Galena Mining

Abra Construction 63% Complete At End of April

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 63% complete on 30 April 2022. Construction achievements during the month include completion of the first 1,000m of decline development and the commencement of the mining the first underground diamond drill chamber. Both GR Engineering Services Ltd. (“GR Engineering”) and Contract Power Australia Pty. Ltd. have made excellent progress at the processing plant and the power station sites.


Managing Director, Tony James commented, “During April we were fortunate to have only 10 COVID-19 isolation cases on site, which has had limited impact on construction works. It’s a credit to the site team on how they have navigated the pandemic-related challenges to date. By the end of April, the decline has reached the 1,380mRL level which is now 67m vertically above the orebody. It's also pleasing to see the development of the first underground diamond drilling drives.

At the processing plant a total of 1,527m3 (61%) of concrete has been poured on track to reach overall design volume of 2,500m3 on schedule. The construction of the fine ore bin is nearing completion and structural steel arriving on site is being installed".

Figure 1 – Lifting of the primary jaw crusher and fine ore bin top into position.

Figure 2 – Shows work progress on site from November 2021 through to April 2022.

Update on Abra Project progress

Overall progress continues to remain in line with Project schedule for the production critical areas of mining and processing. The processing plant engineering, procurement and construction has reached 68% complete by project spend. Underground development continues to be ahead of plan and the first underground drilling drives have been mined. In bulk earthworks, the tailings storage facility (“TSF”) work was suspended whilst a technical review was completed on the proposed TSF design, investigating the material suitability and availability for dam wall construction. A revised TSF has been designed and works have been awarded and for resumption in the second half of May for completion well in advance of plant commissioning. The final works package associated with the remaining non-processing infrastructure, which is not production critical has been finalised and that work has commenced. This includes the remaining buildings and the drill-core processing and storage facility. Owners' costs and contingencies remain under budget.

Click here for the full ASX Release

This article includes content from GALENA MINING LTD. (ASX: G1A), licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
The Conversation (0)

Galena Mining

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
Prince Reports 27.43 Metres Grading 93.7 g/t Silver, 12.0% Mn, 2.29% Pb and 2.48% Zn at Its Prince Silver Project in Nevada;

Prince Reports 27.43 Metres Grading 93.7 g/t Silver, 12.0% Mn, 2.29% Pb and 2.48% Zn at Its Prince Silver Project in Nevada;

Mobilizes Third RC Drill Rig to Accelerate Ongoing 9,000-metre Drill Program

Prince Silver Corp. (CSE: PRNC) (OTCQX: PRNCF) (FSE: T130) ("Prince Silver" or the "Company") is pleased to announce additional assay results from its ongoing 9,000-metre reverse circulation ("RC") drilling program at the Company's Prince Silver Project ("Prince" or the "Prince Project"),... Keep Reading...
Three wooden blocks with black letters "M&A" rest on a computer keyboard.

Elemental Secures Panuco Silver-Gold Royalty in US$239 Million Vizsla Deal

Elemental Royalty (TSX:ELE,NASDAQ:ELE) has inked a US$239 million deal to acquire Vizsla Royalties (TSXV:VROY,OTCQX:VROYF), securing long-life exposure to the Panuco silver-gold project. The acquisition grants Elemental an uncapped 2 to 3.5 percent net smelter return royalty on the Mexico-based... Keep Reading...
A metallic paper airplane rests on a smooth light gray surface.

Record Silver Price a Key Q1 Tailwind for Miners

Following an unprecedented first quarter that saw silver prices break into triple digits before sharply correcting, the sector’s top producers registered massive cash generation and bolstered balance sheets. Silver achieved a historic milestone early in the first quarter, surging past US$100 an... Keep Reading...
Silver bars on shiny metallic surface.

Silver Stocks: 5 Biggest Silver-mining Companies in 2026

Silver mining companies are being supported by a silver price bull run in 2026. After climbing through 2025, silver broke its all-time high set in 1980 in October before reaching a new high of US$121.62 per ounce on January 29.The factors driving the metal's rise remain, most notably tightening... Keep Reading...
Lynette Zang, gold and silver bars.

Lynette Zang: Silver Fuse, Gold Anchor — This Currency Lifecycle is Ending

Lynette Zang, founder and CEO of Zang International, explains what gold and silver are saying about the world today, noting that while spot prices for the precious metals are down, they are on track to eventually assume their true fundamental value. "What I really want people to understand is... Keep Reading...

Interactive Chart

Latest Press Releases

Related News