Galena Mining

Abra December Production Update

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to provide preliminary production numbers for the Abra Base Metals Mine (“Abra”) for the month of December 2023 and the December quarter (subject to final reconciliation). Production levels during December show further improvement with new record highs achieved in several production areas including concentrate production, processed ore tonnes and mine development.


Abra Mining Pty Ltd (“AMPL”) made the first debt repayment of US$4.5M on its Taurus Debt Facilities in December 2023. Based on the mine’s performance during the 2023 ramp-up year to the end of December and continuing technical evaluation work being undertaken on the production outlook for 2024, AMPL has commenced discussions with key stakeholders as part of a strategic review of operations with an initial focus on better matching the capital structure of AMPL to Abra’s expected performance. These discussions are ongoing and are anticipated to be concluded during 1H 2024. The market will be kept informed regarding the progress of these discussions.

DECEMBER HIGHLIGHTS

  • The following production metrics were achieved in December (subject to end of month reconciliations):
    • New monthly record ore processed of ~122kt (i.e., >1.45Mtpa implied annualised production rate compared to original design annualised throughput of 1.3Mtpa).
    • Ore mined of ~101kt at 5.6% Pb (~58kt at 5.5% Pb of Stope ore and ~43kt at 5.8% Pb of development ore. ~21kt at 2.1% Pb low-grade from mine development was also processed during the month). The grade improvement seen in development ore came from the addition of new core-vein headings. Processed ore grade will continue to improve with increased levels of stope production in the mill feed (targeting 80% of monthly ore production).
    • New monthly record for underground development of ~947m (compared to previous best month in September 2023 when 807m was achieved).
    • December lead concentrate shipment departed from Geraldton containing 9,622t on 15 December 2023. Next shipment is scheduled for 11 January 2024.
  • Expected December quarter mining and processing production estimates (subject to final end of month reconciliations):
    • Processing ~358kt at 4.7% Pb (Inclusive of low-grade top-up feed material).
    • ~25kt of lead concentrate produced.
    • Mining ~280kt at 5.6% Pb ore and ~2,440m of development.

Managing Director, Tony James commented, “In December, Abra has achieved the best production month year to date. Processing throughput continued to improve, and the processing plant consistently reached levels above the original design criteria of 1.3Mtpa. Mining and specifically stopping has not reached the levels required to match the plant which resulted in low-grade material being used as supplement feed lowering the overall processing grade.

Production schedules have been based on the monthly requirement of +800m lateral development being achieved. Not achieving this consistently in 2023 has had a detrimental affect with limited access to higher grade ore reserves.

The mining performance and grade is expected to continue to improve in 2024 with depth, additional work areas and higher stope production quantities. New technical evaluation work is currently underway which will form the basis of the 2024 outlook and ongoing discussions with key stakeholders based on the latest understanding of the orebody and other key performance indicators.

During December, underground development has accessed several high-grade core veins on the 1210mRL level which is confirming the latest geological information and understanding of that part of the orebody and its importance. During December the mined development grade was higher than the stopping grade for the first time”.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
The Conversation (0)
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Silver bars with silver graph going up.

When Will Silver Go Up?

It’s no secret that the silver market can be incredibly volatile. From February 2024 to February 2025 alone, silver has seen price levels ranging from lows of US$22.42 per ounce to highs of US$34.72 per ounce.

Many investors are highly focused on the precious metal’s movement. After all, silver is a safe-haven asset that generally fares well during turmoil, and recent times have been packed with tense geopolitical events, environmental disasters and economic uncertainty. While it's trended up over the last 12 months, silver has struggled to maintain the US$30 level.

Why is silver going up? With the support of looming lower interest rates, lower holding costs for bullion, increased central bank interest in precious metals, and the threat of trade wars under US President Donald Trump, the price of silver is trading at highs not seen in nearly decade. But, can silver go even higher? And when?

Answering the question, “When will silver go up?” is tricky. Even seasoned analysts can’t tell the future, and it’s difficult to find a consensus on the topic of when the metal could take off.

Keep reading...Show less
Rows of silver bars with two bars lying on top.

ASX Silver Stocks: 5 Biggest Companies

Silver is often compared to gold due to its importance in jewellery and as a safe-haven investment.

However, silver has many industrial applications too, including in electronics, automobiles and silverware, as well as medicine and photography. Energy transition applications are a growing demand sector for silver too — the metal is valued for its conductive capacity, which makes it particularly useful in the production of photovoltaic panels.

Silver supply has tightened in recent years as industrial demand rises. This was one of several factors that helped the silver price break through the US$34 per ounce mark in October of this year for the first time since 2012.

Keep reading...Show less

SilverCrest Closes Arrangement with Coeur Mining

TSX: SIL | NYSE American: SILV

 SilverCrest Metals Inc. ("SilverCrest" or the "Company") is pleased to announce the completion of the previously announced plan of arrangement (the "Arrangement") involving the Company and Coeur Mining, Inc. ("Coeur"), pursuant to which Coeur indirectly, among other things, acquired all of the issued and outstanding SilverCrest shares (the "SilverCrest Shares").

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Silver bar and metal.

5 Top Canadian Silver Stocks of 2025

Silver-mining companies and juniors have seen support from a strong silver price in 2025. The white metal has gained steadily since the start of the year, rising 11.47 percent to breach the US$32 per ounce mark.

Silver’s dual function as a monetary and industrial metal offers great upside. Demand from energy transition sectors, especially for use in the production of solar panels, has created tight supply and demand forces.

Demand is already outpacing mine supply, making for a positive situation for silver-producing companies.

Keep reading...Show less

First Majestic Announces 2025 Production and Cost Guidance and Announces Conference Call Details

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce the Company's consolidated 2025 production and cost guidance for the Company's four producing underground mines in Mexico, namely the Cerro Los Gatos Silver Mine (the Company holds a 70% interest in the Los Gatos Joint Venture that owns the mine), the Santa Elena SilverGold Mine, the San Dimas SilverGold Mine, and the La Encantada Silver Mine. The Company will be holding a conference call with management at 8:30 a.m. (PT) on Thursday, February 20, 2025, to discuss First Majestic's 2024 financial results and 2025 production and cost guidance.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

First Majestic Announces 2025 Production and Cost Guidance and Announces Conference Call Details

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce the Company's consolidated 2025 production and cost guidance for the Company's four producing underground mines in Mexico, namely the Cerro Los Gatos Silver Mine (the Company holds a 70% interest in the Los Gatos Joint Venture that owns the mine), the Santa Elena SilverGold Mine, the San Dimas SilverGold Mine, and the La Encantada Silver Mine. The Company will be holding a conference call with management at 8:30 a.m. (PT) on Thursday, February 20, 2025, to discuss First Majestic's 2024 financial results and 2025 production and cost guidance.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×