
- NORTH AMERICA EDITIONAustraliaNorth AmericaWorld
January 08, 2024
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to provide preliminary production numbers for the Abra Base Metals Mine (“Abra”) for the month of December 2023 and the December quarter (subject to final reconciliation). Production levels during December show further improvement with new record highs achieved in several production areas including concentrate production, processed ore tonnes and mine development.
Abra Mining Pty Ltd (“AMPL”) made the first debt repayment of US$4.5M on its Taurus Debt Facilities in December 2023. Based on the mine’s performance during the 2023 ramp-up year to the end of December and continuing technical evaluation work being undertaken on the production outlook for 2024, AMPL has commenced discussions with key stakeholders as part of a strategic review of operations with an initial focus on better matching the capital structure of AMPL to Abra’s expected performance. These discussions are ongoing and are anticipated to be concluded during 1H 2024. The market will be kept informed regarding the progress of these discussions.
DECEMBER HIGHLIGHTS
- The following production metrics were achieved in December (subject to end of month reconciliations):
- New monthly record ore processed of ~122kt (i.e., >1.45Mtpa implied annualised production rate compared to original design annualised throughput of 1.3Mtpa).
- Ore mined of ~101kt at 5.6% Pb (~58kt at 5.5% Pb of Stope ore and ~43kt at 5.8% Pb of development ore. ~21kt at 2.1% Pb low-grade from mine development was also processed during the month). The grade improvement seen in development ore came from the addition of new core-vein headings. Processed ore grade will continue to improve with increased levels of stope production in the mill feed (targeting 80% of monthly ore production).
- New monthly record for underground development of ~947m (compared to previous best month in September 2023 when 807m was achieved).
- December lead concentrate shipment departed from Geraldton containing 9,622t on 15 December 2023. Next shipment is scheduled for 11 January 2024.
- Expected December quarter mining and processing production estimates (subject to final end of month reconciliations):
- Processing ~358kt at 4.7% Pb (Inclusive of low-grade top-up feed material).
- ~25kt of lead concentrate produced.
- Mining ~280kt at 5.6% Pb ore and ~2,440m of development.
Managing Director, Tony James commented, “In December, Abra has achieved the best production month year to date. Processing throughput continued to improve, and the processing plant consistently reached levels above the original design criteria of 1.3Mtpa. Mining and specifically stopping has not reached the levels required to match the plant which resulted in low-grade material being used as supplement feed lowering the overall processing grade.
Production schedules have been based on the monthly requirement of +800m lateral development being achieved. Not achieving this consistently in 2023 has had a detrimental affect with limited access to higher grade ore reserves.
The mining performance and grade is expected to continue to improve in 2024 with depth, additional work areas and higher stope production quantities. New technical evaluation work is currently underway which will form the basis of the 2024 outlook and ongoing discussions with key stakeholders based on the latest understanding of the orebody and other key performance indicators.
During December, underground development has accessed several high-grade core veins on the 1210mRL level which is confirming the latest geological information and understanding of that part of the orebody and its importance. During December the mined development grade was higher than the stopping grade for the first time”.
Click here for the full ASX Release
This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
The Conversation (0)
12 September 2022
Galena Mining
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
12 December 2022
Abra Construction At 97% Complete – First Ore Stockpiled For January Processing
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion... Keep Reading...
16 November 2022
Abra Construction At 92% Complete – Reaches First Ore Underground
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November... Keep Reading...
13 November 2022
Abra Mine Reaches Ore
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station... Keep Reading...
31 October 2022
Galena Mining Activities Report For Quarter Ended 30 September 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western... Keep Reading...
27 October
Prince Silver Corp Announces Closing of First Tranche of Private Placement Financing
Prince Silver Corp. ("Prince" or the "Company") (CSE:PRNC)(OTCQB:PRNCF) is pleased to announce that further to its news release dated September 24, 2025, the Company has closed the first tranche (the "First Tranche") of its previously announced non-brokered private placement financing for gross... Keep Reading...
24 October
Ed Steer: Silver Rally Now Unstoppable, Price to Hit Triple Digits
Ed Steer of Ed Steer's Gold and Silver Digest shares his thoughts on silver's run past US$50 per ounce, saying that in his view the bull market is just getting started. "One way or another we're going to run into a supply/demand brick wall, and when that day happens we could see triple-digit... Keep Reading...
22 October
Gianni Kovacevic: Silver, Oil to Break US$100, but This is the Real Speculation
Investor and author Gianni Kovacevic discusses silver's price pullback, saying that in the long term he sees the white metal reaching triple digits. He expects oil prices to reach that level too, but emphasized that he sees lithium as the truly contrarian play for the rest of 2025 and into next... Keep Reading...
21 October
BP Silver Finalizes Targets for Upcoming Drill Program at its Cosuño Silver Project, Bolivia
BP Silver Corp. (TSXV: BPAG) ("BP Silver" or the "Company") announces that it has finalized targets for initial drill testing and has selected Maldonado Exploraciones, a premier Bolivian drilling contractor, to carry out the upcoming drill program at its Cosuño Silver Project ("Cosuño") in... Keep Reading...
21 October
Silver Hammer Enters into Option Agreement to Acquire 100% Interest in a Strategic and Prospective Silver Project in the Silver Valley of Idaho
Silver Hammer Mining Corp. (CSE: HAMR) (the "Company" or "Silver Hammer") is pleased to announce it has entered into an option agreement (the "Option Agreement") on October 20, 2025 with Fahey Group Mines, Inc. ("Fahey"), pursuant to which the Company has been granted the right (the "Option") to... Keep Reading...
Latest News
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00






