CHARBONE Confirms Construction Schedule on Track at Sorel-Tracy and Announces the Imminent Start of Equipment Installation Phase

CHARBONE Confirms Construction Schedule on Track at Sorel-Tracy and Announces the Imminent Start of Equipment Installation Phase

(TheNewswire)

Brossard, Quebec TheNewswire - November 12, 2025 CHARBONE CORPORATION (TSXV: CH,OTC:CHHYF; OTCQB: CHHYF; FSE: K47) (" CHARBONE " or the " Company "), a North American producer and distributor specializing in clean Ultra High Purity (" UHP ") hydrogen and strategic industrial gases, is pleased to confirm that the construction schedule at its Sorel-Tracy site remains fully on track with the equipment installation phase set to begin in the coming days.

The civil construction works , which began on October 27, 2025 , are now completed , including foundation preparation and all required technical infrastructure for the reassembly of the main production systems. All major components delivered in October will be installed on-site before the end of the month, keeping the project on pace for the planned commissioning in November 2025 of Phase 1a.

" The fact that our schedule remains perfectly on track reflects the efficiency and dedication of our teams, along with the exceptional collaboration of our technical and municipal partners ," said Dave B. Gagnon, CEO of CHARBONE . " We are now entering the most tangible phase of the project — the installation of the equipment — marking the transition toward testing and commissioning of our first clean UHP hydrogen production module in Quebec ."

The Sorel-Tracy site represents CHARBONE's first local and modular clean hydrogen production facility in Quebec, aligning with the Company's broader vision to develop a decentralized North American network for the production and distribution of clean and strategic industrial gases. For more information on the Company's 5 phased approach and economics for CHARBONE's modular facility, please see the latest investor presentation on the Company's website.

About CHARBONE CORPORATION

CHARBONE is an integrated company specializing in clean Ultra High Purity (UHP) hydrogen and the strategic distribution of industrial gases in North America and Asia-Pacific. Through a modular approach, the Company is building a distributed network of green hydrogen production plants while diversifying revenues via helium and specialty gas partnerships. This disciplined model reduces risk, enhances flexibility, and positions CHARBONE as a leader in the transition to a low-carbon future. CHARBONE is listed on the TSX Venture Exchange (TSXV: CH,OTC:CHHYF) , the OTC Markets (OTCQB: CHHYF) , and the Frankfurt Stock Exchange (FSE: K47) . Visit www.charbone.com .

Forward-Looking Statements

This news release contains statements that are "forward-looking information" as defined under Canadian securities laws ("forward-looking statements"). These forward-looking statements are often identified by words such as "intends", "anticipates", "expects", "believes", "plans", "likely", or similar words. The forward-looking statements reflect management's expectations, estimates, or projections concerning future results or events, based on the opinions, assumptions and estimates considered reasonable by management at the date the statements are made. Although Charbone believes that the expectations reflected in the forward-looking statements are reasonable, forward-looking statements involve risks and uncertainties, and undue reliance should not be placed on forward-looking statements, as unknown or unpredictable factors could cause actual results to be materially different from those reflected in the forward-looking statements. The forward-looking statements may be affected by risks and uncertainties in the business of Charbone. These risks, uncertainties and assumptions include, but are not limited to, those described under "Risk Factors" in the Corporation's Filing Statement dated March 31, 2022, which is available on SEDAR at www.sedar.com; they could cause actual events or results to differ materially from those projected in any forward-looking statements.

Except as required under applicable securities legislation, Charbone undertakes no obligation to publicly update or revise forward-looking information.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release .

Contact Charbone Corporation

Telephone: +1 450 678 7171

Email: ir@charbone.com

Benoit Veilleux

CFO and Corporate Secretary

Copyright (c) 2025 TheNewswire - All rights reserved.

News Provided by TheNewsWire via QuoteMedia

CH:CC
Charbone

Charbone Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Charbone Corp.

Charbone

North American producer and distributor specializing in clean Ultra High Purity hydrogen and strategic industrial gases

North American producer and distributor specializing in clean Ultra High Purity hydrogen and strategic industrial gases Keep Reading...
Oil barrels in front of world map and fluctuating stock market graph.

Oil Prices Surge as Iran Conflict Halts Tanker Traffic Through Hormuz

Oil and gas prices extended their sharp climb this week as the escalating conflict between the US, Israel and Iran disrupts shipping through one of the world’s most critical energy chokepoints.Crude oil futures surged again on Thursday (March 5), with the US benchmark climbing roughly 3.5... Keep Reading...
Syntholene Energy Corp. Closes Oversubscribed $3.75 Million Non-Brokered Private Placement

Syntholene Energy Corp. Closes Oversubscribed $3.75 Million Non-Brokered Private Placement

Proceeds to be used to Accelerate Procurement and Component Assembly for Demonstration Facility Deployment in IcelandSyntholene Energy CORP. (TSXV: ESAF,OTC:SYNTF) (FSE: 3DD0) (OTCQB: SYNTF) (the "Company" or "Syntholene") is pleased to announce that it has closed its previously announced... Keep Reading...
Aerial view of a red cargo ship on deep blue sea.

Oil, LNG Prices Climb on Fears of Prolonged Hormuz Shutdown

Oil and gas prices surged Monday (March 2) after fresh military strikes between the US, Israel, and Iran rattled energy markets and brought shipping through the Strait of Hormuz close to a halt, raising fears of a wider supply shock.Brent crude, the global oil benchmark, jumped as much as 10... Keep Reading...
Angkor Resources Announces Stock Option Grant

Angkor Resources Announces Stock Option Grant

(TheNewswire) GRANDE PRAIRIE, ALBERTA TheNewswire - March 2, 2026 - Angkor Resources Corp. (TSXV: ANK,OTC:ANKOF) ("ANGKOR" OR "THE COMPANY") wishes to announce that it has granted, effective today, an aggregate of 4,275,000 stock options (each an "Option) to certain Directors, management and... Keep Reading...
U.S. and Iranian flags wave against a dark, cloudy sky.

US-Iran Tensions Put Europe’s Gas Storage Plans at Risk

Escalating tensions between the United States and Iran are reviving a risk energy markets have long feared: a potential closure of the Strait of Hormuz, the narrow Gulf passage that carries roughly 20 percent of global LNG trade and 25 percent of seaborne oil.New modelling from energy analytics... Keep Reading...
Québec Innovative Materials Corp

QIMC Intersects Major Subsurface Fault Corridor with Elevated H2 Readings at 142m Depth

Pressurized Formation Water and Visible Gas Bubbling Confirm Active Structural System in First of Five-Hole Systematic Drill Program

Quebec Innovative Materials Corp. (CSE: QIMC) (OTCQB: QIMCF) (FSE: 7FJ) ("QIMC" or the "Company") is pleased to report significant initial results from the first 300 metres of its planned 650-metre diamond drill hole DDH-26-01 at its West Advocate Eatonville Project, Nova Scotia. Drilling... Keep Reading...
Charbone

Charbone Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Interactive Chart

Latest Press Releases

Related News