Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) is pleased to announce that it has received approval of the Environmental Impact Assessment ("EIA") for the construction and operations of its La Plata mining project located in Ecuador (the "La Plata project").

The La Plata project has been identified by President of Ecuador, Guillermo Lasso as a strategic project and a component of the country's reactivation plan. As a part of this plan, President Lasso has committed to accelerating the restart of the country's economy by leveraging the potential of its mining industry while positioning Ecuador as a major mining investment destination in Latin America.

The EIA baseline process started over 3 years ago and involved independent environmental experts as well as qualified professionals mostly from Ecuador, Canada, Peru as well as from our El Roble mine operation which has been recognized as one of the safest mines in Colombia.

The La Plata project plan consists of a 900 tpd underground mining operation with state of the art infrastructure, the most significant infrastructure being the construction of a filtered tailings facility a first of its kind in Ecuador. This technology, already used at our El Roble mine in Colombia, allows for efficient use of water by significantly reducing water consumption through recirculating almost all of the water needs for the processing plant.

Mr. Alain Bureau, President of Atico Mining stated, "Our Team is very pleased to announce the receipt of the EIA approval for the La Plata project. This announcement is the culmination of a lengthy scientific process to identify every aspect of the project that could be optimized and provide solutions allowing for a responsible mining operation. We also wish to acknowledge the extensive efforts of our employees, consultants, surrounding communities and the support from the Ecuadorian environmental authorities."

The approval of the EIA is a key milestone towards allowing the Company to begin construction of the new process plant facility. This approval enables the Company to advance on its normal course in order to complete the underlying licenses and secondary permits necessary. The La Plata project also includes the upgrade of other infrastructures including the upgrade of the access road, a 69kV powerline and a flotation plant with its filtered tailing facilities. The GAD and Water Management Association of the region are presently working on water infrastructures projects. These water projects will permit the upgrade and modernization of the existing water supply facilities providing a better quality of water delivered to operations and the surrounding communities.

Atico Mining's success and culture are based on investing in sustainable development in communities where it operates through responsible mining with a tremendous emphasis on the surrounding environment.

About Atico Mining Corporation

Atico is a growth-oriented Company, focused on exploring, developing and mining copper and gold projects in Latin America. The Company generates significant cash flow through the operation of the El Roble mine and is developing it's high-grade La Plata VMS project in Ecuador. The Company is also pursuing additional acquisition of advanced stage opportunities. For more information, please visit www.aticomining.com.

ON BEHALF OF THE BOARD

Fernando E. Ganoza
CEO
Atico Mining Corporation

Trading symbols: TSX.V: ATY | OTCQX: ATCMF

Investor Relations
Igor Dutina
Tel: +1.604.633.9022

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

No securities regulatory authority has either approved or disapproved of the contents of this news release. The securities being offered have not been, and will not be, registered under the United States Securities Act of 1933, as amended (the ''U.S. Securities Act''), or any state securities laws, and may not be offered or sold in the United States, or to, or for the account or benefit of, a "U.S. person" (as defined in Regulation S of the U.S. Securities Act) unless pursuant to an exemption therefrom. This press release is for information purposes only and does not constitute an offer to sell or a solicitation of an offer to buy any securities of the Company in any jurisdiction.

Cautionary Note Regarding Forward Looking Statements

This announcement includes certain "forward-looking statements" within the meaning of Canadian securities legislation. All statements, other than statements of historical fact, included herein, without limitation the use of net proceeds, are forward-looking statements. Forward- looking statements involve various risks and uncertainties and are based on certain factors and assumptions. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from the Company's expectations include uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs; the need to obtain additional financing to maintain its interest in and/or explore and develop the Company's mineral projects; uncertainty of meeting anticipated program milestones for the Company's mineral projects; the world-wide economic and social impact of COVID-19 is managed and the duration and extent of the coronavirus pandemic is minimized or not long-term; disruptions related to the COVID-19 pandemic or other health and safety issues, or the responses of governments, communities, the Company and others to such pandemic or other issues; and other risks and uncertainties disclosed under the heading "Risk Factors" in the prospectus of the Company dated March 2, 2012 filed with the Canadian securities regulatory authorities on the SEDAR website at www.sedar.com

Click here to connect with Atico Mining Corporation (TSX.V: ATY | OTC: ATCMF) to receive an Investor Presentation

Source

ATY:CA
The Conversation (0)
Atico Mining Announces Completion NI 43-101 Feasibility Study for the La Plata Project in Ecuador

Atico Mining Announces Completion NI 43-101 Feasibility Study for the La Plata Project in Ecuador

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) is pleased to announce the results of the Definitive Feasibility Study (the "DFS" or the "Study") for its 100% owned La Plata Project ("La Plata") located in Ecuador. The DFS was prepared in accordance with the National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101"). Please note that all financial figures in this press release are in United States dollars, unless otherwise noted.

Key Highlights:

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Reports Consolidated Financial Results for First Quarter of 2024

Atico Reports Consolidated Financial Results for First Quarter of 2024

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) today announced its financial results for the three months ended March 31, 2024, posting income from mining operations of $2.8 million and a net loss of $0.4 million. Production for the period at Atico's El Roble mine totaled 3.3 million pounds ("lbs") of copper and 2,185 ounces ("oz") of gold in concentrate at a cash cost (1) of $2.57 per payable pound of copper (2) .

Fernando E. Ganoza, CEO and Director, commented, "the operational and financial results for this quarter were in line with Company expectations. We are already into development of the newly discovered reserves and have been making additional investments in preparation for ore extraction from these areas." Mr. Ganoza continued, "for the remainder of the year, we should start to see an improvement in our operating costs as we progressively gain access to mining the upper areas of the mine, while at the same time the recent increase in metals prices, particularly in copper should be positively reflected in our revenue and margin."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Produces 3.34 Million Pounds of Cu and 2,156 Ounces of Au in First Quarter 2024

Atico Produces 3.34 Million Pounds of Cu and 2,156 Ounces of Au in First Quarter 2024

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTCQX: ATCMF) announces its operating results for the three months ended March 31, 2024 from its El Roble mine. Production for the quarter totaled 3.34 million pounds of copper and 2,156 ounces of gold in concentrates, an increase of 44% for copper and a decrease of 16% for gold, respectively, over the same period in 2023.

"The El Roble mine operated in line with set expectations for this quarter as we improved on almost all metrics over the same period last year," said Fernando E. Ganoza, CEO. "For the remainder of the year, the team will be focused on optimizing production to take advantage of the higher metal price environment and to deliver on this year's set guidance. In parallel, we continue to drill new high-grade resources in the mine vicinity target areas. These new areas will be incorporated into our mine plan as well as the new resource update which is planned to be published imminently."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Reports Consolidated Financial Results for 2023

Atico Reports Consolidated Financial Results for 2023

(All amounts expressed in US dollars, unless otherwise stated)

Atico Mining Corporation (the "Company" or "Atico") (TSX.V: ATY | OTC: ATCMF) today announced its financial results for the year ended December 31, 2023, posting income from mining operations of $7.4 million and a net loss of $5.8 million. Production for the year at Atico's El Roble mine totaled 13.2 million pounds ("lbs") of copper and 10,149 ounces ("oz") of gold in concentrate at a cash cost ( 1) of $2.04 per payable pound of copper (2) .

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Atico Reports Multiple High Grade Intercepts up to 20.70m of 5.76% Cu, 4.46 g/t Au and 11.50m of 8.16% Cu, 8.09 g/t Au and Continues to Extend the Ore Body at El Roble Mine in Colombia

Atico Reports Multiple High Grade Intercepts up to 20.70m of 5.76% Cu, 4.46 g/t Au and 11.50m of 8.16% Cu, 8.09 g/t Au and Continues to Extend the Ore Body at El Roble Mine in Colombia

Atico Mining Corporation (TSX.V: ATY | OTCQX: ATCMF) ("Atico" or the "Company") is pleased to announce positive results for the latest 49 drill holes being carried out in an area of historical mining to expand tonnage at the El Roble mine. In addition, the Company reports the results for sixteen diamond drill core holes (see first table below), which included 20.70m of 5.76% Cu, 4.46 gt Au and 11.50m of 8.16% Cu, 8.09 gt Au. Ore grade intercepts in another fourteen drill holes are also reported over narrower widths of approximately 1 to 2 meters in areas with limited drilling which highlights the possibility of further extending the ore body with additional drill programs.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Alderan Resources Limited

Alderan Intersects 30m Copper Mineralised Zone at New Years Copper Prospect, Cactus District, Utah, USA

- up to 23.2% copper in averaged pXRF assay intervals in core

Alderan Resources Limited (ASX: AL8) (Alderan or the Company) is pleased to advise that its Stage 1 drilling programme at the New Years copper prospect in the Cactus copper-gold (Cu-Au) district in Utah, USA has intersected high grade copper mineralisation based on visual inspection and pXRF readings on the drill core. Spot pXRF readings reach grades of 45.5% copper between 14.0-14.2m down hole NY2024-DDH2 with the average of three separate readings over this interval being 23.2% copper (see Figure 2). This sits within a 30m interval from 10.8m downhole which contains high pXRF copper grades (see Appendix 3).

Keep reading...Show less
Cyprium Metals

Glencore Loan Facility Closed, Offtakes Executed

Cyprium Metals Limited (ASX: CYM) (Cyprium or the Company) is pleased to announce closing of the Senior Secured Loan Facility with Glencore International AG and its affiliates (Glencore) and execution of offtake agreements for copper products in line with previous announcements on 30 August 2024 – $40m Senior Secured Loan Facility with Glencore, and 26 July 2024 – Cyprium and Glencore Announce Commercial Strategic Partnership.

Keep reading...Show less
True North Copper

Geophysics Reveal Further Highly Prospective Targets at Mt Oxide Project

True North Copper Limited (ASX:TNC) (True North, TNC or the Company) is pleased to announce results from the geophysical survey at the Mt Gordon and Aquila prospects, part of TNC’s Mt Oxide Project, 140km north of Mt Isa in Queensland. The survey has been supported by a $300,000 Queensland Government Collaborate Exploration Initiative (CEI) Grant.
Keep reading...Show less
VVC Resources (TSXV:VVC)

VVC – Extension of Series AG Warrants

VVC Exploration Corporation, dba VVC Resources, ("VVC" or the "Company") announces the following:

Warrant Extension

Keep reading...Show less
Copper ore.

Cobre and BHP in Talks for Copper-Silver Exploration in Botswana

Cobre (ASX:CBE) and a wholly owned subsidiary of BHP (ASX:BHP,NYSE:BHP,LSE:BHP) have signed a letter of intent to exclusively negotiate a material earn-in joint venture agreement.

The partnership will target Cobre’s Kitlanya West and East copper projects, both of which are located on the northern and southern basin margins of the Kalahari Copper Belt in Botswana.

According to Cobre's Monday (September 23) press release, the news follows its participation in BHP’s Xplor program, which funded a recently completed seismic survey at the Kitlanya West site.

Keep reading...Show less
Norwegian flag on the back of boat.

Greenpeace: Deep-Sea Mining in Norway Could Harm Marine Biodiversity

Plans to open the Arctic seabed for deep-sea mining are raising alarms among environmentalists, particularly in light of new findings highlighting the potential damage to one of the world’s least explored ecosystems.

A recent report by Greenpeace warns that Norway’s decision to allow mineral exploration in Arctic waters could irreparably harm marine biodiversity, including species that are vital to the region’s ecological balance.

The area in question lies within the Norwegian Exclusive Economic Zone, specifically a section of the Arctic Ocean known as the Mohns Ridge. This region is believed to be rich in rare minerals like cobalt, nickel and manganese — elements that are critical for modern technology, including electric vehicles and renewable energy infrastructure.