NextSource Materials Announces Fabrication and Assembly of the Molo Graphite Mine Processing Plant Has Been Completed and Factory Acceptance Testing Initiated

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or the "Company") is pleased to announce that fabrication and assembly of the processing plant for Phase 1 of the Molo Graphite Mine (the "Processing Plant") has been completed by our Engineering, Procurement and Construction contractor (the "EPC Contractor") in their off-shore assembly facility and that Factory Acceptance Testing has been initiated

The Processing Plant has been designed and built using an all-modular approach and is capable of processing 240,000 tpa of ore and producing approximately 17,000 tpa of high-quality SuperFlake® graphite concentrate. The Processing Plant will now undergo Factory Acceptance Testing ("FAT") to validate the proper operation of the equipment and ensure that all design specifications and operational requirements have been achieved.

President and CEO, Craig Scherba commented,

"We have reached yet another major milestone with the completion of the fabrication and assembly of the Molo processing plant. The various challenges associated with the construction of a mine during a global pandemic have been greatly mitigated due to NextSource adopting a modular construction philosophy and because of the extremely hard work and perseverance of our technical teams."

FAT is the final and important assembly validation step that simulates and tests the end-to-end functional operation of the Processing Plant in a controlled engineering environment. Once all design specifications and functions have been verified, the Processing Plant will be containerized and shipped to the mine site for installation.

The FAT process is being overseen by the Company's EPC Contractor and SGS, the world-leader in testing, inspection and process certification. SGS designed the process flow sheet for the Processing Plant, which was based on their previous design and operation of our 200-tonne bulk sample pilot plant in 2015.

The Processing Plant is expected to be delivered to the mine site by the end of Q1 2022, followed by installation and commissioning in Q2 2022. The EPC Contractor and SGS will then perform Site Acceptance Testing prior to completing the commissioning process.

Phase 1 of the Molo Graphite Mine is fully funded and when commissioned, Molo will become one of the few operating graphite mines outside of China.

About NextSource Materials Inc.

NextSource Materials Inc. is a strategic materials development company based in Toronto, Canada that is intent on becoming a fully integrated, global supplier of critical battery and technology materials needed to power the sustainable energy revolution.

The Company's Molo graphite project in Madagascar is one of the largest known and highest-quality graphite deposits globally, and the only one with SuperFlake® graphite. Construction of Phase 1 of the Molo Project is underway, with commissioning expected in mid 2022.

NextSource Materials is listed on the Toronto Stock Exchange (TSX) under the symbol "NEXT" and on the OTCQB under the symbol "NSRCF".

For further information contact: +1.416.364.4911

Brent Nykoliation, Senior Vice President, Corporate Development at brent@nextsourcematerials.com or Craig Scherba, President and CEO at craig@nextsourcematerials.com

Safe Harbour: This press release contains statements that may constitute "forward-looking information" or "forward-looking statements" within the meaning of applicable Canadian and United States securities legislation. Readers are cautioned not to place undue reliance on forward-looking information or statements. Forward looking statements and information are frequently characterized by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate", "potential", "possible" and other similar words, or statements that certain events or conditions "may", "will", "could", or "should" occur. Forward-looking statements include any statements regarding, among others the timing of the re-assembly and commissioning of the Molo Plant, completion of FAT, collaboration agreements to build a value-added CSPG (anode) facility, time to commissioning the BAF, the demand for EVs, the use of SuperFlake®, successful and on-budget construction of the Molo Graphite Project, CSPG plant and BAF, sourcing the funds needed to construct the BAF, expansion of the BAF, estimated future production from the Molo Graphite Project, completion of the study relating to the BAF, and the continuation of the supply relationships of the Partners. These statements are based on current expectations, estimates and assumptions that involve a number of risks, which could cause actual results to vary and, in some instances, to differ materially from those anticipated by the Company and described in the forward-looking statements contained in this press release. No assurance can be given that any of the events anticipated by the forward-looking statements will transpire or occur or, if any of them do so, what benefits the Company will derive there from. The forward-looking statements contained in this news release are made as at the date of this news release and the Company does not undertake any obligation to update publicly or to revise any of the forward-looking statements, whether as a result of new information, future events or otherwise, except as may be required by applicable securities laws. Although the forward-looking statements contained in this news release are based on what management believes are reasonable assumptions, the Company cannot assure investors that actual results will be consistent with them. These forward-looking statements are made as of the date of this news release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the Company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release.

SOURCE: NextSource Materials Inc.



View source version on accesswire.com:
https://www.accesswire.com/677443/NextSource-Materials-Announces-Fabrication-and-Assembly-of-the-Molo-Graphite-Mine-Processing-Plant-Has-Been-Completed-and-Factory-Acceptance-Testing-Initiated

News Provided by ACCESSWIRE via QuoteMedia

NextSource Materials

NextSource Materials Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
NextSource Materials

NextSource Materials


Keep reading...Show less

Molo Graphite Mine now in Production with Downstream Battery Anode Facility Not Far Behind

Glowing graphite molecules.

ASX Graphite Stocks: 5 Biggest Companies in 2025

Graphite isn’t just used for pencils — it's also a key lithium-ion battery component due to its high conductivity and quick-charging capacity.

This means the graphite sector could experience tailwinds from rising demand for electric vehicles and energy storage systems in the coming years.

Australian investors searching for ways to get exposure to the graphite industry can look to the ASX, which is home to a slew of companies focused on the graphite market.

Keep reading...Show less
Australian money and magnifying glass.

CSIRO Backs Graphite with AU$400,000 R&D Grant Program

Australia’s Commonwealth Scientific and Industrial Research Organisation (CSIRO) has launched a new graphite research and development (R&D) program geared at assisting small- to medium-sized enterprises.

The initiative will allow grant recipients to collaborate with CSIRO scientists and access quality facilities.

“(It) comes at a crucial time,” said CSIRO Principal Research Scientist Adam Best.

Keep reading...Show less
NextSource Materials

NextSource Materials Shifts Battery Anode Facility Plans to Middle East for Accelerated Growth

 NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or "the Company") announces an update to its Battery Anode Facility (BAF) strategy, withdrawing from its Mauritius option to focus on accelerated, larger-scale opportunities in the Middle East.

Since November 2022, NextSource has been working closely with its project stakeholders to establish a world-class BAF in Mauritius. The Company leased a potential BAF site and invested in upgrading existing processes to ensure compliance with local regulations and to minimize any environmental impact. Throughout the extensive Environmental Impact Assessment (EIA) review process, the Company continually and promptly met all requests for information.

Keep reading...Show less
E-Power Resources (CSE:EPR)

E-Power Resources Inc. Announces Closing of a Third and Final Tranche of Oversubscribed Private Placement

E-Power Resources Inc (CSE: EPR) ("E-Power" or the "Company") announces that it has closed the third and final tranche "Third Tranche" of the private placement previously announced on March 12, 2025 (the "Private Placement").

An aggregate of 5,598,240 units (the " Units") of the Company were issued in the Third Tranche of the Private Placement at a price of $0.05 per Unit for gross proceeds of $279,912, each Unit being comprised of one common share in the capital of the Company (each a "Common Share") and one-half common share purchase warrant (each a "Warrant"), each Warrant entitling its holder thereof to acquire one additional common share (each a "Warrant Share") at a price of $0.10 per Warrant Share for a period of 60 months from the closing date (the "Offering").

Keep reading...Show less
Altech Batteries

Altech Batteries


Keep reading...Show less
NextSource Materials

NextSource Materials Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×