Galena Mining

Key Equipment Arrives as Abra Reaches 73% Complete

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 73% complete as of 30 June 2022. Significant equipment arrivals over the last month include the remaining mill equipment, secondary and tertiary cone crushers, and the remaining LNG tanks. The completion of the installation of 16,000 solar panels also delivers another significant construction milestone.


Managing Director, Tony James commented, “Construction activities are rapidly progressing with concrete poured at 2,378m3 (95% complete) and structural steel installation already up to 237 tonnes (42% complete). Arrival of key overseas supplied equipment being the remaining mill equipment, secondary and tertiary cone crushers, and LNG tanks has certainly reduced risk and energised the remaining work programs.

Decline mining delays occurred over 12 days in June, when the decline intercepted an un-grouted drill hole, which produced water, requiring an increase in pumping capacity. This was quickly rectified, and the mine plans were updated to keep the mining schedule aligned with the plant construction and commissioning timeframe. Underground grade control drilling continued in June in preparation for ore mining as planned”.

Figure 1 – Abra mine construction site (photo: 28 June 2022)

Update on Abra Project progress

Overall progress continues to remain in line for Project completion followed by first commercial production in Q1 CY2023. The processing plant engineering, procurement and construction has reached 79% complete. Remaining items on the key equipment order list shown in Table 1 which are currently not received are the flotation cells and the regrind mill. The flotation cells are completed and are waiting shipping from China and the regrind mill is currently shipping from Germany and is expected in Melbourne by 12th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. The arrival of key items since the last update has enabled GR Engineering to consolidate their remaining work schedules and plans.

Mine decline development was delayed in June for 12 days when the west decline intercepted an un-grouted diamond drill hole forcing an upgrade in the mine dewatering capacity. A total of 128m was developed prior to the delay, taking the west decline down to 1,357mRL which is 44m vertically above the orebody. During the delay the mine installed its primary ventilation fan on the surface and upgraded the underground power reticulation. Once this work was completed, the hole was plugged, and mining resumed.

A revised mining plan has been completed and put in place to ensure that following this development delay, mining targets remain in line with the plant completion and commissioning timeframe.

In surface bulk earthworks, good progress was made on the tailing’s storage facility (“TSF”) during June. The final works package associated with the remaining non-processing infrastructure is progressing as planned.

Owners' costs and contingencies remain within budget.

Figure 2 - Progress of the Abra underground mine development to the 1 July (yellow).


Click here for the full ASX Release

This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
The Conversation (0)

Galena Mining

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."

Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion... Keep Reading...
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November... Keep Reading...
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station... Keep Reading...
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western... Keep Reading...
Silver Dollar Resources

Silver Dollar Samples Up to 2,753 g/t AgEq in Underground Sampling Campaign at its La Joya Silver Project

Silver Dollar Resources Inc. (CSE:SLV)(OTCQX:SLVDF)(FSE:4YW) ("Silver Dollar" or the "Company") is pleased to report underground sample assay results and preliminary geologic modeling of existing high-grade drill results in support of an exploration and mining strategy shift from open pit to... Keep Reading...
Critical Mineral Resources

Critical Mineral Resources

Critical Mineral Resources Plc is an exploration and resource development company operating in the Republic of Cyprus. Its current focus is on copper-gold opportunities. Some of its projects are the Kalavasos Project, the Troulli Project, and the Mathiatis Project. Keep Reading...
Silver bars on pile of $100 bills and green chart going up.

Could the Silver Price Really Hit $100 per Ounce?

Will the First Majestic Silver (TSX:FR,NYSE:AG) CEO’s silver price prediction of over US$100 per ounce come true?The silver price has surged over 80 percent in 2025 on growing economic uncertainty amid ongoing geopolitical tensions and US President Donald Trump’s escalating trade war, supported... Keep Reading...
Silver bars on shiny metallic surface.

Silver Stocks: 5 Biggest Companies in 2025

Silver mining companies are being supported by a silver price bull run in 2025. After climbing through 2025, silver broke its all-time high set in 1980 this October, reaching a new high of US$54.47 per ounce on October 17.The factors driving the metal's rise remain, most notably tightening... Keep Reading...
Closeup of a handshake over a desk with charts and a notebook.

Americas Gold & Silver to Acquire Crescent Silver in US$65 Million Deal

Mid-tier precious metals producer Americas Gold and Silver (TSX:USA,NYSEAMERICAN:USAS) continues to grow its North American footprint with its intended acquisition of privately owned Crescent Silver. The two companies inked a US$65 million binding purchase agreement on Thursday (November 13). It... Keep Reading...
Stacks of shiny silver bars labeled "FINE SILVER" and "999" purity.

ASX Silver Stocks: 5 Biggest Companies in 2025

The silver price rose to new highs this year, breaking above its previous record set in 1980, as strong safe-haven demand for precious metals aligned with tightening supply.Over the years, silver has seen a broadening of industrial use, particularly in electronics and for the energy transition.... Keep Reading...

Latest Press Releases

Related News