
- WORLD EDITIONAustraliaNorth AmericaWorld
September 15, 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 83% complete as of 31 August 2022. The arrival of the flotation cells and regrind mill to Australia completes the arrival of all the key construction equipment coming from overseas suppliers.
Managing Director, Tony James commented, “With the flotation cells and the regrind mill landing in Australia, all the key pieces of equipment required for Abra processing facility have arrived. On site, construction activities have now past 83% with focus at the plant shifting to installation of the remaining mechanical items, piping and electrical installation. Operational readiness activities continue as the site prepares to start some early dry commissioning activities. It’s also pleasing to see the TSF earthworks essentially completed and the power station reaching 94% completion”.
Figure 1 – Abra plant screening and materials handling (photo: 9 September).
Update on Abra Project progress
Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 90% complete. All key overseas supplied equipment itemised in the regular project updates shown in table 1 below have arrived in Australia. All the items in table 1 are shown as “strike-out” for completion purposes.
Table 1 – Key equipment order and delivery schedule from overseas suppliers.
Mine decline development continued in the East Decline during August. A total of 242 metres was developed with the decline reaching 1,337mRL. The decline location is 213m vertically below the surface and approximately 24m vertically above the orebody.
During August the primary ventilation raise drill pilot hole reached the 1,390mRL and back- reaming of the 6m diameter hole commenced.
In August, 15 new underground diamond drill grade control holes were completed (2,141m). Assays from the holes drilled in July are expected to be returned in September for evaluation. The second underground drill is also scheduled to commence drilling in early September, following installation of the required power services.
Click here for the full ASX Release
This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
The Conversation (0)
12 September 2022
Galena Mining
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
19 March
Silver X Secures US$50 Million to Expand Peru Project
Silver X Mining (TSXV:AGX,OTCQB:AGXPF) has tapped investor demand for exposure to the rising silver price, closing a US$50.4 million financing to fund expansion at its flagship project in Peru.It completed an oversubscribed brokered private placement of secured convertible debentures on... Keep Reading...
16 March
Vox Royalty Announces Inclusion in MVIS Global Junior Gold Miners Index and VanEck Junior Gold Miners ETF
DENVER, CO / ACCESS Newswire / March 16, 2026 / Vox Royalty Corp. (NASDAQ:VOXR)(TSX:VOXR) ("Vox" or the "Company"), a returns-focused mining royalty and streaming company, is pleased to announce that it has been added to the MVIS® Global Junior Gold Miners Index ("MVGDXJ"), the underlying... Keep Reading...
12 March
Ted Butler: Silver Blow-Off Top Years Away, How to Play Volatility
Precious metals analyst Ted Butler shares his thoughts on where the silver price will go next after running into triple digits and then pulling back. He expects a period of consolidation, but emphasized that the white metal's bull run isn't over. "I maintain that we are still relatively early in... Keep Reading...
12 March
Nine Mile Metals Announces Certified Assays from DDH-WD-25-01 of 3.83% CuEq Over 22.65 Meters (39.52 g/t Ag, 0.96 g/t Au, 0.99% Cu, 2.25% Pb, 1.61% Zn) and 4.33% CuEq Over 17.65 Meters (42.5 g/t Ag, 1.01 g/t Au, 1.2% Cu, 2.62% Pb, 2.05% Zn) Including 1.21 g/t Au and 50.33 g/t Ag Over 13.00 Meters
NINE MILE METALS LTD. (CSE: NINE) (OTC Pink: VMSXF) (FSE: KQ9) (the "Company" or "Nine Mile") is pleased to announce it has received certified assays for drill hole WD-25-01 at the Wedge Mine situated in the renowned Bathurst Mining Camp, New Brunswick (BMC).WD-25-01 HIGHLIGHTS:DDH WD-25-01 was... Keep Reading...
10 March
John Feneck: Gold, Silver to Retest Highs, "Don't Get Off the Horse"
John Feneck, portfolio manager and consultant at Feneck Consulting, explains why he expects gold and silver prices to retest January's highs, noting that he sees investors beginning to rotate away from the tech sector and toward commodities. "My suggestion is don't get off the horse, right?" he... Keep Reading...
10 March
Silver Stocks: 5 Biggest Silver-mining Companies in 2026
Silver mining companies are being supported by a silver price bull run in 2026. After climbing through 2025, silver broke its all-time high set in 1980 in October before reaching a new high of US$121.62 per ounce on January 29.The factors driving the metal's rise remain, most notably tightening... Keep Reading...
Latest News
Interactive Chart
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00







