Long Term Pumping Tests to Commence at HMW

Long Term Pumping Tests to Commence at HMW

Galan Lithium Limited (ASX:GLN) (Galan or the Company) is pleased to announce the initiation of the long-term pumping test program at its 100%-owned Hombre Muerto West Lithium Project (HMW Project), located on the Western Basin of the Hombre Muerto salar in Catamarca Province, Argentina. These tests are an integral part of the current Definitive Feasibility Study (DFS) for the HMW Project


  • Four (4) pumping wells to be tested at Pata Pila and Rana de Sal
  • Hydraulic and chemical data to support ongoing HMW Definitive Feasibility Study (DFS)
  • Pumping test program expected to be finished by end Q3 CY2022
  • DFS on track for completion by end CY2022
The program consists of four (4) platforms. Two (2) are located at Pata Pila (PPB-01-21 (constructed) and PPB-02-22 (under construction)), with the other two located at Rana de Sal (RSB-01-22 (constructed) and RSB-02-22 (to be constructed)). The pump tests and subsequent analysis work is expected to be completed by the end of Q3 CY2022.
Each platform consists of one pumping well and 2 to 3 nearby monitoring wells. The construction of each monitoring well was specifically designed by WSP (Chile) to provide the optimal hydraulic information from the test and the expected evolution of the future production well field.
The pumping tests are comprised of two phases:
1. The first phase characterizes the hydraulic information and consists of an initial step-drawdown test, a recovery test and a constant rate test for a total of one week. Brine samples are also collected on each test.
2. The second phase is the execution of a long term (30 days) production pilot test. Several brine samples will be obtained during this phase.
The main objectives of these tests are to:
  • Determine the hydraulic properties of the brine reservoir (permeability, vertical anisotropy and storage coefficient) for each aquifer unit;
  • Verify the maximum sustainable pumping rate for each pumping well; and
  • Register hydraulic parameters (flow rate and brine level), chemical and physical parameters evolution of the brine during each test.

These tests are set to provide the critical information required for the planned Reserve model, to be conducted by SRK (Australia), as part of the DFS. The Reserve model will provide the basis for the production capacity parameters of the HMW Project, and the expected brine feed for the life-of-mine.


Click here for the full ASX release

This article includes content from Galan Lithium, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

GLN:AU
Galan Lithium

Galan Lithium Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galan Lithium

Galan Lithium


Keep reading...Show less
Drilling Commences at the Barra Lithium Project in Brazil

Drilling Commences at the Barra Lithium Project in Brazil

Summit Minerals Limited (ASX:SUM) (“Summit” or the “Company”) is pleased to announce that Summit’s maiden drilling program has commenced at the recently acquired 100% owned Barra Lithium Project (“Barra”).

The Barra Lithium Project consists of four recently acquired tenements that are located within close proximity to the existing operating Miranda Lithium mine that is within the Borborema Pegmatitic Province (“BPP”) in northeast Brazil.

Keep reading...Show less
Lithium Universe

Lithium Universe


Keep reading...Show less
CleanTech Lithium (AIM:CTL)

Issue of Equity and TVR


Keep reading...Show less
Lithium-ion batteries.

Rio Tinto Shares Initial Resources and Ore Reserves for Rincon Lithium Project

Rio Tinto ( ASX:RIO,NYSE:RIO,LSE:RIO) released an initial mineral resources and ore reserves report for its 100 percent owned Argentina-based Rincon project on Wednesday (December 4).

Mineral resources inclusive of ore reserves comprise 1.54 million tonnes of lithium carbonate equivalent in the measured category, with 7.75 million tonnes in the indicated category and 2.29 million tonnes in the inferred category.

Probable ore reserves are made up of 2.07 million tonnes of lithium carbonate equivalent.

Keep reading...Show less
Galan Lithium

Galan Lithium Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×