
August 16, 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 78% complete as of 31 July 2022. New milestones have been achieved with the commencement of the installation of the ball-mill components and total underground development passing 2km in early August.
Managing Director, Tony James commented, “Construction activities have progressed past 78% complete. Most of the concrete work has been completed and structural steel installation increased to 352 tonnes (72% complete). Plant construction work is quickly progressing into the mechanical, piping, and electrical fit out stages. It’s also pleasing to see the progress being made with the operational readiness activities including first fills and critical spares, with orders placed for over 75% of the items”.
Figure 1 – Abra ball mill installation (photo: 10 August).
Three other announcements were released by the company between this monthly update and the previous monthly update dated 18 July 2022. The first was “Re-release: Abra Initial Production Guidance” (ASX: 25 July 2022). The second was “Galena Successfully Raises
$17 Million” (ASX: 26 July 2022) and “Diggers and Dealers Investor Presentation” (ASX: 1 August 2022).
Update on Abra Project progress
Overall progress continues to remain in line for Project completion, with first commercial production expected in Q1 CY2023. The processing plant engineering, procurement and construction has reached 85% complete. As previously advised, the remaining items on the key equipment order list shown in Table 1 below which are currently not received are the flotation cells and the regrind mill. The flotation cells and drive mechanisms are currently in shipment with 2 separate shipments delivering the flotation equipment to Fremantle. The flotation cells (bulk shipment) are currently expected to arrive by the 2nd September and the flotation drive mechanisms (container shipment) has arrived in Perth. The regrind mill is currently shipping from Germany and is now expected to arrive in Melbourne by 20th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. These revised arrival dates do not affect the project construction timelines.
Table Notes – All items with strike through have been delivered (1) Flotation equipment shipped in 2 separate parts. Flotation cells ETA now 2 September and Flotation drive mechanisms have arrived in Perth. (2) Regrind Mill ETA Melbourne 17 August for final assembly by Glencore Technology.
Table 1 – Key equipment order and delivery schedule from overseas suppliers.
Mine decline development continued in the East Decline and the 1,375mRL diamond drill drive during July. A total of 243 metres was developed during July with the East decline reaching 1,360mRL. During July the second leg of the mines escape way system was drilled (1.5-meter raise bore) down to 1,400mRL (150m below surface). By the end of July, 16 underground diamond drill holes have been completed.
Figure 2 - Progress of the Abra underground mine development to 31 July (yellow).
In surface bulk earthworks, good progress continued with the tailing’s storage facility (“TSF”) passing 50% completion. The final works package associated with the remaining non- processing infrastructure is progressing as planned with the power station reaching 81% complete.
Owners' costs and contingencies remain within budget.
Figure 3 – Abra TSF construction.
Click here for the full ASX Release
This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
Alert Options
No alert set
INN Article Notification
Alert Option
You will be notified when this event occurs. No additional settings needed.
The Conversation (0)
11 August
Smart Silver Strategies: Investing in the Dual Identity Metal
It’s time for silver mining investment to shine.As one of the world’s most prominent precious metals, silver presents as a key element in both the industrial and financial sectors. Its usage in powering electronics, solar panels and even medical devices makes it a compelling investment.Amidst... Keep Reading...
31 July
Silver Sector M&A Hits US$14.3 Billion As Miners Hunt for Growth
After five years of stagnant dealmaking, the silver mining sector underwent an aggressive US$14.3 billion consolidation wave since 2024. Data compiled by Metals Focus shows that announced transaction values surged from a negligible US$244 million over the preceding five-year window to US$14.3... Keep Reading...
28 July
Steve Penny: Silver at Key Inflection Point, What's Next for Price?
Steve Penny, founder of SilverChartist.com, shares his outlook for silver and gold, saying that while he expects much higher prices in the long term, the near and even medium term could bring more sideways movement for the precious metals. Penny also shares his current approach to oil, uranium... Keep Reading...
28 July
Silver Storm Ships First Concentrate from La Parrilla
Silver Storm Mining (TSXV:SVRS,OTCQB:SVRSF) dispatched its first commercial shipment of lead-silver and zinc concentrates from the La Parrilla mine in Mexico, marking the complex's official return to commercial production.The initial batch of ore through La Parrilla’s sulphide circuit yielded a... Keep Reading...
23 July
Silver Miners Post Record Q2 Output Despite Volatility
Silver prices fell more than 22 percent in the second quarter of 2026, as high volatility and macroeconomic pressures pulled the metal down from its earlier heights.However, top miners insulated their balance sheets by turning to production, driving record throughputs and strong operational... Keep Reading...
Latest News
Interactive Chart
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00









