Galena Mining

Abra December Production Update

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to provide preliminary production numbers for the Abra Base Metals Mine (“Abra”) for the month of December 2023 and the December quarter (subject to final reconciliation). Production levels during December show further improvement with new record highs achieved in several production areas including concentrate production, processed ore tonnes and mine development.


Abra Mining Pty Ltd (“AMPL”) made the first debt repayment of US$4.5M on its Taurus Debt Facilities in December 2023. Based on the mine’s performance during the 2023 ramp-up year to the end of December and continuing technical evaluation work being undertaken on the production outlook for 2024, AMPL has commenced discussions with key stakeholders as part of a strategic review of operations with an initial focus on better matching the capital structure of AMPL to Abra’s expected performance. These discussions are ongoing and are anticipated to be concluded during 1H 2024. The market will be kept informed regarding the progress of these discussions.

DECEMBER HIGHLIGHTS

  • The following production metrics were achieved in December (subject to end of month reconciliations):
    • New monthly record ore processed of ~122kt (i.e., >1.45Mtpa implied annualised production rate compared to original design annualised throughput of 1.3Mtpa).
    • Ore mined of ~101kt at 5.6% Pb (~58kt at 5.5% Pb of Stope ore and ~43kt at 5.8% Pb of development ore. ~21kt at 2.1% Pb low-grade from mine development was also processed during the month). The grade improvement seen in development ore came from the addition of new core-vein headings. Processed ore grade will continue to improve with increased levels of stope production in the mill feed (targeting 80% of monthly ore production).
    • New monthly record for underground development of ~947m (compared to previous best month in September 2023 when 807m was achieved).
    • December lead concentrate shipment departed from Geraldton containing 9,622t on 15 December 2023. Next shipment is scheduled for 11 January 2024.
  • Expected December quarter mining and processing production estimates (subject to final end of month reconciliations):
    • Processing ~358kt at 4.7% Pb (Inclusive of low-grade top-up feed material).
    • ~25kt of lead concentrate produced.
    • Mining ~280kt at 5.6% Pb ore and ~2,440m of development.

Managing Director, Tony James commented, “In December, Abra has achieved the best production month year to date. Processing throughput continued to improve, and the processing plant consistently reached levels above the original design criteria of 1.3Mtpa. Mining and specifically stopping has not reached the levels required to match the plant which resulted in low-grade material being used as supplement feed lowering the overall processing grade.

Production schedules have been based on the monthly requirement of +800m lateral development being achieved. Not achieving this consistently in 2023 has had a detrimental affect with limited access to higher grade ore reserves.

The mining performance and grade is expected to continue to improve in 2024 with depth, additional work areas and higher stope production quantities. New technical evaluation work is currently underway which will form the basis of the 2024 outlook and ongoing discussions with key stakeholders based on the latest understanding of the orebody and other key performance indicators.

During December, underground development has accessed several high-grade core veins on the 1210mRL level which is confirming the latest geological information and understanding of that part of the orebody and its importance. During December the mined development grade was higher than the stopping grade for the first time”.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Eastern Metals

Appointment of Dr Jason Berton as Non-Executive Chairman

Eastern Metals Limited (ASX: EMS) (“Eastern Metals” or “the Company”) is pleased to announce the appointment of experienced mining executive, Dr Jason Berton, as the Company’s Non-Executive Chairman. Dr Berton’s appointment follows the recent retirement of Mr Robert Duffin from the Board1.

Keep reading...Show less
Silver Tiger Announces PFS With NPV of US$222M for the Stockwork Zone of the El Tigre Silver-Gold Project, Sonora, Mexico

Silver Tiger Announces PFS With NPV of US$222M for the Stockwork Zone of the El Tigre Silver-Gold Project, Sonora, Mexico

Silver Tiger Metals Inc. (TSXV:SLVR)(OTCQX:SLVTF) ("Silver Tiger" or the "Corporation") is pleased to announce a Preliminary Feasibility Study(" PFS") for its 100% owned, silver-gold El Tigre Project (the "Project" or "El Tigre") located in Sonora, Mexico. The PFS is focused on the conventional open pit mining economics of the Stockwork Mineralization Zone defined in the updated Mineral Resource Estimate ("MRE") (Figure 1). The updated MRE also contains an Out-of-Pit Mineral Resource that Silver Tiger plans to study in a Preliminary Economic Assessment in H1-2025.

Highlights of the PFS are as follows (all figures in US dollars unless otherwise stated):

Keep reading...Show less
Eastern Metals

September 2024 Quarterly Activities Report

New targets identified at Browns Reef, the commencement of drilling, and co-funding grant awarded for IP survey at Arunta

Eastern Metals Limited (ASX: EMS) (“Eastern Metals” or “the Company”) is pleased to present its Quarterly Report for the period ending 30 September 2024.

Keep reading...Show less
Andean Silver

Spectacular High-Grade Hits Continue to Extend Mineralisation Outside Resource

Latest results to underpin the Resource update proposed for next quarter

Andean Silver Limited (ASX: ASL) is pleased to announce further spectacular drilling results which will form part of the next Resource update at its Cerro Bayo Silver-Gold Project in Chile.

Keep reading...Show less
Locksley Resources

46% Antimony (Sb) & 1,022 g/t Silver Assay Results at the Mojave Project

Locksley Resources Limited (ASX:LKY) (“Locksley” or “the Company”) is pleased to announce high-grade antimony grades up to 46% Sb from the recent rock chip sampling program. Eighteen (18) rock chips returned grades in excess of 1.4% Sb with eight (8) returning grades over 17% Sb. Since mid-2023, Locksley Resources has completed four surface sampling programs, mainly focused on detecting rare earth minerals at the Mojave Project, CA, located 45 minutes from Las Vegas. The most recent surface sampling program focused on the Desert Antimony Mine and potential for high-grade antimony mineralisation to be present along strike of the historically mined mineralised structures in an east-west and north-south direction. The sampling program revealed polymetallic mineralisation along strike of the mineralised structures suggesting a zoned reduced intrusive related system (RIRS).

Keep reading...Show less
Silver bar chart going up.

5 Silver Stocks With Dividends (Updated 2024)

Silver is a notoriously volatile metal capable of wide price swings in either direction.

However, the metal is also seen by many as a safe-haven investment and a hedge against inflation. While investing in silver bullion is one popular method for gaining exposure, silver-mining companies offer another route.

Silver-mining companies with strong balance sheets and experienced management teams are able to capitalize on high silver prices and weather the storm of low silver prices. Some of the most profitable silver-mining companies are even able to offer investors dividends, which may be appealing for those who are in it for the long haul.

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×