Walkabout Resources Ltd

First Graphite Concentrate Shipment from the Lindi Jumbo Graphite Mine

Walkabout Resources Limited (ASX:WKT) (“Walkabout” or the “Company”) is pleased to announce that it has produced and shipped the first consignment of on-specification graphite concentrate from the Lindi Jumbo Graphite Mine in Tanzania.


HIGHLIGHTS

  • Lindi Jumbo plant commissioning ongoing with first graphite concentrate bagged in early May
  • Product shipped from site for first sales in Europe
  • Commissioning team currently focused on improvements in plant performance, availability and utilisation
  • Operations team achieving significant cost efficiencies in power and fuel usage
  • Announced US tariffs on Chinese graphite improve product pricing

Walkabout’s Managing Director and CEO Andrew Cunningham said, “The successful production of on-spec, saleable product during the commissioning process at the Lindi Jumbo plant facility is an exciting milestone. To achieve our first concentrate shipment from site, at a time when customers are looking to shore up their graphite supply chains is a rewarding and outstanding outcome for the tenacity of our people, community, contractors and shareholders. We now have the opportunity to engage with more end-users as we continue to demonstrate we have a viable product and that we are serious contenders in development of non-Chinese graphite supply.”

Lindi Jumbo Project Update

COMMISSIONING ACTIVITIES

All sections of the plant are commissioned.

The priority commissioning team remains focused on is the increase of plant availability to run the entire circuit on a more continuous basis, while steadily increasing throughput to reach the planned production volume of 40Ktpa. Having the plant available and operating for an entire 12-hour shift has been an important milestone during the commissioning and ramp-up period.

Once the throughput targets have been met the team will turn its attention to the end-to-end optimisation of processing circuits to consistently achieve customer product specifications.

Logistics efficiency is also a focus, with bagged on-spec product accumulated in the load out area ready to be transported to port. Currently, any product not meeting specification is reprocessed as determined by the Lindi Jumbo on-site laboratory.

Figure 1: Lindi Jumbo bagged, on-spec flake graphite concentrate awaiting shipment at the Lindi Jumbo loading hold.

PRODUCT SHIPMENT

Although volumes are still relatively modest due to limited plant availability and utilisation during the commissioning and early ramp-up phase, the first consignment of on-spec bagged graphite concentrate has been shipped to Dar es Salaam for sale to Wogen under the exclusive offtake agreement (See announcement 22 July 2022). This first sale forms part of a larger order from an end customer in Europe. Road access to both ports is now available after the recent cyclone.

CONTRACTS

Issue of the Final Completion Certificate (“FCC”) by the EPC contractor (Jinpeng) will occur once the required throughput tonnages are achieved and sustained for a period of 48 hours. Once signed off, the plant will be handed over to the operating team to continue the ramp up over the coming months. A number of processing and maintenance specialists from Jinpeng will remain on site for as long as required.

Following FCC, it is not expected that Lindi Jumbo will make any post commissioning cash payments to Jinpeng as the mine has incurred a substantial amount of in-country costs on behalf of the EPC contractor and the remaining net balance will be settled by way of the issue of shares (See ASX announcement of 28 August 2023).


Click here for the full ASX Release

This article includes content from Walkabout Resources Ltd, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

The Conversation (0)
E-Power Resources (CSE:EPR)

E-Power Resources


Keep reading...Show less

NMG Provides Update on its Progress Toward FID for its Fully Integrated Ore-to-Active-Anode-Materials Phase-2 Operations

  • Integrated feasibility study for NMG's Phase-2 Matawinie Mine and Bécancour Battery Material Plant advancing to optimize production parameters, engineering, and cost projections, with the updated results expected early in Q1-2025.
  • Active work with Anchor Customers Panasonic Energy and GM to advance product qualification, project execution, commercial, and corporate requirements associated with the respective offtake agreements with a view to underpin Phase-2 development.
  • On-going project financing activities for the Company's Phase 2 including cumulative expressions of interest for approximately $1.4 billion comprised of potential lenders, Anchor Customers and institutional equity investors.
  • Eligibility to a refundable investment tax credit from the Canadian government estimated at about $350 million for the Phase-2 facilities.
  • Detailed engineering of Phase-2 facilities progressing with key engineering firms, supporting the preparation of purchase orders for vendor engineering and long-lead items.
  • Electrification program progressing well; Matawinie Mine's 120kV electrical substation contract awarded to ABB, construction planning underway for the powerline to supply the mine with clean hydropower, and development of zero-emission mining equipment by Caterpillar Inc. ("Caterpillar").
  • Even in the pressured market, 11.2% year-to-date gain on graphite prices (Benchmark Mineral Intelligence, September 2024) and 11.5 million EV sales (Rho Motion, October 2024); GM's EV production and sales in North America are growing significantly (GM, October 2024).
  • Appointment of Stéphane Leblanc to the Board of Directors and Karine Doucet to the position of Vice President Human Resources.
  • Continued engagement with First Nations and community to inform project execution and maximize local benefits.
  • Twelve-month rolling total recordable injury frequency rate of 1.73 and severity rate of 0.86 at the Company's facilities; and no major environmental incidents.
  • Period-end cash position of $56.5 million.

Nouveau Monde Graphite Inc. ("NMG" or the "Company") ( NYSE: NMG , TSX.V: NOU ) reports progress update on its multiple workstreams to bring its Phase-2 Matawinie Mine and Bécancour Battery Material Plant to a Final Investment Decision ("FID"). The Company is actively advancing its integrated feasibility study, engaging with its Anchor Customers Panasonic Energy Co., Ltd. ("Panasonic Energy"), a wholly owned subsidiary of Panasonic Holdings Corporation ("Panasonic") ( TYO: 6752 ), and General Motors Holdings LLC, a wholly owned subsidiary of General Motors Co. (collectively, "GM") ( NYSE: GM ), ongoing project financing activities, and preparing for the construction of its Phase-2 operations.

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
Altech Batteries

Altech – $4M Placement to Advance Battery Projects

Altech Batteries Limited (Altech/Company) (ASX: ATC) (FRA: A3Y) announces a capital raising of $4 million, comprising the issue of 66,666,667 fully paid ordinary shares in the capital of the Company at an issue price of $0.06 per Share. This price is a premium of 50% of the issue price to the Company’s shareholders in the recent Entitlement Offer conducted on 7 August 24. Participants in the placement will also receive free attaching listed options (ASX: ATCOC) of 1 option for every 1 share issued with an exercise price of $0.06 and expiry date of 31 December 2025.

Keep reading...Show less
Person signing agreement with hard hat in background.

International Graphite Gets AU$4.5 Million Grant for Collie Micronising Facility

International Graphite (ASX:IG6) has secured a AU$4.5 million government grant that will fund the construction of its Collie micronising facility, the company said in a press release on Tuesday (November 12).

The amount will be funded under the Australian Government Critical Minerals Office grant.

“We are excited to be pushing ahead with the construction of the new plant at Collie. Establishing a micronising business in Collie has been an important step in our development plans,” said CEO and Managing Director Andrew Worland.

Keep reading...Show less
Business handshake.

NOVONIX Pens Synthetic Graphite Offtake Deal with Carmaker Stellantis

NOVONIX (ASX:NVX,NASDAQ:NVX) announced on Sunday (November 10) that it has signed a binding offtake agreement with automotive company Stellantis (NYSE:STLA) for synthetic graphite material.

NOVONIX said that starting in 2026, it will provide a minimum of 86,250 tonnes of the material to Stellantis over a period of six years. The maximum amount NOVONIX will provide is 115,000 tonnes.

The high-performance synthetic graphite material will be sent to Stellantis' cell manufacturing partners in North America from NOVONIX's Riverside facility in Tennessee, US, and a planned expansion site.

Keep reading...Show less
Australia from above.

Lincoln Releases Kookaburra PFS, Outlines Plan to Become Newest Australian Graphite Miner

Lincoln Minerals (ASX:LML) moved closer to its goal of becoming Australia's newest graphite miner with the release of a prefeasibility study (PFS) for its Kookaburra project in South Australia.

The company shared the results on time, saying in September that the PFS was expected this month.

The study outlines two stages of development, and is designed to bring Kookaburra online at a low cost.

Keep reading...Show less

Latest Press Releases

Related News

×