release Third Quarter 2026 Results on November 10, 2026

Lithium Argentina AG ("Lithium Argentina" or the "Company") (TSX: LAR) (NYSE: LAR) will release its third quarter 2026 earnings results before market open on Tuesday, November 10, 2026. The Company will hold a webcast and conference call to discuss its third quarter 2026 results on Tuesday,... Keep Reading...
SAGA Metals Drills 495.6 m at 37.86% Fe2O3, 5.51% TiO2, 0.273% V2O5 Including 68.2 m at 52.95% Fe2O3, 8.57% TiO2, 0.381% V2O5 at Radar Critical Minerals Project in Labrador

SAGA Metals Drills 495.6 m at 37.86% Fe2O3, 5.51% TiO2, 0.273% V2O5 Including 68.2 m at 52.95% Fe2O3, 8.57% TiO2, 0.381% V2O5 at Radar Critical Minerals Project in Labrador

Saga Metals Corp. ("SAGA" or the "Company") (TSXV: SAGA) (OTCQX: SAGMF) (FSE: 20H), a North American exploration company focused on critical mineral discoveries, is pleased to report additional assay results from drill holes R-0082, -0083, -0084, -0085, -0086, and -0087 drilled as part of its... Keep Reading...

Interactive Chart

Latest Press Releases

Related News