Galena Mining

Abra December Production Update

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to provide preliminary production numbers for the Abra Base Metals Mine (“Abra”) for the month of December 2023 and the December quarter (subject to final reconciliation). Production levels during December show further improvement with new record highs achieved in several production areas including concentrate production, processed ore tonnes and mine development.


Abra Mining Pty Ltd (“AMPL”) made the first debt repayment of US$4.5M on its Taurus Debt Facilities in December 2023. Based on the mine’s performance during the 2023 ramp-up year to the end of December and continuing technical evaluation work being undertaken on the production outlook for 2024, AMPL has commenced discussions with key stakeholders as part of a strategic review of operations with an initial focus on better matching the capital structure of AMPL to Abra’s expected performance. These discussions are ongoing and are anticipated to be concluded during 1H 2024. The market will be kept informed regarding the progress of these discussions.

DECEMBER HIGHLIGHTS

  • The following production metrics were achieved in December (subject to end of month reconciliations):
    • New monthly record ore processed of ~122kt (i.e., >1.45Mtpa implied annualised production rate compared to original design annualised throughput of 1.3Mtpa).
    • Ore mined of ~101kt at 5.6% Pb (~58kt at 5.5% Pb of Stope ore and ~43kt at 5.8% Pb of development ore. ~21kt at 2.1% Pb low-grade from mine development was also processed during the month). The grade improvement seen in development ore came from the addition of new core-vein headings. Processed ore grade will continue to improve with increased levels of stope production in the mill feed (targeting 80% of monthly ore production).
    • New monthly record for underground development of ~947m (compared to previous best month in September 2023 when 807m was achieved).
    • December lead concentrate shipment departed from Geraldton containing 9,622t on 15 December 2023. Next shipment is scheduled for 11 January 2024.
  • Expected December quarter mining and processing production estimates (subject to final end of month reconciliations):
    • Processing ~358kt at 4.7% Pb (Inclusive of low-grade top-up feed material).
    • ~25kt of lead concentrate produced.
    • Mining ~280kt at 5.6% Pb ore and ~2,440m of development.

Managing Director, Tony James commented, “In December, Abra has achieved the best production month year to date. Processing throughput continued to improve, and the processing plant consistently reached levels above the original design criteria of 1.3Mtpa. Mining and specifically stopping has not reached the levels required to match the plant which resulted in low-grade material being used as supplement feed lowering the overall processing grade.

Production schedules have been based on the monthly requirement of +800m lateral development being achieved. Not achieving this consistently in 2023 has had a detrimental affect with limited access to higher grade ore reserves.

The mining performance and grade is expected to continue to improve in 2024 with depth, additional work areas and higher stope production quantities. New technical evaluation work is currently underway which will form the basis of the 2024 outlook and ongoing discussions with key stakeholders based on the latest understanding of the orebody and other key performance indicators.

During December, underground development has accessed several high-grade core veins on the 1210mRL level which is confirming the latest geological information and understanding of that part of the orebody and its importance. During December the mined development grade was higher than the stopping grade for the first time”.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
The Conversation (0)
Galena Mining Director & CEO Tony James

Galena Mining

Galena Mining CEO Tony James: On Track for Commercial Production in 2023youtu.be

Galena Mining (ASX:G1A) announced that construction at its Abra base metals mine is already 78 percent complete as of July 31, 2022. CEO Tony James said the company has done a great job building the project.

James commented, “The project's 80 percent complete. I think a lot of people have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job, and people will suddenly realise that everything's on track.”

The Abra base metals mine is a high-grade lead-silver mine located in the highly prospective Edmund sedimentary basin in the Gascoyne region of Western Australia. The project is under full construction in 2022 and remains on target for first commercial production in January 2023.


The activities that have progressed include concrete works and structural steel installation, as well as the mechanical, piping and electrical fit-out stages. The flotation cells and drive mechanisms are currently in shipment and are expected to arrive by September. The mine’s regrind mill has been shipped from Germany to Melbourne.

In July 2022, Galena raised a AU$17 million buffer for Abra’s critical initial commissioning and ramp-up stages.

“We raised some money in late July, which serves as our reserve facility. It’s been put in place by the joint venture partners to look after our working cap and risk period, which is the first initial commissioning period of the project. We don't believe we need to raise any more money at this stage.”

“I think we've done a great job building this project, I think we're on top of our risk profile. And this project is going to go ahead. We'll start producing concentrate in January and start supplying the market. We're very confident.”

Watch the full interview of Galena Mining CEO Tony James above.

Disclaimer: This interview is sponsored by Galena Mining (ASX:G1A). This interview provides information which was sourced by the Investing News Network (INN) and approved by Galena Mining in order to help investors learn more about the company. Galena Mining is a client of INN. The company’s campaign fees pay for INN to create and update this interview.

INN does not provide investment advice and the information on this profile should not be considered a recommendation to buy or sell any security. INN does not endorse or recommend the business, products, services or securities of any company profiled.

The information contained here is for information purposes only and is not to be construed as an offer or solicitation for the sale or purchase of securities. Readers should conduct their own research for all information publicly available concerning the company. Prior to making any investment decision, it is recommended that readers consult directly with Galena Mining and seek advice from a qualified investment advisor.

This interview may contain forward-looking statements including but not limited to comments regarding the timing and content of upcoming work programs, receipt of property titles, etc. Forward-looking statements address future events and conditions and therefore involve inherent risks and uncertainties. Actual results may differ materially from those currently anticipated in such statements. The issuer relies upon litigation protection for forward-looking statements. Investing in companies comes with uncertainties as market values can fluctuate.

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."

Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Southern Silver Acquires Right to Purchase Key Mining Claim Contiguous to Its Cerro Las Minitas Property in Durango, Mexico

Southern Silver Acquires Right to Purchase Key Mining Claim Contiguous to Its Cerro Las Minitas Property in Durango, Mexico

Southern Silver Exploration Corp. (TSXV: SSV,OTC:SSVFF) (the "Company" or "Southern Silver") is pleased to report it has reached an agreement to acquire the Puro Corazon mining claim located contiguous to its 100%-owned Cerro Las Minitas project (see Figures 1 and 2 below) from an arms-length third-party.

The Puro Corazon mine, which is operated privately, is currently mining approximately sixty tonnes of ore per day and produces a silver-lead concentrate and a zinc concentrate. Southern Silver will be incorporating Puro Corazon into the much larger Cerro Las Minitas project to unlock significant capital and operating synergies. Southern Silver intends to immediately commence a 12,000-meter infill drilling program at Puro Corazon and then in the first quarter of 2026, commence preparation of an updated Technical Report and Preliminary Economic Assessment ("PEA") in accordance with the provisions of National Instrument 43-101.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Silver Dollar Announces $4.0 Million Brokered LIFE Offering

Silver Dollar Announces $4.0 Million Brokered LIFE Offering

Silver Dollar Resources Inc. (CSE: SLV,OTC:SLVDF) (OTCQX: SLVDF) (FSE: 4YW) ("Silver Dollar" or the "Company") is pleased to announce that it has entered into an agreement with Research Capital Corporation to act as the sole agent and sole bookrunner (the "Agent") in connection with a "best efforts" private placement offering (the "Offering") for gross proceeds of a minimum of $950,000 and a maximum of $4,000,000 from the sale of a minimum of 2,714,286 and a maximum of 11,428,571 units of the Company (each, a "Unit") at a price of $0.35 per Unit.

Each Unit will consist of one common share of the Company (each, a "Unit Share") and one common share purchase warrant (a "Warrant"). Each Warrant will entitle the holder to purchase one common share of the Company (each, a "Warrant Share") at a price of $0.45 at any time on or before that date which is 36 months after the closing date of the Offering.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Locksley Resources

Analyst Report: Locksley’s US Strategy Strengthens Critical Minerals Position

Description:

Locksley Resources (ASX:LKY,OTQB:LKYRF,FSE: X5L) has strengthened its position in the US critical minerals sector through a dual strategy that could reduce funding risk and enhance shareholder value, according to a market update from Peak Asset Management.

Keep reading...Show less
Silver bars on pile of $100 bills and green chart going up.

Could the Silver Price Really Hit $100 per Ounce?

Will the First Majestic Silver (TSX:FR,NYSE:AG) CEO’s silver price prediction of over US$100 per ounce come true?

The silver spot price has surged nearly 40 percent in the first eight months of 2025 to reach a 14 year high, breaking through the US$40 per ounce mark in early September. The white metal has rallied on growing economic uncertainty amid ongoing geopolitical tensions and US President Donald Trump’s escalating trade war.

Well-known figure Keith Neumeyer, CEO of First Majestic, has frequently said he believes the white metal could climb even further, hitting the US$100 mark or even reaching as high as US$130 per ounce.

Keep reading...Show less
Silver and copper bars with "5 Top Canadian Mining Stocks" text overlay.

Top 5 Canadian Mining Stocks This Week: Carlton Precious Gains 78 Percent

Welcome to the Investing News Network's weekly look at the best-performing Canadian mining stocks on the TSX, TSXV and CSE, starting with a round-up of Canadian and US news impacting the resource sector.

Statistics Canada released its August jobs numbers on Friday (September 5). The report indicates a loss of 66,000 jobs in the Canadian economy and an increase in the unemployment rate to 7.1 percent from the 6.9 percent recorded in July.

The losses were primarily felt in the professional, scientific and technical services sector with a decrease of 26,000 jobs, followed by losses of 23,000 jobs in the transportation and warehousing sector and 19,000 jobs in manufacturing.

Keep reading...Show less
Silver bars in front of newspaper showing high price performance.

What Was the Highest Price for Silver?

Like its sister metal gold, silver has been attracting renewed attention as a safe-haven asset.

Although it continues to exhibit its hallmark volatility, many silver investors believe that a bull market is starting up for the precious metal. Experts are optimistic about the future, and as a result, some market watchers are looking for price forecasts and asking, “What was the highest price for silver?”

The answer reveals how much potential there is for the silver price to rise. Read on for a look at silver's historical moves, and what they could mean for both the price of silver today and the white metal’s price in the future.

Keep reading...Show less

Latest Press Releases

Related News