Galena Mining

Key Equipment Arrives as Abra Reaches 73% Complete

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 73% complete as of 30 June 2022. Significant equipment arrivals over the last month include the remaining mill equipment, secondary and tertiary cone crushers, and the remaining LNG tanks. The completion of the installation of 16,000 solar panels also delivers another significant construction milestone.


Managing Director, Tony James commented, “Construction activities are rapidly progressing with concrete poured at 2,378m3 (95% complete) and structural steel installation already up to 237 tonnes (42% complete). Arrival of key overseas supplied equipment being the remaining mill equipment, secondary and tertiary cone crushers, and LNG tanks has certainly reduced risk and energised the remaining work programs.

Decline mining delays occurred over 12 days in June, when the decline intercepted an un-grouted drill hole, which produced water, requiring an increase in pumping capacity. This was quickly rectified, and the mine plans were updated to keep the mining schedule aligned with the plant construction and commissioning timeframe. Underground grade control drilling continued in June in preparation for ore mining as planned”.

Figure 1 – Abra mine construction site (photo: 28 June 2022)

Update on Abra Project progress

Overall progress continues to remain in line for Project completion followed by first commercial production in Q1 CY2023. The processing plant engineering, procurement and construction has reached 79% complete. Remaining items on the key equipment order list shown in Table 1 which are currently not received are the flotation cells and the regrind mill. The flotation cells are completed and are waiting shipping from China and the regrind mill is currently shipping from Germany and is expected in Melbourne by 12th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. The arrival of key items since the last update has enabled GR Engineering to consolidate their remaining work schedules and plans.

Mine decline development was delayed in June for 12 days when the west decline intercepted an un-grouted diamond drill hole forcing an upgrade in the mine dewatering capacity. A total of 128m was developed prior to the delay, taking the west decline down to 1,357mRL which is 44m vertically above the orebody. During the delay the mine installed its primary ventilation fan on the surface and upgraded the underground power reticulation. Once this work was completed, the hole was plugged, and mining resumed.

A revised mining plan has been completed and put in place to ensure that following this development delay, mining targets remain in line with the plant completion and commissioning timeframe.

In surface bulk earthworks, good progress was made on the tailing’s storage facility (“TSF”) during June. The final works package associated with the remaining non-processing infrastructure is progressing as planned.

Owners' costs and contingencies remain within budget.

Figure 2 - Progress of the Abra underground mine development to the 1 July (yellow).


Click here for the full ASX Release

This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
The Conversation (0)
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Errawarra Resources

Transformational Acquisition of the High-Grade Elizabeth Hill Silver Project

A 180km2 tenement package located in Western Australia and completion of a $3M Placement

Errawarra Resources Ltd (ASX: ERW) (Errawarra or the Company) is delighted to announce that it has entered binding agreements (refer Acquisition Terms) pursuant to which the Company has acquired 70% of the historical Elizabeth Hill Silver Project (“Project” or “Elizabeth Hill”), 70% of the silver rights to the Pinderi Hills Project tenement package and 70% of the ownership of 3 tenements or tenement applications surrounding the silver project. This collective tenement package totalling 180km2 is in the Tier 1 mining jurisdiction of the Pilbara, Western Australia (Figure 2 – Project Location).

Keep reading...Show less
Dana Samuelson, silver bars.

Dana Samuelson: Silver Facing Supply Shock, Will Price Hit Tipping Point?

Dana Samuelson, president of American Gold Exchange, sheds light on key questions in the gold and silver market, including why the metals are flowing into the US in such large amounts.

He also shares his outlook on gold and silver prices, as well as the US economy.

Keep reading...Show less
Apollo Silver VP for Corporate Development Amandip Singh

Apollo Silver Targets Growth with California and Mexico Projects

Amandip Singh, vice president of corporate development at Apollo Silver (TSXV:APGO), discusses the 2025 work program for the Calico silver project in California, highlighting key milestones like permitting and engineering studies, as well as plans to unlock value at the Cinco de Mayo project in Mexico.

Apollo Silver Engages Danayi Capital for Investor Relations and Digital Marketing Services

Apollo Silver Engages Danayi Capital for Investor Relations and Digital Marketing Services

Apollo Silver Corp. (" Apollo Silver " or the " Company ") (TSX.V:APGO, OTCQB:APGOF, Frankfurt:6ZF0) is pleased to announce that it has engaged Danayi Capital Corp. (" Danayi "), an arm's-length service provider, to provide the Company certain investor relations and digital marketing services (the " Services "), in accordance with the policies of the TSX Venture Exchange (" TSXV ") and applicable securities laws. Based in Vancouver, British Columbia, Danayi specializes in marketing, advertising, and public awareness within the mining and metals sector. Under a digital marketing agreement dated March 13, 2025 (the " Agreement "), Danayi will provide digital media, marketing strategies, and advertising for a trial period of one month at a fee of US$50,000. The Company may extend the Agreement at its discretion. The engagement is subject to the approval of the TSXV.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
First Majestic Appoints Daniel Muniz Quintanilla to Its Board of Directors

First Majestic Appoints Daniel Muniz Quintanilla to Its Board of Directors

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce the appointment of Daniel Muñiz Quintanilla to the Company's Board of Directors, effective March 13, 2025.

Mr. Daniel Muñiz Quintanilla has more than 28 years of experience in international law, M&A, capital markets, and finance in the mining, logistics and infrastructure industries. He is currently a member of the board of directors of Novagold Resources, Inc. and Brookfield Infrastructure Partners L.P. Mr. Muñiz is also a Founding Partner of Axkan Capital Partners S.L., and serves as a director of Tharsis Mining S.L., a private company focused on copper, and as a director and special advisor to the chairman of both Sinda Ltd. and Sunshine Silver Mining & Refining Company, privately held companies in The Electrum Group's portfolio.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×