HMW Plant in Transit to Site, Phase 1 on Track

HMW Plant in Transit to Site, Phase 1 on Track

Highlights:

  • Nano-filtration plant has been assembled and tested off-site and is now in transit to Hombre Muerto West (HMW)

  • Phase 1 construction activities at HMW continue to advance toward completion, ahead of expected first production of lithium chloride in H1 2026

PERTH, AU / ACCESS Newswire / December 15, 2025 / Galan Lithium Limited (ASX:GLN,OTC:GLNLF) (Galan or the Company) is pleased to provide an update on the progress of its Phase 1 construction activities for HMW, as it advances towards its final stages.

Nano-Filtration Plant

Significant progress has been achieved on the nano-filtration plant, a critical component of the Phase 1 operation. In Sydney, general assembly of the nano-filtration plant has been completed, and pre-installation testing of the plant has also been successfully completed.

The nano-filtration plant is now in transit and is expected to arrive in South America in early 2026. Commissioning activities will commence immediately following the plant's arrival at the HMW site.

Figure 1. Load out of part of the nano-filtration plant

Figure 2. Nano-filtration pumping units loaded into containers for transport

Evaporation Ponds and Site Works

At HMW, evaporation Ponds 4 and 5 have been re-designed and scaled to support the Phase 1 production rate of 4,000 tonnes per annum of lithium carbonate equivalent ("LCE"). Liner installation on Pond 4 and 5 has been completed, and works are currently underway to subdivide areas of these ponds to optimize the concentration process of the lithium chloride product.

Figure 3. Liner installation team working on pond 4

Figure 4. Liner installation for ponds 4 and 5, adjacent to ponds 1-3.

Earthworks at the plant area have been completed, and the concrete foundation for the processing plant has been poured.

Key project infrastructure items, including power supply, electrical systems and pumps, have been ordered or procured in line with the Phase 1 construction schedule. Phase 1 of the HMW Project remains on track to be delivered within budget, with construction and procurement activities progressing in accordance with the Company's development plan.

The Company has also started to evaluate an option to expand the production capacity of Phase 1 HMW (4,000 tpa LCE) to the original Phase 1 capacity (around 5,400 tpa LCE) as studied in the 2023 HMW Phase 1 Definitive Feasibility Study.

Figure 5. Foundations for HMW plant site

Galan's Managing Director, Juan Pablo (JP) Vargas de la Vega, commented:

"Solid progress at Hombre Muerto West continues to reflect the strong commitment and teamwork of our entire team as well as our contractors and partners at Authium Ltd. Completing assembly and testing of the nano-filtration plant and advancing site works at HMW are important milestones as we move closer to first production. The project is transitioning into an exciting final phase of construction and commissioning. The momentum being built across the team gives us confidence as we move toward becoming a producing lithium company."

The Galan Board has authorised this release.

For further information contact:

COMPANY

Juan Pablo ("JP") Vargas de la Vega
Managing Director
jp@galanlithium.com.au
+ 61 8 9214 2150

MEDIA

Matt Worner
Vector Advisors
mworner@vectoradvisors.au
+61 429 522 924

SOURCE: Galan Lithium Limited



View the original press release on ACCESS Newswire

News Provided by ACCESS Newswire via QuoteMedia

GLN:AU
The Conversation (0)
Galan Lithium

Galan Lithium

Developing high-grade lithium brine projects in Argentina

Developing high-grade lithium brine projects in Argentina Keep Reading...
Successful Due Diligence Ends - $20M Placement To Proceed

Successful Due Diligence Ends - $20M Placement To Proceed

Galan Lithium (GLN:AU) has announced Successful Due Diligence Ends - $20m Placement To ProceedDownload the PDF here. Keep Reading...
Final At-The-Market Raise for 2025

Final At-The-Market Raise for 2025

Galan Lithium (GLN:AU) has announced Final At-The-Market Raise for 2025Download the PDF here. Keep Reading...
Quarterly Activities and Cash Flow Report

Quarterly Activities and Cash Flow Report

Galan Lithium (GLN:AU) has announced Quarterly Activities and Cash Flow ReportDownload the PDF here. Keep Reading...
Incentive Regime for HMW Project in Argentina

Incentive Regime for HMW Project in Argentina

Galan Lithium (GLN:AU) has announced Incentive Regime for HMW Project in ArgentinaDownload the PDF here. Keep Reading...
Trading Halt

Trading Halt

Galan Lithium (GLN:AU) has announced Trading HaltDownload the PDF here. Keep Reading...
Ridgeline files Early Warning Report in Respect of Spartan Metals Corp.

Ridgeline files Early Warning Report in Respect of Spartan Metals Corp.

Ridgeline Minerals Corp. (TSXV: RDG) (OTCQB: RDGMF) (FSE: 0GC0) ("Ridgeline" or the "Company") announces that on July 13, 2026 it disposed of a total of 600,000 common shares (the "Spartan Shares") in the capital of Spartan Metals Corp. ("Spartan") at a price of $0.48 per Spartan Share for... Keep Reading...
Western Uranium & Vanadium Provides Update on Mill License Application

Western Uranium & Vanadium Provides Update on Mill License Application

July 14, 2026 Western Uranium & Vanadium Corp. (CSE: WUC,OTC:WSTRF) (OTCQX: WSTRF) ("Western" or the "Company") is pleased to provide an update on its progress toward submitting the radioactive materials license application for the Mustang Mineral Processing Plant ("Mustang"), located at the... Keep Reading...
Nevada Sunrise Completes Soil Survey Program at the Fivemile Gold Project, Cortez Mining District, Nevada

Nevada Sunrise Completes Soil Survey Program at the Fivemile Gold Project, Cortez Mining District, Nevada

Nevada Sunrise Metals Corporation (TSXV: NEV,OTC:NVSGF) (OTC Pink: NVSGF) ("Nevada Sunrise" or the "Company") is pleased to announce the completion of an Ionic Leachâ„¢ soil survey program at the Fivemile Gold Project ("Fivemile", or the Property"), located within the Battle Mountain-Eureka-Cortez... Keep Reading...
Homerun Resources Inc. Formally Included in "Programa Desenvolve" Tax Incentive Program to Support Industrial Development and Economic Integration in the State of Bahia, Brazil

Homerun Resources Inc. Formally Included in "Programa Desenvolve" Tax Incentive Program to Support Industrial Development and Economic Integration in the State of Bahia, Brazil

Homerun Resources Inc. (TSXV: HMR,OTC:HMRFF) (OTCQB: HMRFF) ("Homerun" or the "Company") is pleased to announce that the Company's wholly owned Brazilian subsidiary, Homerun Brasil Mineração Ltda., has been formally included in "PROGRAMA DESENVOLVE," the industrial development and economic... Keep Reading...
Outstanding Silver Lead & Zinc Flotation Recoveries

Outstanding Silver Lead & Zinc Flotation Recoveries

Rapid Critical Metals (RCM:AU) has announced Outstanding Silver Lead & Zinc Flotation RecoveriesDownload the PDF here. Keep Reading...
SAGA Metals Completes Acquisition of Wolverine Heavy Rare Earth Element Project in Labrador-REE Mineralized Potential Similar to Strange Lake and Tanbreez

SAGA Metals Completes Acquisition of Wolverine Heavy Rare Earth Element Project in Labrador-REE Mineralized Potential Similar to Strange Lake and Tanbreez

Saga Metals Corp. (TSXV: SAGA,OTC:SAGMF) (OTCQB: SAGMF) (FSE: 20H) ("SAGA" or the "Company"), a North American exploration company focused on critical mineral discoveries, is pleased to announce that, further to its news release dated April 14, 2026, it has closed the previously announced... Keep Reading...

Interactive Chart

Latest Press Releases

Related News