Fortuna reports that construction at its Séguéla gold Project is 83 percent complete

 

Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) is pleased to provide an update on construction activities at its Séguéla gold Project located in Côte d'Ivoire. In September of 2021, the Company made a construction decision to proceed to build a 3,750 tonne per day mill at Séguéla, with first gold pour expected in mid-2023 (refer to Fortuna news release dated September 29, 2021 ). All references to dollar amounts in this news release are expressed in US dollars.

 

David Whittle, Chief Operating Officer - West Africa, commented, "We are pleased to report that the construction progress at Séguéla continues to track on-time and on-budget despite a particularly heavy wet season." Mr. Whittle added, "The operation is now moving forward with its recruitment and on-boarding of key senior personnel allowing for the development of the operational procedures and systems in order to facilitate a smooth transition from construction into operation."

 

  Construction Highlights  

 
  • Overall project is 83 percent complete as of October 31, 2022 and first gold pour remains on target for mid-2023
  •  
  • Deliveries continue to arrive in Abidjan, Côte d´Ivoire with all SAG mill components now shipped; last SAG mill package is due to arrive in early December

  •  
  • The process plant structural, mechanical, and piping (SMP) contractor has advanced work across multiple work fronts
  •  
  • Construction of the 90kV transmission line and substation is nearing completion and on-track to be energized in December
  •  
  • Approximately 565,000 m 3 of water has collected in the water storage dam (WSD) which is in line with expectations and needs for commissioning and startup activities
  •  
  • Earthworks and high density polyethylene (HDPE) lining of the tailings storage facility (TSF) is on-track for completion before the end of 2022
  •  
  • Mining contractor mobilized to site and has commenced establishment activities
  •  

 Project construction overview

 

Project construction overview

 

  Processing Plant  

 

Lycopodium has made excellent progress in advancing the critical path scopes for the plant. As of the end of October, the main construction activities include:

 
  • Civil and concrete works nearing completion with handover of the SAG mill pedestals to the SMP contractor complete
  •  
  • Carbon-in-leach (CIL) tank fabrication and hydrostatic / settlement completed
  •  
  • Assembly of the water tanks and hydrostatic testing completed
  •  
  • Erection of the reagents storage building, warehouse and workshop completed
  •  
  • Structural steel erected in the crushing, surge bin and milling and grinding areas
  •  
  • Mechanical equipment installations commenced for items such as the thickener, intensive leach reactor, and apron feeder
  •  
  • Installation of conveyors underway
  •  
  • Fabrication of steel pipe spools commenced
  •  

The delivery and installation of the SAG mill remains on the project's critical path and, despite global supply chain challenges and risks, all components have been shipped and are expected to be delivered to site before the end of the year.

 

 Photo 2

 

 
Site Bulk Earthworks  

 

Construction of the TSF and WSD are well advanced. Construction of the WSD is nearly complete and has already captured approximately 565,000 m 3 of raw water as of the end of October in preparation for commissioning and transition to operations. Likewise, good progress has been made on the TSF embankment which is on track to be completed this quarter. Forty-eight percent of the total surface of the TSF has been lined with HDPE lining. As the wet season has ended, the lining contractor is re-mobilizing to site to complete the lining of the TSF.

 

 Photo 3

 

  Grid Connection  

 

At the end of October, the construction of the HV substation was approximately 97 percent complete. Work is on-track for the energization of the substation in December 2022 ahead of commissioning activities at the processing plant.

 

 HV substation construction work overview

 

HV substation construction work overview

 

  Mining  

 

Mota-Engil, the mining services contractor at Séguéla, is well underway with its recruitment activities for the project and has mobilized its team to the site. All long-lead equipment has been procured and started to arrive in country in October.

 

  Operational Readiness  

 

Preparations for the operational phase of the mine are progressing well. Mota-Engil is currently undertaking civil works associated with the establishment of their infrastructure, including workshops, offices and explosives magazine area. Construction of the ROM pad and preliminary grade control drilling is expected to commence during the current quarter.

 

The first delivery of mining equipment has been received in Côte d'Ivoire with further deliveries of the mining fleet expected throughout the quarter.

 

Operational mine team recruitment activities are well advanced with General Manager Operations and other senior management positions appointed. Recruitment continues for the remainder of the operational team.

 

  Cost  

 

As of October 31, 2022, $166.0 million of the total approved budget of $173.5 million, including $8.9 million contingency, has been committed. The total commitments to date include contracts for a guaranteed maximum price of $87 million, fixed price contracts for $15.4 million and earthworks bill of quantity and schedule of rates for $13.7 million. The remaining commitments are largely comprised of employee salaries, equipment and material purchase orders, land compensation and livelihood restoration programs.

 

Project commitments as of October 31, 2022:

 

 Project commitments as of October 31, 2022

 

  Schedule  

 

Construction at Séguéla is tracking on schedule with the project's next major milestones below:

 

 Construction at Séguéla is tracking on schedule with the project's next major milestones below

 

Further updates on the construction of the Séguéla gold Project will be provided as the development of the project proceeds. Séguéla´s construction photo gallery can be accessed here .

 

  Qualified Person  

 

Raul Espinoza, Director of Technical Services for the Company, is a Fellow member and Chartered Professional of the Australasian Institute of Mining and Metallurgy (FAusIMM CP) and a Qualified Person as defined by National Instrument 43-101, Standards of Disclosure for Mineral Projects. Mr. Espinoza has reviewed and approved the scientific and technical information pertaining to the Séguéla Gold Project contained in this news release and has verified the underlying data.

 

  About Fortuna Silver Mines Inc.  

 

Fortuna Silver Mines Inc. is a Canadian precious metals mining company with four operating mines in Argentina, Burkina Faso, Mexico and Peru, and a fifth mine under construction in Côte d'Ivoire. Sustainability is integral to all our operations and relationships. We produce gold and silver and generate shared value over the long-term for our stakeholders through efficient production, environmental protection, and social responsibility. For more information, please visit our website .

 

ON BEHALF OF THE BOARD

 

  Jorge A. Ganoza  
President, CEO, and Director
Fortuna Silver Mines Inc.

 

Investor Relations:
Carlos Baca | info@fortunasilver.com | Twitter : @Fortuna_Silver | LinkedIn : fortunasilvermines  

 

   Forward looking Statements   

 

  This news release contains forward looking statements which constitute "forward looking information" within the meaning of applicable Canadian securities legislation and "forward looking statements" within the meaning of the "safe harbor" provisions of the Private Securities Litigation Reform Act of 1995 (collectively, "Forward looking Statements"). All statements included herein, other than statements of historical fact, are Forward looking Statements and are subject to a variety of known and unknown risks and uncertainties which could cause actual events or results to differ materially from those reflected in the Forward looking Statements. The Forward looking Statements in this news release may include, without limitation, statements about the Company's plans for the construction of an open pit gold mine at the Séguéla gold Project, including the timeline for construction, the costs of constructing the mine, the securing of contracts necessary for the construction of the mine, the timing of the delivery of equipment to the project; the signing of the Mining Convention with the Government of Côte d'Ivoire, the ability to sign contracts for outstanding equipment and services in line with the estimates for same, the timing of the first gold pour; the Company's business strategy, plans and outlook; the merit of the Company's mineral properties; mineral resource and reserve estimates; timelines; the future financial or operating performance of the Company; expenditures; approvals and other matters. Often, but not always, these Forward looking Statements can be identified by the use of words such as "estimated", "potential", "open", "future", "assumed", "projected", "used", "detailed", "has been", "gain", "planned", "reflecting", "will", "containing", "remaining", "to be", or statements that events, "could" or "should" occur or be achieved and similar expressions, including negative variations.  

 

  Forward looking Statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any results, performance or achievements expressed or implied by the Forward looking Statements. Such uncertainties and factors include, among others, changes in general economic conditions and financial markets; the duration and effects of the COVID-19 pandemic on our operations and workforce and the effects on the global economy and society; changes in prices for silver, gold and other metals; changes in the prices of supplies required for the construction at the Séguéla gold Project such as equipment and services; the ability to sign the Mining Convention on terms currently contemplated and acceptable to the Company; technological and operational hazards in Fortuna's mining and mine development activities; risks inherent in mineral exploration; fluctuations in prices for energy, labor, materials, supplies and services; fluctuations in currencies; increases in inflation; uncertainties inherent in the estimation of mineral reserves, mineral resources, and metal recoveries; our ability to obtain all necessary permits, licenses and regulatory approvals in a timely manner; governmental and other approvals; political unrest or instability in countries where Fortuna is active; labor relations issues; as well as those factors discussed under "Risk Factors" in the Company's Annual Information Form. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in Forward looking Statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.  

 

  Forward looking Statements contained herein are based on the assumptions, beliefs, expectations and opinions of management, including but not limited to that the construction at the Séguéla gold Project will continue on the time line and in accordance with the budget as planned; that COVID-19 and the current inflationary environment will not have an adverse effect on the cost of construction of the mine at the Séguéla gold Project and will not adversely affect the supply chain and delivery of materials and equipment for the construction; expected trends in mineral prices and currency exchange rates; that there will be no adverse weather conditions that will delay work at the project; that the Company's activities will be in accordance with the Company's public statements and stated goals; that there will be no material adverse change affecting the Company or its properties; that all required approvals will be obtained; that there will be no significant disruptions affecting operations, and such other assumptions as set out herein. Forward looking Statements are made as of the date hereof and the Company disclaims any obligation to update any Forward looking Statements, whether as a result of new information, future events or results or otherwise, except as required by law. There can be no assurance that Forward looking Statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, investors should not place undue reliance on Forward looking Statements.  

 

  Primary Logo 

 

News Provided by GlobeNewswire via QuoteMedia

FVI:CA,FSM
The Conversation (0)
Fortuna Announces Pricing of Convertible Senior Notes

Fortuna Announces Pricing of Convertible Senior Notes

 

Fortuna Silver Mines Inc. (TSX: FVI) (NYSE: FSM) ("Fortuna" or the "Company") announces that it has priced its previously announced offering of convertible senior notes due 2029 (the "Notes") in an aggregate principal amount of US$150 million (the "Offering"). The Company has granted the initial purchasers of the Notes an option for a period of 15 days to purchase up to an additional US$22.5 million aggregate principal amount of Notes. The Notes will be issued at par value.

 

The Notes will bear cash interest semi-annually at a rate of 3.75% per annum. The initial conversion rate for the Notes will be 151.7220 common shares of Fortuna ("Shares") per US$1,000 principal amount of Notes, equivalent to an initial conversion price of approximately US$6.59 per Share. The initial conversion rate represents a premium of approximately 30% relative to today's closing sale price of the Shares and is subject to adjustment in certain events.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Fortuna's Yaramoko Mine reaches one-million-ounce gold pour milestone

Fortuna's Yaramoko Mine reaches one-million-ounce gold pour milestone

 

Fortuna Silver Mines Inc. (TSX: FVI) (NYSE: FSM) is pleased to report that the Yaramoko Mine located in Burkina Faso reached the one-million-ounce gold pour milestone on May 19, 2024. Yaramoko started production on May 16, 2016 and Fortuna acquired the mine on July 2, 2021 (refer to Fortuna news release dated July 2, 2021 ).

 

As of December 31, 2023, Yaramoko has a remaining mine life of two years with Proven and Probable Mineral Reserves of 0.9 Mt at a grade of 7.90 g/t Au and containing 219 koz Au, in addition to Measured and Indicated Mineral Resources, exclusive of Mineral Reserves, of 0.5 Mt at a grade of 2.87 g/t Au and containing 43 koz Au, and Inferred Mineral Resources, exclusive of Mineral Reserves, of 0.16 Mt at a grade of 3.52 g/t Au and containing 18 koz Au (refer to Fortuna news release dated February 15, 2024, " Fortuna reports updated Mineral Reserves and Mineral Resources "). The mine's exploration budget for 2024 is US$6.1 million, which includes 41,450 meters of drilling (refer to Fortuna news release dated January 18, 2024 ).

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Silver bars, stock market data and graph with "Weekly Editor's Picks" banner.

Editor's Picks: Silver Price Breaks US$39 Again, Rare Earths Stock Soars

The gold price saw both peaks and troughs this week, reacting to the release of June consumer and producer price index data out of the US, as well as renewed discussions about whether President Donald Trump may fire Federal Reserve Chair Jerome Powell.

Silver was the real precious metals star, pushing past the US$39 per ounce level once again.

Keep reading...Show less
Closeup of US silver coins with eagle and stars design on a black background.

Silver Price Update: Q2 2025 in Review

Silver took some luster from gold in Q2 as its price climbed to 14 year highs.

Many of the same contributors that affected the gold price were also in play for silver.

Uncertainty in financial markets, driven by a chaotic US trade and tariff policy, coincided with rising tensions in the Middle East and continued fighting between Russia and Ukraine, prompting investors to seek safe-haven assets.

Keep reading...Show less
Ted Butler, silver bars.

Ted Butler: Silver's Moment is Here, Time for Price to Outperform

Has silver's moment finally arrived?

Precious metals analyst Ted Butler believes the answer is "yes."

Keep reading...Show less
Mani Alkhafaji, silver bars.

Silver Price at New Base, What Comes Next? First Majestic's Mani Alkhafaji

Mani Alkhafaji, vice president of corporate of development and investor relations at First Majestic Silver (TSX:AG,NYSE:AG) discusses silver's recent price rise.

He notes that the gold-silver mining ratio is at seven to one, while the price ratio is at 90 to one.

Keep reading...Show less
Silver bar surrounded by shiny silver nuggets on a black background.

Top 5 Canadian Silver Stocks of 2025

Silver prices surged during the second quarter of 2025, surpassing the US$37 per ounce mark and reaching their highest levels in 14 years.

The price movements stem from a tightening supply and demand situation, which has seen above-ground inventories squeezed due to an increasing need from industrial sectors, particularly the growing photovoltaics industry.

However, demand has also increased due to heightened investor interest in alternative safe-haven assets, as gold prices reached record highs. The shifting sentiment comes amid uncertainty over a US trade policy that could reduce the world's gross domestic product by 1 percent.

Keep reading...Show less
Silver bar chart going up.

5 Silver Stocks With Dividends

Silver is a notoriously volatile metal capable of wide price swings in either direction. However, the metal is also seen by many as a safe-haven investment and a hedge against inflation.

While investing in silver bullion is one popular method for gaining exposure, silver-mining companies offer another route.

Silver-mining companies with strong balance sheets and experienced management teams are able to capitalize on high silver prices and weather the storm of low silver prices. Some of the most profitable silver-mining companies are even able to offer investors dividends, which may be appealing for those who are in it for the long haul.

Keep reading...Show less

Latest Press Releases

Related News

×