Element 25 Limited

E25 Progresses USA HPMSM Refinery Plans

Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to provide an update in relation to it’s planned construction of a high-purity manganese sulphate (HPMSM) refinery in Louisiana USA to supply domestic HPMSM to the US electric vehicle battery industry.


Element 25 Managing Director Justin Brown said: “E25 aims to be a leading source of high quality, vertically integrated, traceable and ESG and IRA-compliant battery material to the global electric vehicle industry. Construction of our HPMSM facility in the USA – the first of its kind there – is a key pillar to the strategic plan which aims to position E25 as the industry leading provider of high quality ethically sourced battery-grade manganese to support global electrification efforts.

Engineering Development

Basic engineering packages for specific sections of the plant are being generated by equipment vendors. Design development of the balance of the processing facility is progressing. The project engineers have developed an initial project execution plan, procurement plan and other foundational elements, which are being reviewed. Project controls are being developed to manage cost and schedule.

Figure 1. 3D engineering model development for Louisiana HPMSM refinery.

Schedule

The project schedule has been developed, incorporating all facets of the project, including engineering, permitting, project financing and construction. Commencement of construction and commissioning are under review pending the execution of binding terms on the project site, in addition to the conclusion of project financing activities and a Final Investment Decision by E25’s Board of Directors to commence construction (FID).

The current schedule development provides for approximately 80 weeks of project build time based on the current critical path, however is being reviewed with the aim of compressing construction timelines.

The current timeline assumes no material interruptions to project development once construction commences due to procurement, procurement delays or weather-related disruptions.

Project Site Selection

Discussions continue with the owners of the preferred project site with the intention of combining land, sulphuric acid and ancillary services into the commercial terms. The principal reagent required by the Element 25 HPMSM process is sulphuric acid, and securing reliable supply at competitive commercial terms is an important aspect of the site selection process. Other considerations include inbound and outbound logistics and site permitting requirements. Site-specific engineering activities are currently paused pending finalisation of these commercial agreements.

Permitting

Air Permit

The air permit is a key requirement to commence facility construction. Any source, including a temporary source, which emits or has the potential to emit any air contaminant (defined as particulate matter, dust, fumes, gas, mist, smoke, or vapour, or any combination thereof produced by the process(es) other than natural) requires an air permit. As part of the permitting process, Element 25 has completed a detailed assessment of expected emissions from the HPMSM refinery and provided this information along with supporting documentation to the Louisiana Department of Environmental Quality (LDEQ).

A draft permit has been issued, and comments have been provided to the regulator. The final stage of the permitting process is a public meeting, currently scheduled to be held on 18 April 2024 to be held in the local community centre close to the proposed project site.

The LDEQ Office of Environmental Services will conduct a public hearing in order to receive comments on the proposed Initial Part 70 Air Operating Permit and the associated Environmental Assessment Statement (EAS) for Element 25 (Louisiana) LLC, being the operator of the site. It is anticipated that the final permit will be issued during May 2024 at the conclusion of this process.


Click here for the full ASX Release

This article includes content from Element 25 Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

E25:AU
The Conversation (0)
Miramar Resources

Goldfields Exploration Update

Miramar Resources Limited (ASX:M2R, “Miramar” or “the Company”) is pleased to provide an update on gold exploration activities within the Company’s strategic Eastern Goldfields project portfolio.

Keep reading...Show less
Manganese highlighted on periodic table.

Element 25 Increases MRE for Butcherbird Manganese Mine

Manganese-focused producer Element 25 (ASX:E25,OTCQX:ELMTF) provided an update to the mineral resource estimate for its Butcherbird manganese operations earlier this week.

The company recently completed an infill drilling program at the site, which targeted known mineralisation within granted mining lease M52/1074, where Butcherbird Stage 1 mining and processing operations are located.

Element 25 reported a 142 percent increase in measured and indicated resources, which now total 130 million tonnes at 10.23 percent manganese. Additionally, the site hosts a total resource of 274 million tonnes at 10 percent manganese, marking a 6 percent increase from its 263 million tonne resource estimate from April 2019.

Keep reading...Show less
Files labelled "funding," "projects" and "grants."

Element 25 Chosen for US$166 Million Grant from US Department of Energy

Element 25 (ASX:E25,OTCQX:ELMTF) has been selected to receive a US$166 million grant from the US Department of Energy, the company said in an announcement on Tuesday (September 24).

The funds will come from the Battery Materials Processing Grant Program, and will be used for the construction of the company’s proposed battery-grade high-purity manganese sulphate monohydrate (HPMSM) facility in Louisiana.

The Battery Materials Processing Grant Program has a US$3 billion budget to distribute grants for endeavours that will help ensure that the US has a viable battery materials processing industry.

Keep reading...Show less
Element 25 Limited

E25’s High-Purity Manganese Project Selected for US$166M Grant Under U.S. DoE Grant Program

Element 25 Limited (E25 or Company) (ASX: E25; OTCQX: ELMTF) is pleased to announce it has been selected for award negotiations for a US$166 million grant from the U.S. Department of Energy (DoE) under the Battery Materials Processing Grant Programme. This funding will support the construction of its proposed battery-grade high-purity manganese sulphate monohydrate (HPMSM) facility in Louisiana, USA. The grant award is in addition to the US$115 million already committed by offtake partners General Motors LLC (GM) and Stellantis N.V. (Stellantis).

Keep reading...Show less
Piece of manganese.

Trek Metals to Sell Pilbara-based Hendeka Manganese Project to AEFI

Trek Metals (ASX:TKM) announced on Tuesday (September 10) that it has signed a binding option and acquisition agreement to sell its Hendeka manganese project to private US-based company Advanced Energy Fuels (AEFI).

Under the agreement, AEFI has the option to acquire the project as part of a proposed US listing by paying AU$450,000 in cash; it will also issue Trek 8 million shares once it lists, or an amount of shares equal to not less than 20 percent of its total issued capital on a fully diluted basis. The maximum value of the shares will be AU$4 million.

In addition, AEFI will make certain payments, and will solely fund AU$2 million worth of exploration. Other conditions include an option fee of AU$50,000, AU$25,000 of which has already been paid by AEFI.

Keep reading...Show less
Manganese and hematite with an EU flag and text that says "5 Top Canadian Mining Stocks This Week."

Top 5 Canadian Mining Stocks This Week: Euro Manganese Climbs on EU Application

Welcome to the Investing News Network's weekly look at the best-performing Canadian mining stocks on the TSX and TSX Venture Exchange, starting with a round-up of Canadian and US data impacting the resource sector.

The S&P/TSX Venture Composite Index (INDEXTSI:JX) lost 10.12 points this week to close at 567.91. Meanwhile, the S&P/TSX Composite Index (INDEXTSI:OSPTX) was up by 60.1 points to finish at 23,346.18.

Statistics Canada shared real GDP figures on Friday (August 30) for the second quarter of 2024. The data shows the GDP saw a 0.5 percent quarterly gain in Q2, building on a 0.4 percent increase in the first quarter of the year.

Keep reading...Show less
Manganese ore.

Euro Manganese Enters 7 Year Offtake Deal with Wildcat Discovery

Euro Manganese (ASX:EMN,TSXV:EMN,OTCQB:EUMNF) has entered an offtake term sheet with Wildcat Discovery for the sale of high-purity manganese product from its Chvaletice project in the Czech Republic.

The deal, dated August 15 and announced on Monday (August 19), is non-binding and subject to Wildcat completing its planned cathode materials plant in the US. It has an initial term of seven years with the potential for renewal.

Euro Manganese said the news is a major milestone for itself, as well as the west's battery supply chain. President and CEO Dr. Matthew James added that the agreement accounts for a "significant percentage" of Chvaletice's output.

Keep reading...Show less

Latest Press Releases

Related News

×