Production Ramp-Up Proceeding to Plan with Technology Proven at Commercial Scale

Honeymoon on track to meet FY25 production target of 850,000lbs of U308 as set out in Feasibility Study; Construction of second and third NIMCIX production columns on schedule

Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to report on the June 2024 quarter, during which the Company achieved a number of milestones including first production at Honeymoon and at its 30 per cent-owned Alta Mesa Project in South Texas.

Highlights

Honeymoon Uranium Project, South Australia

Operations

  • Successful commissioning, with Boss proving its lixiviant chemistry and ion exchange technology at commercial scale
  • 57,364lbs of uranium produced during the June quarter
  • Ramp-up to steady-state production proceeding to plan, with key production metrics meeting Feasibility Study forecasts
  • Construction of NIMCIX columns 2 and 3 proceeding to plan and on target for commissioning in Q3 and Q4, 2024 respectively
  • Preliminary updates on costs to be provided once NIMCIX columns 2 and 3 are commissioned
  • Boss expects production of at least 850,000lbs of U308 in FY25; This is in line with Feasibility Study forecasts

Geology

  • Strong drilling intercepts confirm production potential of Gould’s Dam at Honeymoon
  • A further 96 mud rotary holes were drilled for 12,911m, with uranium mineralisation highlights including (PFN results, ppm pU3O8):

Alta Mesa, South Texas (Boss 30%)

  • Successful production start-up announced 13 June 2024
  • Alta Mesa expected to reach full operational capacity of 1.5Mlbs a year by 2026. Boss’ share
  • of Alta Mesa production is 30 per cent (450,000lbs a year at nameplate capacity)
  • Alta Mesa has potential for further resource growth and additional drying capacity of 500,000lbs a year

Corporate

  • As at 30 June 2024, Boss held liquid assets of A$272.5M; Boss has no debt
  • Well positioned to benefit from rising uranium prices with most of Honeymoon Life of Mine (LOM) production and all of Alta Mesa production uncontracted
  • Boss continues to strengthen its senior management team in line with the Company’s growing status as a global uranium producer; Highly experienced uranium exploration geologist Dr. Andy Wilde was appointed Chief Geologist

Boss Managing Director Duncan Craib said:

“Putting cake in the can with our first production at Honeymoon was a significant milestone for Boss which proved that our lixiviant chemistry and ion exchange technology works at commercial scale.

“The production ramp up at Honeymoon, including the key production metrics, is progressing in line with our Feasibility Study forecasts and therefore we are on track to produce at least 850,000 pounds of U308 in FY25.

“This strong outlook is also supported by the progress being made in the construction of the second and third NIMCIX columns which are scheduled to start operating, in line with the production ramp-up timetable, by Q3 and Q4, 2024 respectively.

“With both Honeymoon and Alta Mesa producing, Boss has become the only multi-asset uranium producer on the ASX.”


Click here for the full ASX Release

This article includes content from Boss Energy Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
BOE:AU
The Conversation (0)
Boss Energy (ASX:BOE)

Boss Energy Limited

Multi-mine uranium producer in Australia and the US

Multi-mine uranium producer in Australia and the US Keep Reading...
December 2024 Quarterly Results Presentation

December 2024 Quarterly Results Presentation

Boss Energy Limited (BOE:AU) has announced December 2024 Quarterly Results PresentationDownload the PDF here. Keep Reading...
Quarterly Cashflow Report - December 2024

Quarterly Cashflow Report - December 2024

Boss Energy Limited (BOE:AU) has announced Quarterly Cashflow Report - December 2024Download the PDF here. Keep Reading...
Quarterly Activities Report - December 2024

Quarterly Activities Report - December 2024

Boss Energy Limited (BOE:AU) has announced Quarterly Activities Report - December 2024Download the PDF here. Keep Reading...
Close-up of Kazakhstan flag with sun and eagle design on blue fabric.

Laramide Exits Kazakhstan Uranium Project After Government Policy Shifts

Laramide Resources (TSX:LAM,OTCQX:LMRXF) has pulled out of a greenfield uranium exploration venture in Kazakhstan, citing policy changes that it says have effectively shut the door on economically viable foreign investment in the country’s uranium sector.The Toronto-based company announced on... Keep Reading...
Resource Expansion Drilling Confirms 3,000 metres of New Uranium Trends with Best Drill Hole of 1.4 GT over 7.6 metres

Resource Expansion Drilling Confirms 3,000 metres of New Uranium Trends with Best Drill Hole of 1.4 GT over 7.6 metres

Resource expansion drilling of 50 holes completed at Lo Herma as planned yielding significant mineralised extensions over 3km to the north of proposed Mine Units 1 and 2. Drilling delivered AMU’s strongest intercept to date ahead of 2026 MRE and Scoping Study updates at AMU’s flagship Lo Herma ISR Uranium Project in Wyoming’s Powder River Basin.

American Uranium Limited (ASX:AMU, OTC:AMUIF) (American Uranium, AMU or the Company) is pleased to advise that 2025 resource expansion drilling at its Lo Herma ISR uranium project in Wyoming’s Powder River Basin (Lo Herma, the Project) has been completed according to plan with the drilling of 50... Keep Reading...
Completes phase one drilling and expands Sybella-Barkly

Completes phase one drilling and expands Sybella-Barkly

Basin Energy (BSN:AU) has announced Completes phase one drilling and expands Sybella-BarklyDownload the PDF here. Keep Reading...
Bruce Lane, executive director of American Uranium

American Uranium Eyes Resource, Scoping Study Update in 2026

American Uranium (ASX:AMU) is advancing drilling at its Lo Herma project in Wyoming, with work continuing into the winter season, according to Executive Director Bruce Lane in an interview with the Investing News Network. The company is currently awaiting results from recent hydrogeological... Keep Reading...

Interactive Chart

Latest Press Releases

Related News