Element 25 Limited

E25 Progresses USA HPMSM Refinery Plans

Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to provide an update in relation to it’s planned construction of a high-purity manganese sulphate (HPMSM) refinery in Louisiana USA to supply domestic HPMSM to the US electric vehicle battery industry.


Element 25 Managing Director Justin Brown said: “E25 aims to be a leading source of high quality, vertically integrated, traceable and ESG and IRA-compliant battery material to the global electric vehicle industry. Construction of our HPMSM facility in the USA – the first of its kind there – is a key pillar to the strategic plan which aims to position E25 as the industry leading provider of high quality ethically sourced battery-grade manganese to support global electrification efforts.

Engineering Development

Basic engineering packages for specific sections of the plant are being generated by equipment vendors. Design development of the balance of the processing facility is progressing. The project engineers have developed an initial project execution plan, procurement plan and other foundational elements, which are being reviewed. Project controls are being developed to manage cost and schedule.

Figure 1. 3D engineering model development for Louisiana HPMSM refinery.

Schedule

The project schedule has been developed, incorporating all facets of the project, including engineering, permitting, project financing and construction. Commencement of construction and commissioning are under review pending the execution of binding terms on the project site, in addition to the conclusion of project financing activities and a Final Investment Decision by E25’s Board of Directors to commence construction (FID).

The current schedule development provides for approximately 80 weeks of project build time based on the current critical path, however is being reviewed with the aim of compressing construction timelines.

The current timeline assumes no material interruptions to project development once construction commences due to procurement, procurement delays or weather-related disruptions.

Project Site Selection

Discussions continue with the owners of the preferred project site with the intention of combining land, sulphuric acid and ancillary services into the commercial terms. The principal reagent required by the Element 25 HPMSM process is sulphuric acid, and securing reliable supply at competitive commercial terms is an important aspect of the site selection process. Other considerations include inbound and outbound logistics and site permitting requirements. Site-specific engineering activities are currently paused pending finalisation of these commercial agreements.

Permitting

Air Permit

The air permit is a key requirement to commence facility construction. Any source, including a temporary source, which emits or has the potential to emit any air contaminant (defined as particulate matter, dust, fumes, gas, mist, smoke, or vapour, or any combination thereof produced by the process(es) other than natural) requires an air permit. As part of the permitting process, Element 25 has completed a detailed assessment of expected emissions from the HPMSM refinery and provided this information along with supporting documentation to the Louisiana Department of Environmental Quality (LDEQ).

A draft permit has been issued, and comments have been provided to the regulator. The final stage of the permitting process is a public meeting, currently scheduled to be held on 18 April 2024 to be held in the local community centre close to the proposed project site.

The LDEQ Office of Environmental Services will conduct a public hearing in order to receive comments on the proposed Initial Part 70 Air Operating Permit and the associated Environmental Assessment Statement (EAS) for Element 25 (Louisiana) LLC, being the operator of the site. It is anticipated that the final permit will be issued during May 2024 at the conclusion of this process.


Click here for the full ASX Release

This article includes content from Element 25 Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

E25:AU
The Conversation (0)
Miramar Resources

Goldfields Exploration Update

Miramar Resources Limited (ASX:M2R, “Miramar” or “the Company”) is pleased to provide an update on gold exploration activities within the Company’s strategic Eastern Goldfields project portfolio.

Keep reading...Show less
Element 25 Limited

Infill Drilling Completed at Butcherbird Targeting Reserve Extension to Support Expansion

Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to advise that resource infill drilling has been completed at the Company’s 100%-owned Butcherbird Manganese Project (Butcherbird or Project). E25 recently completed a Feasibility Study (FS) to support the Butcherbird Expansion Project, which is targeting a nominal 1.1 million tonnes per annum of manganese concentrate production1.

Keep reading...Show less
Element 25 Limited

Element 25 Extends Share Purchase Plan

Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) advises that the closing date for the current Share Purchase Plan (SPP)1 will be extended until 5:00pm, Wednesday, 26 June 2024 Australian Western Standard Time (AWST).

Keep reading...Show less
Element 25 Limited

E25 Investigates Butcherbird Restart Options Amid Record High Manganese Ore Prices

Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to provide an update on activities to investigate the potential to recommence operations at the Company’s 100%-owned Butcherbird Manganese Project in Western Australia (Butcherbird) to take advantage of recent upward movement in manganese ore prices caused by market factors including disruptions at South 32 Limited’s Groote Eylandt (GEMCO) operations1. This may include the sale of stockpiles and or recommencing processing of run-of mine (ROM) stockpiles.

Keep reading...Show less
Closeup of manganese ore from mines.

Manganese in Australia (Updated 2024)

Manganese is a hard, silvery metal with many uses in the world driving demand today. Manganese mines in Australia are working to meet that demand.

Despite being brittle, it adds strength and wear-resistance to metals like iron. It can be used to make glass and ceramics, and manganese sulphate is even used as a fungicide. Manganese is also an essential mineral in our diets, and is found in bones as well as organs like the kidneys, liver and brain.

But most substantially, manganese is used in the Australian and global industrial metals sector. Right now, about 85 to 90 percent of manganese demand comes from the steelmaking sector, including ironmaking.

Keep reading...Show less
Manganese ore in the foreground at an open-pit manganese mine.

Top 5 Manganese Reserves by Country (Updated 2024)

Manganese, a key ingredient for the steel market, is also seeing growth in demand from the electric vehicle battery sector, particularly when it comes to high-purity manganese chemical products.

Manganese investors are often interested to hear which countries produce the most of the metal. After all, if a nation is producing a lot of manganese, many companies are likely operating there — and investment opportunities may thus be available. However, what investors sometimes fail to consider is manganese reserves, or how much economically mineable manganese a country holds, and what companies are working to bring those reserves into production.

CPM Group told the Investing News Network that there are about 60 development-stage manganese ferroalloy projects scheduled to start production by 2027. If all of these new projects in the pipeline are brought online, the impact on the global market would be about a 6 percent increase in manganese ferroalloy production capacity.

Keep reading...Show less

Latest Press Releases

Related News

×