July 23, 2024
Honeymoon on track to meet FY25 production target of 850,000lbs of U308 as set out in Feasibility Study; Construction of second and third NIMCIX production columns on schedule
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to report on the June 2024 quarter, during which the Company achieved a number of milestones including first production at Honeymoon and at its 30 per cent-owned Alta Mesa Project in South Texas.
Highlights
Honeymoon Uranium Project, South Australia
Operations
- Successful commissioning, with Boss proving its lixiviant chemistry and ion exchange technology at commercial scale
- 57,364lbs of uranium produced during the June quarter
- Ramp-up to steady-state production proceeding to plan, with key production metrics meeting Feasibility Study forecasts
- Construction of NIMCIX columns 2 and 3 proceeding to plan and on target for commissioning in Q3 and Q4, 2024 respectively
- Preliminary updates on costs to be provided once NIMCIX columns 2 and 3 are commissioned
- Boss expects production of at least 850,000lbs of U308 in FY25; This is in line with Feasibility Study forecasts
Geology
- Strong drilling intercepts confirm production potential of Gould’s Dam at Honeymoon
- A further 96 mud rotary holes were drilled for 12,911m, with uranium mineralisation highlights including (PFN results, ppm pU3O8):
Alta Mesa, South Texas (Boss 30%)
- Successful production start-up announced 13 June 2024
- Alta Mesa expected to reach full operational capacity of 1.5Mlbs a year by 2026. Boss’ share
- of Alta Mesa production is 30 per cent (450,000lbs a year at nameplate capacity)
- Alta Mesa has potential for further resource growth and additional drying capacity of 500,000lbs a year
Corporate
- As at 30 June 2024, Boss held liquid assets of A$272.5M; Boss has no debt
- Well positioned to benefit from rising uranium prices with most of Honeymoon Life of Mine (LOM) production and all of Alta Mesa production uncontracted
- Boss continues to strengthen its senior management team in line with the Company’s growing status as a global uranium producer; Highly experienced uranium exploration geologist Dr. Andy Wilde was appointed Chief Geologist
Boss Managing Director Duncan Craib said:
“Putting cake in the can with our first production at Honeymoon was a significant milestone for Boss which proved that our lixiviant chemistry and ion exchange technology works at commercial scale.
“The production ramp up at Honeymoon, including the key production metrics, is progressing in line with our Feasibility Study forecasts and therefore we are on track to produce at least 850,000 pounds of U308 in FY25.
“This strong outlook is also supported by the progress being made in the construction of the second and third NIMCIX columns which are scheduled to start operating, in line with the production ramp-up timetable, by Q3 and Q4, 2024 respectively.
“With both Honeymoon and Alta Mesa producing, Boss has become the only multi-asset uranium producer on the ASX.”
Click here for the full ASX Release
This article includes content from Boss Energy Limited, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
BOE:AU
INN Article Notification
The Conversation (0)
27 June 2024
Boss Energy Limited
Multi-mine uranium producer in Australia and the US
Multi-mine uranium producer in Australia and the US Keep Reading...
28 January 2025
December 2024 Quarterly Results Presentation
Boss Energy Limited (BOE:AU) has announced December 2024 Quarterly Results PresentationDownload the PDF here. Keep Reading...
28 January 2025
Quarterly Cashflow Report - December 2024
Boss Energy Limited (BOE:AU) has announced Quarterly Cashflow Report - December 2024Download the PDF here. Keep Reading...
28 January 2025
Quarterly Activities Report - December 2024
Boss Energy Limited (BOE:AU) has announced Quarterly Activities Report - December 2024Download the PDF here. Keep Reading...
08 April
Athabasca Basin Positions Canada to Lead Global Uranium Supply
With uranium demand forecast to rise by 28 percent by 2030, Canada is positioning itself to become the leading global supplier. The country is currently the second largest uranium producer, driven by ongoing development and discovery in Saskatchewan’s Athabasca Basin.The Athabasca Basin hosts... Keep Reading...
07 April
American Uranium: Targeting Resource Growth and Confidence Increase at Lo Herma Project
American Uranium (ASX:AMU,OTCQB:AMUIF) is advancing its flagship Lo Herma in-situ recovery (ISR) uranium project in Wyoming, with current work focused on increasing scale and improving resource confidence ahead of a planned scoping study.Recent drilling has grown the total resource to 9.45... Keep Reading...
06 April
Uranium Price Update: Q1 2026 in Review
Propelled by surging nuclear demand projections and energy transition needs, spot U3O8 prices started 2026 at just over US$80 per pound. The positive fundamentals pushed the energy fuel to US$101.41on January 29, marking a year-to-date high. Geopolitical instability in February and March weighed... Keep Reading...
06 April
5 Best-performing Canadian Uranium Stocks in 2026
The spot uranium price endured a turbulent first quarter of 2026, surging to a year-to-date high above US$101 per pound in late January before geopolitical shocks sent the market into a steep but short-lived decline.Driven by surging nuclear demand projections and growing global energy... Keep Reading...
Latest News
Interactive Chart
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00