
July 17, 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 73% complete as of 30 June 2022. Significant equipment arrivals over the last month include the remaining mill equipment, secondary and tertiary cone crushers, and the remaining LNG tanks. The completion of the installation of 16,000 solar panels also delivers another significant construction milestone.
Managing Director, Tony James commented, “Construction activities are rapidly progressing with concrete poured at 2,378m3 (95% complete) and structural steel installation already up to 237 tonnes (42% complete). Arrival of key overseas supplied equipment being the remaining mill equipment, secondary and tertiary cone crushers, and LNG tanks has certainly reduced risk and energised the remaining work programs.
Decline mining delays occurred over 12 days in June, when the decline intercepted an un-grouted drill hole, which produced water, requiring an increase in pumping capacity. This was quickly rectified, and the mine plans were updated to keep the mining schedule aligned with the plant construction and commissioning timeframe. Underground grade control drilling continued in June in preparation for ore mining as planned”.
Figure 1 – Abra mine construction site (photo: 28 June 2022)
Update on Abra Project progress
Overall progress continues to remain in line for Project completion followed by first commercial production in Q1 CY2023. The processing plant engineering, procurement and construction has reached 79% complete. Remaining items on the key equipment order list shown in Table 1 which are currently not received are the flotation cells and the regrind mill. The flotation cells are completed and are waiting shipping from China and the regrind mill is currently shipping from Germany and is expected in Melbourne by 12th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. The arrival of key items since the last update has enabled GR Engineering to consolidate their remaining work schedules and plans.
Mine decline development was delayed in June for 12 days when the west decline intercepted an un-grouted diamond drill hole forcing an upgrade in the mine dewatering capacity. A total of 128m was developed prior to the delay, taking the west decline down to 1,357mRL which is 44m vertically above the orebody. During the delay the mine installed its primary ventilation fan on the surface and upgraded the underground power reticulation. Once this work was completed, the hole was plugged, and mining resumed.
A revised mining plan has been completed and put in place to ensure that following this development delay, mining targets remain in line with the plant completion and commissioning timeframe.
In surface bulk earthworks, good progress was made on the tailing’s storage facility (“TSF”) during June. The final works package associated with the remaining non-processing infrastructure is progressing as planned.
Owners' costs and contingencies remain within budget.
Figure 2 - Progress of the Abra underground mine development to the 1 July (yellow).
Click here for the full ASX Release
This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
The Conversation (0)
12 September 2022
Galena Mining
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
12 March
Ted Butler: Silver Blow-Off Top Years Away, How to Play Volatility
Precious metals analyst Ted Butler shares his thoughts on where the silver price will go next after running into triple digits and then pulling back. He expects a period of consolidation, but emphasized that the white metal's bull run isn't over. "I maintain that we are still relatively early in... Keep Reading...
12 March
Nine Mile Metals Announces Certified Assays from DDH-WD-25-01 of 3.83% CuEq Over 22.65 Meters (39.52 g/t Ag, 0.96 g/t Au, 0.99% Cu, 2.25% Pb, 1.61% Zn) and 4.33% CuEq Over 17.65 Meters (42.5 g/t Ag, 1.01 g/t Au, 1.2% Cu, 2.62% Pb, 2.05% Zn) Including 1.21 g/t Au and 50.33 g/t Ag Over 13.00 Meters
NINE MILE METALS LTD. (CSE: NINE) (OTC Pink: VMSXF) (FSE: KQ9) (the "Company" or "Nine Mile") is pleased to announce it has received certified assays for drill hole WD-25-01 at the Wedge Mine situated in the renowned Bathurst Mining Camp, New Brunswick (BMC).WD-25-01 HIGHLIGHTS:DDH WD-25-01 was... Keep Reading...
10 March
John Feneck: Gold, Silver to Retest Highs, "Don't Get Off the Horse"
John Feneck, portfolio manager and consultant at Feneck Consulting, explains why he expects gold and silver prices to retest January's highs, noting that he sees investors beginning to rotate away from the tech sector and toward commodities. "My suggestion is don't get off the horse, right?" he... Keep Reading...
10 March
Silver Stocks: 5 Biggest Silver-mining Companies in 2026
Silver mining companies are being supported by a silver price bull run in 2026. After climbing through 2025, silver broke its all-time high set in 1980 in October before reaching a new high of US$121.62 per ounce on January 29.The factors driving the metal's rise remain, most notably tightening... Keep Reading...
10 March
Brixton Metals Targets High-grade Silver and Copper in BC and Ontario
Brixton Metals (TSXV:BBB,OTCQB:BBBXF) Chairman, CEO, President and Director Gary Thompson revealed that following drilling commencement at Langis, the company is seeking to advance all its assets. Its flagship project, Thorn, is located in Northwest BC, and assays from recent sampling returned... Keep Reading...
09 March
ASX Silver Stocks: 5 Biggest Companies in 2026
The silver price rose to new highs this year, breaking well above its previous record set in 1980, as strong safe-haven demand for precious metals aligned with tightening supply.Over the years, silver supply has tightened alongside broadening industrial use, particularly in electronics and for... Keep Reading...
Latest News
Interactive Chart
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00







