PolyMet Mining reports results for period ended March 31, 2021

PolyMet Mining Corp. (TSX: POM) (NYSE American: PLM) today reports it has filed its financial results for the three months ended March 31, 2021 and provides a business update.

The company made meaningful progress in litigation, continued its focus on optimization and engineering efforts related to the NorthMet Project, and maintained full compliance with all operating permits during the period, according to Jon Cherry, chairman, president and CEO.

"We are pleased with the rulings we received this spring from the Minnesota Supreme Court, which provide added clarity as we continue to work through the remaining legal challenges to our permits," Cherry said. "We expect litigation will continue to at least year-end 2021."

The following is a brief summary of recent cases:

  • In April 2021, the Minnesota Supreme Court overturned a decision by the Court of Appeals that had remanded the Permit to Mine to the Minnesota Department of Natural Resources (MDNR) for an open-ended contested case hearing. Of the many issues decided on by the court, PolyMet prevailed in the vast majority including the key legal challenge of whether state agencies have discretion to hold contested case hearings. However, the court ruled the MDNR must revisit, in a contested case hearing, one element of the expansive Permit to Mine: the effectiveness of bentonite clay capping for eventual closure of the tailings basin. "We expect this hearing will be addressed in an expeditious manner by the MDNR," Cherry said, noting that the contested case hearing is expected to run concurrent with other litigation that is in progress. Importantly, the Supreme Court also reversed the Court of Appeals' decision to require contested case hearings on the dam safety permits.

  • In March 2021, the U.S. Environmental Protection Agency (EPA) sought, and the company agreed to, a 90-day review of EPA's downstream water quality decision under section 401(a)(2) of the Clean Water Act. Because EPA's downstream water quality determination is a prerequisite for PolyMet's federal section 404 wetlands permit, the U.S Army Corps of Engineers on March 17 notified the company it had put the permit on hold for the duration of EPA's review. The company is participating in this review as appropriate. The EPA is expected to issue its determination at the end of the 90-day review period in early June.

  • In February 2021, the Minnesota Supreme Court overturned a decision by the Court of Appeals related to the PolyMet air permit. On the central argument in that case, the Supreme Court held that the lower court had "relied on erroneous interpretation of federal law" when it ruled against PolyMet. The case was returned to the Court of Appeals to resolve a limited number of items the lower court did not specifically address in its original decision. The Court of Appeals will make a decision by late July.

  • To date, PolyMet has received favorable decisions in all six cases that have reached final conclusion - four federal and two state. More information on recent court developments can be found on the company's website at www.polymetmining.com/investors/news/ and on its SEDAR and EDGAR profiles.

Key Balance Sheet Statistics
(in '000 US dollars)


  March 31, 2021     December 31, 2020  

Cash $ 6,463
$ 3,554
Working capital 1
(13,417 )
(15,241 )
Total assets
465,590

460,714
Total liabilities
98,101

91,075
Shareholders' equity $ 367,489
$ 369,639  
1 Deficiency primarily due to the $16.9 million promissory note with Glencore being due December 31, 2021. Glencore has committed to provide financial support to enable the Company to continue its business operations for the next twelve months.


 

 

 

Key Income and Cash Flow Statement Statistics
(in '000 US dollars, except per share amounts)


  Three months ended
March 31, 2021
    Three months ended
March 31, 2020
 

Operations expense $ 3,576
$ 5,207
Other expenses/(income):
 

   
      Debt accretion and interest
780

329
      Rehabilitation accretion
479

525
      Gain on financial asset fair value
(812 )
(292 )
      Restricted deposit (gain)/loss
(277 )
1,647
      Other income - net
(49 )
(7 )
 

 

 
Loss for the period:
3,697

7,409
Loss for the period ($/share)
0.04

0.07  
   

 

 
Cash used in investing activities $ 1,758
$ 2,553  
   

 

   
Weighted average shares outstanding
100,862,592

100,588,276  

 

  • Loss for the three months ended March 31, 2021, was $3.7 million compared with $7.4 million for the prior year period. The decreased loss was primarily due to reduced spend on studies and evaluation of the mineral resource and on investment gains from restricted deposits.
  • Capital expenditures for the three months ended March 31, 2021, was $1.8 million compared with $2.9 million for the prior year. The decrease was due to lower capitalized spend following receipt of permits in March 2019 as the company awaits resolution of legal challenges to permits.

The financial statements have been filed at www.polymetmining.com and on SEDAR and EDGAR and have been prepared in accordance with International Financial Reporting Standards. All amounts are in U.S. dollars. Copies can be obtained free of charge by contacting the company at 444 Cedar Street, Suite 2060, St. Paul, MN 55101, or by e-mail at info@polymetmining.com. Project developments described above are derived from these documents and should be read in conjunction with them.

* * * * *

About PolyMet

PolyMet is a mine development company that owns 100% of the NorthMet Project, the first large-scale project to be permitted within the Duluth Complex in northeastern Minnesota, one of the world's major, undeveloped mining regions. NorthMet has significant proven and probable reserves of copper, nickel and palladium - metals vital to infrastructure improvements and global carbon reduction efforts - in addition to marketable reserves of cobalt, platinum and gold. When operational, NorthMet will become one of the leading producers of nickel, palladium and cobalt in the U.S., providing a much needed, responsibly mined source of these critical and essential metals.

Located in the Mesabi Iron Range, the project will provide economic diversity while leveraging the region's established supplier network and skilled workforce, and generate a level of activity that will have a significant effect in the local economy. For more information: www.polymetmining.com.

For further information, please contact:

Media
Bruce Richardson, Corporate Communications
Tel: +1 (651) 389-4111
brichardson@polymetmining.com

Investor Relations
Tony Gikas, Investor Relations
Tel: +1 (651) 389-4110
investorrelations@polymetmining.com

PolyMet Disclosures

This news release contains certain forward-looking statements concerning anticipated developments in PolyMet's operations in the future. Forward-looking statements are frequently, but not always, identified by words such as "expects," "anticipates," "believes," "intends," "estimates," "potential," "possible," "projects," "plans," and similar expressions, or statements that events, conditions or results "will," "may," "could," or "should" occur or be achieved or their negatives or other comparable words. These forward-looking statements may include statements regarding the ability to receive environmental and operating permits, job creation, and the effect on the local economy, or other statements that are not a statement of fact. Forward-looking statements address future events and conditions and therefore involve inherent known and unknown risks and uncertainties. Actual results may differ materially from those in the forward-looking statements due to risks facing PolyMet or due to actual facts differing from the assumptions underlying its predictions.

PolyMet's forward-looking statements are based on the beliefs, expectations and opinions of management on the date the statements are made, and PolyMet does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations and opinions should change.

Specific reference is made to risk factors and other considerations underlying forward-looking statements discussed in PolyMet's most recent Annual Report on Form 40-F for the fiscal year ended December 31, 2020, and in our other filings with Canadian securities authorities and the U.S. Securities and Exchange Commission.

The Annual Report on Form 40-F also contains the company's mineral resource and other data as required under National Instrument 43-101.

No regulatory authority has reviewed or accepted responsibility for the adequacy or accuracy of this release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/83209

News Provided by Newsfile via QuoteMedia

The Conversation (0)
Empire Metals

Empire Metals Limited Announces Drilling Outlines Large, High-Grade Zone

Empire Metals Limited, theAIM-quoted and OTCQB-tradedexploration and development company,is pleased to report outstanding assay results from its latest drilling campaign at the Pitfield Project in Western Australia ('Pitfield' or the 'Project'). This programme, focused on the in-situ weathered cap at the Thomas Prospect, has delivered some of the highest titanium dioxide ('TiO₂') grades recorded to date and will underpin the Company's maiden JORC-compliant Mineral Resource Estimate ('MRE').

Highlights

Keep reading...Show less
Electric Royalties (TSXV:ELEC)

Electric Royalties Announces Interest Conversion under Convertible Credit Facility

Electric Royalties Ltd. (TSXV:ELEC)(OTCQB:ELECF) ("Electric Royalties" or the "Company") announces that Gleason & Sons LLC (the "Lender") has elected to convert C$536,500.00 of accrued interest on the principal amount of the Company's convertible credit facility (the "Interest") under the amended and restated convertible loan agreement dated February 16, 2024 between the Lender and Company (the "A&R Agreement"), into 3,700,000 common shares of the Company (the "Conversion Shares"), at a conversion price of C$0.145 per Conversion Share (the "Interest Conversion"). Subject to acceptance of the TSX Venture Exchange (the "TSXV"), the Company expects to issue the Conversion Shares in August 2025.

Keep reading...Show less
 Adam Woolridge, CEO of Cobre.

Cobre Unveils Maiden Resource at Comet, Targets Low-cost In-situ Copper Recovery

Highlighting the first mineral resource estimate (MRE) at Comet within the Ngami copper project in Botswana, Cobre (ASX:CBE) CEO Adam Woolridge outlines a path toward low-cost, scalable in-situ copper recovery, backed by significant exploration upside.

“You're looking at an exploration target of 200 million to 300 million tonnes at around 0.4 percent copper,” Woolridge said.

“When you start looking at this as an in-situ copper recovery process, you have really good grade continuity. And this has been reflected in the MRE. And it's also come out from just looking at this deposit from a geometry point of view — it's got a really simple geometry, a lot of great continuity, and it's been relatively cost effective to move each tonne of contained copper into category.”

Keep reading...Show less
"Welcome to Arizona" sign with sunburst design against a blue sky background.

Hudbay Secures US$600 Million Mitsubishi Partnership for Arizona Copper Project

Hudbay Minerals (TSX:HBM,NYSE:HBM) has struck a US$600 million deal with automobile giant Mitsubishi (TSE:8058) for a 30 percent stake in its Copper World project in Arizona, marking one of the largest foreign investments in the US copper sector in recent years.

Announced Tuesday (August 12), the agreement will see Mitsubishi pay US$420 million on closing and a further US$180 million within 18 months.Mitsubishi will also fund its 30 percent share of future capital contributions as the mine moves toward full construction.

Keep reading...Show less
Copper bars with weight stamps, stock market chart background.

What Was the Highest Price for Copper?

Strong demand in the face of looming supply shortages has pushed copper to new heights in recent years.

With a wide range of applications in nearly every sector, copper is by far the most industrious of the base metals. In fact, for decades, the copper price has been a key indicator of global economic health, earning the red metal the moniker “Dr. Copper.” Rising prices tend to signal a strong global economy, while a significant longer-term drop in the price of copper is often a symptom of economic instability.

After bottoming out at US$2.17 per pound, or US$5,203.58 per metric ton (MT), in mid-March 2020, copper has largely been on an upward trajectory.

Keep reading...Show less
Map of Argentina with the Chilean flag placed in central Argentina.

Codelco Seeks Partial Restart at El Teniente Mine After Fatal Collapse

Chile’s state-owned copper giant Codelco is seeking approval to restart parts of its flagship El Teniente mine less than a week after a deadly collapse killed six workers and forced a full suspension of operations, according to sources familiar with the matter.

The accident, triggered by a 4.2-magnitude seismic event last Thursday (July 31), halted production at the world’s largest underground copper mine.

Keep reading...Show less

Latest Press Releases

Related News

×