PolyMet Mining Reports Results for Period Ended March 31, 2022

PolyMet Mining Corp. (TSX: POM) (NYSE American: PLM), today filed its financial results for the three months ended March 31, 2022, and provided a business update.

The company made steady progress in litigation, continued its focus on optimization and engineering efforts related to the NorthMet Project, and maintained full compliance with all operating permits during the period, according to Jon Cherry, chairman, president and CEO.

"In the latest court decision, the Minnesota Court of Appeals in January affirmed nearly all aspects of the company's water discharge permit, an indication of steady and meaningful progress," Cherry said.

However, the court ruled that the Minnesota Pollution Control Agency must consider whether any discharges are the "functional equivalent" of a direct surface water discharge. The ruling stems from a U.S. Supreme Court ruling unrelated to PolyMet and issued more than a year after PolyMet's permit was issued. This functional-equivalence analysis is expected to be completed this year and to affirm earlier conclusions.

The water discharge permit is one of only three permits that remain on hold pending additional legal proceedings or regulatory process, which is anticipated to be largely addressed this year. The other two are the Permit to Mine and the federal wetlands (Section 404) permit.

The company made progress on the wetlands permit as the U.S. Army Corps of Engineers completed a three-day section 401(a)(2) hearing under the Clean Water Act on May 5, in Cloquet, Minnesota. The hearing was held to determine if the project will violate water quality requirements within the reservation boundaries of the Fond du Lac Band of Lake Superior Chippewa. State and federal agencies concluded during environmental review and permitting that the project will not affect water quality before reaching the reservation, which is 116 river miles downstream.

"We are confident the Corps will affirm the original conclusions by state and federal agencies that the PolyMet project will meet water quality standards downstream, including at the Fond du Lac boundary," Cherry said. "We are committed to bringing the former taconite site up to modern, safe mining standards and cleaning up legacy issues in the process."

Regarding the Permit to Mine, a contested case hearing by the Minnesota Department of Natural Resources on the effectiveness of bentonite clay at the tailings impoundment is anticipated in the second or third quarter of this year. Several preliminary hearings already have been held.

To date, PolyMet has received favorable decisions in all six cases that have reached final conclusion - four federal and two state. More information on recent court developments can be found on the company's website at www.polymetmining.com/investors/news/ and on its SEDAR and EDGAR profiles.

Key Balance Sheet Statistics
(in '000 US dollars)


March 31, 2022

  December 31, 2021

Cash
$5,331
$2,958
Working capital 1

(59,615)

(17,609)
Total assets

473,396

468,126
Total liabilities

121,225

110,519
Shareholders' equity
$352,171
$357,607




 

 

1 Deficiency at March 31, 2022 primarily due to the $62.7 million convertible debt with Glencore being due March 31, 2023. Glencore has committed to provide financial support to enable the Company to continue its business operations for the next twelve months.

Key Income and Cash Flow Statement Statistics
(in '000 US dollars, except per share amounts)



Three months ended
March 31, 2022


Three months ended
March 31, 2021

Operations expense
$3,808
$3,576
Other expenses/(income):

 

 
    Debt accretion and interest

2,026

780
    Loss on refinancing

1,598

-
    Rehabilitation accretion

480

479
    Gain on financial asset fair value

(152)

(812)
    Loss/(gain) on restricted deposits

837

(277)
    Other income - net

5

(49)



 

 
Loss for the period:

8,602

3,697
Loss for the period ($/share)

0.08

0.04



 

 
Cash used in investing activities
$2,162
$1,758



 

 
Weighted average shares outstanding101,428,723

100,862,592

 

  • Loss for the three months ended March 31, 2022, was $8.6 million compared with $3.7 million for the prior year period. The increased loss was primarily due to non-cash charges related to debt refinancing, investments of restricted deposit, and interest expense partially offset by lower spend on project studies.
  • Capital expenditures for the three months ended March 31, 2022, was $2.2 million compared with $1.8 million for the prior year. The increase was primarily due to increased activities supporting legal defense of project permits.

The financial statements have been filed at www.polymetmining.com and on SEDAR and EDGAR and have been prepared in accordance with International Financial Reporting Standards. All amounts are in U.S. dollars. Copies can be obtained free of charge by contacting the company at 444 Cedar Street, Suite 2060, St. Paul, MN 55101, or by e-mail at info@polymetmining.com. Project developments described above are derived from these documents and should be read in conjunction with them.

* * * * *

About PolyMet

PolyMet is a mine development company that owns 100% of the NorthMet Project, the first large-scale project to have received permits within the Duluth Complex in northeastern Minnesota, one of the world's major, undeveloped mining regions. NorthMet has significant proven and probable reserves of copper, nickel and palladium - metals vital to infrastructure improvements and global carbon reduction efforts - in addition to marketable reserves of cobalt, platinum and gold. When operational, NorthMet will become one of the leading producers of nickel, palladium and cobalt in the U.S., feeding the supply chain with high-demand, responsibly mined metals crucial to the manufacture of clean energy and clean mobility technologies such as wind and solar generation, battery storage and electric vehicles.

Located in the Mesabi Iron Range, the project will provide economic diversity while leveraging the region's established supplier network and skilled workforce and generate a level of activity that will have a significant effect in the local economy. For more information: www.polymetmining.com.

For further information, please contact:

Media
Bruce Richardson, Corporate Communications
Tel: +1 (651) 389-4111
brichardson@polymetmining.com

Investor Relations
Tony Gikas, Investor Relations
Tel: +1 (651) 389-4110
investorrelations@polymetmining.com

PolyMet Disclosures

This news release contains certain forward-looking statements concerning anticipated developments in PolyMet's operations in the future. Forward-looking statements are frequently, but not always, identified by words such as "expects," "anticipates," "believes," "intends," "estimates," "potential," "possible," "projects," "plans," and similar expressions, or statements that events, conditions or results "will," "may," "could," or "should" occur or be achieved or their negatives or other comparable words. These forward-looking statements may include statements regarding the ability to receive environmental and operating permits, job creation, and the effect on the local economy, or other statements that are not a statement of fact. Forward-looking statements address future events and conditions and therefore involve inherent known and unknown risks and uncertainties. Actual results may differ materially from those in the forward-looking statements due to risks facing PolyMet or due to actual facts differing from the assumptions underlying its predictions.

PolyMet's forward-looking statements are based on the beliefs, expectations and opinions of management on the date the statements are made, and PolyMet does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations and opinions should change.

Specific reference is made to risk factors and other considerations underlying forward-looking statements discussed in PolyMet's most recent Annual Report on Form 40-F for the fiscal year ended December 31, 2021, and in our other filings with Canadian securities authorities and the U.S. Securities and Exchange Commission.

The Annual Report on Form 40-F also contains the company's mineral resource and other data as required under National Instrument 43-101.

No regulatory authority has reviewed or accepted responsibility for the adequacy or accuracy of this release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/123868

News Provided by Newsfile via QuoteMedia

POM:CA,PLM
The Conversation (0)
Juggernaut Announces Financing of $1,100,000 from Institutions and Accredited Investors

Juggernaut Announces Financing of $1,100,000 from Institutions and Accredited Investors

(TheNewswire)

Juggernaut Exploration Ltd.

Vancouver, British Columbia June 4 th 2025 TheNewswire - Juggernaut Exploration Ltd. (TSX-V: JUGR) (OTCQB: JUGRF) (FSE: 4JE) (the "Company" or "Juggernaut"), is pleased to announce a fully subscribed $1,100,000 hard dollar financing further confirming the quality of the newly discovered 11 km Highway of Gold surrounding the Eldorado porphyry system on the Big One property. The discovery is in an area of glacial and snowpack abatement next door to the gold-rich porphyry systems at Newmont Mining's Galore Creek. The Big One Property is a discovery previously announced Jan 20 th (Click Link) with assays up to 79.01 gt gold (2.54 ozt gold) and 3157.89 gt silver (101.5 ozt silver) from over 200 gold-silver-copper rich polymetallic veins up to 8 m wide and striking for up to 500 m that all remain open at surface. The Big One Project covers 33,693 hectares in a globally ranked tier 1 jurisdiction with tremendous additional discovery potential in the heart of the Golden Triangle, British Columbia.

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less
Aerial view of copper mine in Cobar, New South Wales.

Surge in Copper Demand Re-energises Cobar Basin’s Underexplored Resource Potential

The Cobar Basin in central New South Wales, Australia, may be emerging as a key focus for investors positioning for the next wave of copper supply. With a looming global shortage of the red metal and long-term demand being driven by electrification and decarbonisation, savvy investors are turning to proven but underexplored regions like Cobar — home to some of Australia’s highest-grade copper and polymetallic deposits.

Located within a region that holds 12 percent of Australia’s economic demonstrated copper resource, the Cobar Basin is backed by more than a century of mining success, strong infrastructure and modern exploration upside. With such high resource potential, junior explorers are keen to capitalise on the region’s rich copper history and established infrastructure.

Keep reading...Show less
Juggernaut Files for Final Approval of Oversubscribed Financing

Juggernaut Files for Final Approval of Oversubscribed Financing

(TheNewswire)

Juggernaut Exploration Ltd.

Vancouver, British Columbia TheNewswire - May 30, 2025 Juggernaut Exploration Ltd. (TSX-V: JUGR) (OTCQB: JUGRF) (FSE: 4JE) (the "Company" or "Juggernaut"), further to its April 14 th April 23 rd April 25 th 2025, and May 15, 2025, news releases, the Company is pleased to announce that it has filed documents with the TSX Venture Exchange (the "Exchange") seeking final approval to close its private placement financing (the "Financing") for aggregate gross proceeds of $10,362,735.

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less
Two copper-colored pens.

Harmony Gold to Acquire MAC Copper in US$1.03 Billion Deal

Harmony Gold Mining Company's (NYSE:HMY,JSE:HAR) wholly owned Australian subsidiary, Harmony Gold (Australia), has entered into a binding agreement to acquire MAC Copper (NYSE:MTAL,ASX:MAC).

MAC is the owner of the CSA copper mine in New South Wales. Its annual production comes to approximately 40,000 metric tons of copper, with 2024 output totaling 41,000 metric tons of the red metal.

The transaction is priced at US$12.12 per MAC share in cash, implying a total equity value of US$1.03 billion for MAC.

Keep reading...Show less
"Mine closed" sign with a yellow hard hat on textured blue wall.

Ivanhoe, Zijin Halt Operations at Kakula Copper Mine in DRC

Operations at Ivanhoe Mines' (TSX:IVN,OTCQX:IVPAF) Kakula mine in the Democratic Republic of the Congo (DRC) remain suspended after seismic activity was reported at the site.

Ivanhoe initially disclosed the interruption on May 20, when seismic activity was first detected, but extended the temporary shutdown on Monday (May 26) following several days of ongoing seismic events.

Employees working in the mine have been safely brought above ground, and mobile equipment has been removed.

Keep reading...Show less