Galena Mining

Abra December Production Update

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to provide preliminary production numbers for the Abra Base Metals Mine (“Abra”) for the month of December 2023 and the December quarter (subject to final reconciliation). Production levels during December show further improvement with new record highs achieved in several production areas including concentrate production, processed ore tonnes and mine development.


Abra Mining Pty Ltd (“AMPL”) made the first debt repayment of US$4.5M on its Taurus Debt Facilities in December 2023. Based on the mine’s performance during the 2023 ramp-up year to the end of December and continuing technical evaluation work being undertaken on the production outlook for 2024, AMPL has commenced discussions with key stakeholders as part of a strategic review of operations with an initial focus on better matching the capital structure of AMPL to Abra’s expected performance. These discussions are ongoing and are anticipated to be concluded during 1H 2024. The market will be kept informed regarding the progress of these discussions.

DECEMBER HIGHLIGHTS

  • The following production metrics were achieved in December (subject to end of month reconciliations):
    • New monthly record ore processed of ~122kt (i.e., >1.45Mtpa implied annualised production rate compared to original design annualised throughput of 1.3Mtpa).
    • Ore mined of ~101kt at 5.6% Pb (~58kt at 5.5% Pb of Stope ore and ~43kt at 5.8% Pb of development ore. ~21kt at 2.1% Pb low-grade from mine development was also processed during the month). The grade improvement seen in development ore came from the addition of new core-vein headings. Processed ore grade will continue to improve with increased levels of stope production in the mill feed (targeting 80% of monthly ore production).
    • New monthly record for underground development of ~947m (compared to previous best month in September 2023 when 807m was achieved).
    • December lead concentrate shipment departed from Geraldton containing 9,622t on 15 December 2023. Next shipment is scheduled for 11 January 2024.
  • Expected December quarter mining and processing production estimates (subject to final end of month reconciliations):
    • Processing ~358kt at 4.7% Pb (Inclusive of low-grade top-up feed material).
    • ~25kt of lead concentrate produced.
    • Mining ~280kt at 5.6% Pb ore and ~2,440m of development.

Managing Director, Tony James commented, “In December, Abra has achieved the best production month year to date. Processing throughput continued to improve, and the processing plant consistently reached levels above the original design criteria of 1.3Mtpa. Mining and specifically stopping has not reached the levels required to match the plant which resulted in low-grade material being used as supplement feed lowering the overall processing grade.

Production schedules have been based on the monthly requirement of +800m lateral development being achieved. Not achieving this consistently in 2023 has had a detrimental affect with limited access to higher grade ore reserves.

The mining performance and grade is expected to continue to improve in 2024 with depth, additional work areas and higher stope production quantities. New technical evaluation work is currently underway which will form the basis of the 2024 outlook and ongoing discussions with key stakeholders based on the latest understanding of the orebody and other key performance indicators.

During December, underground development has accessed several high-grade core veins on the 1210mRL level which is confirming the latest geological information and understanding of that part of the orebody and its importance. During December the mined development grade was higher than the stopping grade for the first time”.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
The Conversation (0)
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Globe made of silver metal showing North America and South America.

Top 10 Silver-producing Countries

There are many factors to consider when investing in silver-focused stocks, including the silver price outlook, the company's management team and whether its assets are in one of the top silver-producing countries.

Location can be key, and knowing the top silver-producing countries can help investors made sound decisions. For example, high silver production in a particular nation might indicate mining-friendly laws or high-grade deposits.

So which country produces the most silver? In 2024, Mexico was once again the world’s leading silver-producing country, followed by China and Peru.

Keep reading...Show less
Silver bars on a financial chart background with upward trend lines.

Silver Miners Deliver Record Q2 Earnings on Fresh Price Highs

Top silver miners around the world delivered a slate of stronger second quarter earnings as a mixture of higher realized prices and production gains boosted results across the sector.

Spot silver has broken decisively above the US$35 per ounce level — its highest in more than 14 years — fueled by structural supply deficits and robust industrial demand that have tightened the market.

Keep reading...Show less
Anteros Metals (CSE:ANT)

Anteros Metals


Keep reading...Show less
Prismo Metals (CSE:PRIZ)

Prismo Metals


Keep reading...Show less
Stacks of shiny silver bars labeled "FINE SILVER" and "999" purity.

ASX Silver Stocks: 5 Biggest Companies in 2025

Silver is often compared to gold due to its importance in jewellery and as a safe-haven investment.

However, silver has many industrial applications too, including in electronics, automobiles and silverware, as well as medicine and photography. Energy transition applications are a growing demand sector for silver too — the metal is valued for its conductive capacity, which makes it particularly useful in the production of photovoltaic panels.

Silver has performed strongly in 2025 supported by several tailwinds, and broke through the US$39 per ounce mark on July 23 for the first time since 2011.

In this environment, it's a good time to learn about the largest primary silver companies on the ASX. These ASX silver stocks are sorted by market cap, and data was gathered using TradingView’s stock screener on July 24, 2025.

Keep reading...Show less
Completion of Silver Acquisition & Appointment of New Managing Director

Completion of Silver Acquisition & Appointment of New Managing Director

Rapid Critical Metals Limited (‘Rapid,’ ‘RCM’ or ‘Company’) is pleased to advise that the Company has today completed the acquisition of Silver Metal Group Limited’s two wholly-owned subsidiaries, Conrad Resources Pty Ltd and Webbs Resources Pty Ltd (Transaction), the terms of which are contained in the Company’s announcement to ASX of 22 May, 2025. The Transaction was approved by shareholders at the Extraordinary General Meeting (EGM) held on 7 July, 2025.

Keep reading...Show less

Latest Press Releases

Related News

×