SilverCrest Reports Third Quarter Financial Results and Update

SilverCrest Metals Inc. (TSX: SIL) (NYSE American: SILV) ("SilverCrest" or the "Company") is pleased to report the Company's unaudited financial results for the third quarter ("Q3") of 2020 and an update on activities. The unaudited condensed interim consolidated financial statements and management's discussion and analysis for the three and nine months ended September 30, 2020 are available under the Company's SEDAR profile on www.sedar.com or on SilverCrest's website www.silvercrestmetals.com.

Highlights - September 30, 2020

  • During the nine months ended September 30, 2020, the exploration team completed 146,000 metres of in-fill and expansion drilling at the Las Chispas Project ("Las Chispas"), located in Sonora Mexico. Further results from this work will be announced after compilation;

  • During the nine months ended September 30, 2020, the underground team completed approximately 4.1 kilometres of underground decline and lateral drifting, and stockpiled an additional estimated 19,000 tonnes of mineralized material for a total stockpile of an estimated 47,000 tonnes at estimated diluted grade of 1,130 gpt silver equivalent ("AgEq" at 75:1, Ag:Au);

  • Las Chispas site activities continued with the building of the administration and warehouse facilities, phase 1 of the temporary quarantined COVID-19 camp, communication system, and water pumping stations;

  • The Company continued to work with its consultants to advance the Feasibility Study for release during December 2020 or January 2021, provided that COVID-19 interruptions are minimal; and

  • As at October 31, 2020, SilverCrest is well funded with cash and cash equivalents of $184.0 million (US$138.2 million).

COVID-19 Update

The Company continues to adjust to the unprecedented COVID-19 conditions. At Las Chispas, the Company installed a fully confined temporary camp with a capacity for 160 essential persons to continue its exploration, underground workings, and construction of early works with the objective of limiting potential exposure of personnel and nearby communities to the virus. Before entering the confined camp, all persons are tested for COVID-19 (rRT-PCR test) and following receipt of negative tests, are transported to site using strict health and safety protocols. Once on site, all appropriate COVID-19 related protocols are enforced. As of September 30, 2020, the Company incurred approximately $1.0 million of expenditures related to COVID-19, the majority of which were for the construction and operation of the fully confined camp at Las Chispas and for providing assistance with medical needs in the local communities.

Exploration Update

During the nine months ended September 30, 2020, the Company completed approximately 146,000 metres of infill and expansion drilling (55% in-fill and 45% expansion). Budgeted drilling of an estimated 34,000 metres is planned for Q4, focusing on high-grade resource expansion. As of September 30, 2020, the Company had drilled an estimated cumulative 461,000 metres (1,712 drill holes) since inception of the project. Results since February 2019 (drilling cut-off date for the Preliminary Economic Assessment filed on SEDAR July 5, 2019) are expected to be presented in a sixth technical report, the Feasibility Study, anticipated in December 2020 or January 2021, subject to further impacts caused by the COVID-19 pandemic.

From January 1, 2020, the Company announced further exploration and drill results, which included:

  • Expansion of the Babi Sur Vein (news release dated January 20, 2020);

  • Discovery of Area 200 zone and additional drill results from the Babicanora Norte Vein (news release dated February 18, 2020);

  • Expansion of the Babi Vista Vein (news releases dated March 9, 2020, May 12, 2020 and August 13, 2020); and

  • Discovery of the El Muerto zone (news release dated November 5, 2020).

During Q3, the Company acquired the El Picacho property by paying $2.2 million (or US$1.6 million) for 100% ownership in 11 mining concessions located in Sonora, Mexico (near Las Chispas).

Operations Update

During the nine months ended September 30, 2020, the Company completed approximately 4.1 km of underground decline and lateral drifting, including 569 metres of in-vein drifting, and stockpiled an additional estimated 19,000 tonnes of mineralized material. By the end of October 2020, cumulatively, the Company had completed approximately 7.5 km of underground workings, including 1.3 km of in-vein drifting, and stockpiled approximately 47,000 tonnes of mineralized material with an estimated diluted grade 7.21 gpt Au and 590 gpt Ag, or 1,130 gpt AgEq (75:1 Ag:Au). The Company has budgeted 525 metres per month of underground workings for Q4, 2020.

Other ongoing site work during the nine months ended September 30, 2020 included feasibility site assessment work, basic engineering, detailed engineering, infrastructure construction activities, an extensive metallurgical test program (see news release dated March 5, 2020), completion of a vent raise associated with the Santa Rosa decline and underground workings, and permitting for various additional work. The Feasibility Study is progressing in parallel with the exploration and early works at Las Chispas. Camp expansion to house up to 500 essential persons and procurement of long lead equipment items are expected to start in Q4, 2020, the majority of which will be pending the announcement a positive feasibility study and decision to proceed with major construction.

Las Chispas Expenditures

During the nine months ended September 30, 2020, the Company incurred $49.0 million of expenditures at Las Chispas, for a cumulative total of $125.7 million since inception. To September 30, 2020, the Company had also capitalized acquisition costs of $5.5 million for the Las Chispas Property for cumulative property expenditures of $131.2 million.

Financial Results

At September 30, 2020, the Company held $188.3 million (December 31, 2019 - $110.4 million) as cash and cash equivalents. The primary factors that contributed to the increase in cash and cash equivalents from December 31, 2019 to September 30, 2020 include $142.8 million generated by financing activities, including the completion of the private placement (see new release dated April 17, 2020), the two private placements with SSR Mining Inc. (see news releases dated January 10, 2020 and April 24, 2020) and the exercise of options. These cash inflows were offset by $49.0 million incurred on the exploration program at Las Chispas.

During the three and nine months ended September 30, 2020, comprehensive losses were $23.7 million and $57.4 million, respectively, compared to $14.8 million and $38.4 million for the three and nine months ended September 30, 2019.

ABOUT SILVERCREST METALS INC.

SilverCrest is a Canadian precious metals exploration company headquartered in Vancouver, BC, that is focused on new discoveries, value-added acquisitions and targeting production in Mexico's historic precious metal districts. The Company's current focus is on the high-grade, historic Las Chispas mining district in Sonora, Mexico. The Las Chispas Project consists of 28 mineral concessions, of which the Company has 100% ownership and where all the known mineral resources of the Company are located. SilverCrest is the first company to successfully drill-test the historic Las Chispas Property resulting in numerous high-grade precious metal discoveries. The Company is led by a proven management team in all aspects of the precious metal mining sector, including taking projects through discovery, finance, on time and on budget construction, and production.

FORWARD-LOOKING STATEMENTS

This news release contains "forward-looking statements" and "forward-looking information" (collectively, "forward-looking statements") within the meaning of Canadian and United States securities legislation. These include, without limitation, statements with respect to: the strategic plans, timing and expectations for the Company's exploration and drilling programs of the Las Chispas Property, including preparing a feasibility study; information with respect to high grade areas and size of veins projected from underground sampling results and drilling results; and the possibility of future mining at the Las Chispas Property. Such forward-looking statements or information are based on a number of assumptions, which may prove to be incorrect. Assumptions have been made regarding, among other things: impact of the COVID-19 pandemic on operations and future operating costs; the reliability of mineralization and metallurgical test estimates, the conditions in general economic and financial markets; availability of skilled labour; timing and amount of expenditures related to underground development and drilling programs; and effects of regulation by governmental agencies. The actual results could differ materially from those anticipated in these forward-looking statements as a result of risk factors including: uncertainty as to the impact and duration of the COVID-19 pandemic; the timing and content of work programs; results of exploration activities; the interpretation of drilling results and other geological data; receipt, maintenance and security of permits and mineral property titles; environmental and other regulatory risks; project cost overruns or unanticipated costs and expenses; and general market and industry conditions. Forward-looking statements are based on the expectations and opinions of the Company's management on the date the statements are made. The assumptions used in the preparation of such statements, although considered reasonable at the time of preparation, may prove to be imprecise and, as such, readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of the date the statements were made. The Company undertakes no obligation to update or revise any forward-looking statements included in this news release if these beliefs, estimates and opinions or other circumstances should change, except as otherwise required by applicable law.

N. Eric Fier, CPG, P.Eng
Chief Executive Officer
SilverCrest Metals Inc.

For Further Information:

SilverCrest Metals Inc.
Contact: Jacy Zerb, Investor Relations
Telephone: +1 (604) 694-1730
Fax: +1 (604) 357-1313
Toll Free: 1-866-691-1730 (Canada & USA)
Email: info@silvercrestmetals.com
Website: www.silvercrestmetals.com
570 Granville Street, Suite 501
Vancouver, British Columbia V6C 3P1

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/68044

News Provided by Newsfile via QuoteMedia

The Conversation (0)
Klondike Silver Announces Private Placement

Klondike Silver Announces Private Placement

Klondike Silver Corp. (the “Company”) (TSX.V: KS) The Company announces that it is raising up to $1,500,000 through a non-brokered private placement (the “Offering”) of up to 30,000,000 units at a price of $0.05 per unit. Each unit will consist of one common share and one share purchase warrant, with each warrant exercisable for a period of 5 years from the closing at a price of $0.05 per share in year one and two then $0.08 per share in years three, four and five. All Units are subject to a four-month hold period from the date of issuance. Commissions may be paid on a portion of the funds raised. The Offering is subject to TSX Venture Exchange ("TSXV") final acceptance.

Keep reading...Show less

Endeavour Silver Announces First Drawdown on The Terronera Senior Secured Debt Facility

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to announce the first drawdown of $60 million of the $120 million senior secured debt facility (the " Debt Facility ") for the development of the Terronera Mine in Jalisco state, Mexico. The debt facility is provided by Société Générale and ING Bank N.V. and closed last year (see news release dated October 10, 2023 ). All references to dollars ($) in this news release are in United States dollars.

Construction of the Terronera mine is well underway and remains on track and has satisfied all conditions precedent to first draw. Key terms of the Debt Facility remain consistent with those previously announced in the Company's news release dated April 18, 2023 and the hedge contract terms have now been executed, further reducing financial risk in the project. The key terms of these contracts are as follows:

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Pan American Silver to Announce First Quarter 2024 Unaudited Results and Host Annual General and Special Meeting of Shareholders on May 8

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) (" Pan American ") will announce its unaudited results for the first quarter of 2024 after market close on Wednesday, May 8, 2024. Pan American will also be holding its Annual General and Special Meeting of shareholders (the "Shareholders Meeting") the same day at 3:00 pm PT.

First Quarter 2024 Unaudited Results Conference Call and Webcast

News Provided by Business Wire via QuoteMedia

Keep reading...Show less

Endeavour Silver Delivers Strong Production in Q1 2024

Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE: EXK; TSX: EDR) is pleased to report first quarter 2024 production of 1,460,006 silver ounces (oz) and 10,133 gold oz, for silver equivalent (1) ("AgEq") production of 2.3 million oz.

"Across our portfolio, the operations performed largely in-line with our expectations to deliver our annual production guidance of 8.1- 8.8 million silver equivalent ounces in 2024," commented Dan Dickson, Chief Executive Officer. "The infrastructure upgrades in pumping and ventilation have stabilized production at Guanacevi, and the impact from these improvements is being realized by our strong start to the year. Gold and silver prices have strengthened considerably, which will improve future revenues. I look forward to building upon the success of this quarter."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Rows of silver bars with two lying on top of them.

ASX Silver Stocks: 5 Biggest Companies in 2024

As a precious metal, silver is often compared to gold, and similarly holds an important role in the production of jewellery and as a safe-haven investment. However, silver also has increasing industrial uses.

In addition to its applications in jewellery and silverware, the white metal is becoming important for its use in the energy transition, specifically for its conductive capacity, which makes it particularly useful in the production of photovoltaic panels. It also has a wide array of uses in the production of electronics, automobiles, medicine and photography.

Despite its important role, silver is still largely a secondary metal, being mined as a by-product of lead, gold, zinc and copper. There are, however, several Australian companies that have put silver first.

Keep reading...Show less

Fortuna reports strong gold equivalent production of 112,543 ounces in the first quarter of 2024

Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) reports strong gold and gold equivalent production for the first quarter of 2024 from its five operating mines in West Africa and Latin America. Gold and silver production for the quarter was 89,678 ounces and 1.1 million ounces, respectively, or 112,543 gold equivalent ounces 1 including lead and zinc by-products.

Fortuna reiterates its 2024 annual production guidance range of 343 to 385 thousand ounces of gold and 4.0 to 4.7 million ounces of silver or between 457 and 497 thousand ounces of gold equivalent ounces 2 , including lead and zinc by-products (refer to Fortuna news release dated January 18, 2024 ). All amounts expressed in this news release are in US dollars unless otherwise stated.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
{{ sections }}

Latest Press Releases

Related News

×