Galena Mining

Key Equipment Arrives as Abra Reaches 73% Complete

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 73% complete as of 30 June 2022. Significant equipment arrivals over the last month include the remaining mill equipment, secondary and tertiary cone crushers, and the remaining LNG tanks. The completion of the installation of 16,000 solar panels also delivers another significant construction milestone.


Managing Director, Tony James commented, “Construction activities are rapidly progressing with concrete poured at 2,378m3 (95% complete) and structural steel installation already up to 237 tonnes (42% complete). Arrival of key overseas supplied equipment being the remaining mill equipment, secondary and tertiary cone crushers, and LNG tanks has certainly reduced risk and energised the remaining work programs.

Decline mining delays occurred over 12 days in June, when the decline intercepted an un-grouted drill hole, which produced water, requiring an increase in pumping capacity. This was quickly rectified, and the mine plans were updated to keep the mining schedule aligned with the plant construction and commissioning timeframe. Underground grade control drilling continued in June in preparation for ore mining as planned”.

Figure 1 – Abra mine construction site (photo: 28 June 2022)

Update on Abra Project progress

Overall progress continues to remain in line for Project completion followed by first commercial production in Q1 CY2023. The processing plant engineering, procurement and construction has reached 79% complete. Remaining items on the key equipment order list shown in Table 1 which are currently not received are the flotation cells and the regrind mill. The flotation cells are completed and are waiting shipping from China and the regrind mill is currently shipping from Germany and is expected in Melbourne by 12th August. The regrind mill is being shipped to Melbourne so that Glencore Technology can finalise assembly with some Australian components. The arrival of key items since the last update has enabled GR Engineering to consolidate their remaining work schedules and plans.

Mine decline development was delayed in June for 12 days when the west decline intercepted an un-grouted diamond drill hole forcing an upgrade in the mine dewatering capacity. A total of 128m was developed prior to the delay, taking the west decline down to 1,357mRL which is 44m vertically above the orebody. During the delay the mine installed its primary ventilation fan on the surface and upgraded the underground power reticulation. Once this work was completed, the hole was plugged, and mining resumed.

A revised mining plan has been completed and put in place to ensure that following this development delay, mining targets remain in line with the plant completion and commissioning timeframe.

In surface bulk earthworks, good progress was made on the tailing’s storage facility (“TSF”) during June. The final works package associated with the remaining non-processing infrastructure is progressing as planned.

Owners' costs and contingencies remain within budget.

Figure 2 - Progress of the Abra underground mine development to the 1 July (yellow).


Click here for the full ASX Release

This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
The Conversation (0)
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Chris Marcus, silver bars.

Chris Marcus: Silver Market Tight, but Volatile — Price Drivers and Outlook

Chris Marcus, founder of Arcadia Economics, shares his latest thoughts on the silver market, outlining the white metal’s key price drivers right now.

He also shares his outlook for gold as its historic run continues.

Keep reading...Show less
Silver Dollar Extends Curlew Vein Strike Length to 700 Metres with Near Surface Intercepts at Ranger-Page

Silver Dollar Extends Curlew Vein Strike Length to 700 Metres with Near Surface Intercepts at Ranger-Page

Previously reported intercept of 162 g/t Ag, 15.5% Pb and 4.1% Zn over 3 metres interpreted to be the extension of the Curlew Vein from the Blackhawk Mine

Silver Dollar Resources Inc. (CSE: SLV) (OTCQX: SLVDF) (FSE: 4YW) ("Silver Dollar" or the "Company") is pleased to report geologic modeling results correlating to the recently reported near-surface drilling discoveries at the Ranger-Page Project located in northern Idaho's prolific Coeur d'Alene Mining District.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Futuristic 3D holographic visualization of resource and geophysical data analysis.

From Data to Discovery: How AI is Changing the Face of Modern Mining

Mineral exploration is one of the riskiest and most capital-intensive phases of the mining lifecycle. The process has traditionally relied heavily on historical geological records, field surveys and extensive drilling, often with low success rates and long time horizons. But a new wave of digital innovation is reshaping the landscape.

Artificial intelligence (AI) and advanced data analytics are increasingly at the forefront of a quiet revolution in mining, offering tools that enhance discovery potential, reduce exploration risk and deliver stronger returns for investors.

Historically, mineral exploration has been marked by high uncertainty and significant financial risk. Companies spend millions of dollars poring over old geological maps, conducting labor-intensive fieldwork and drilling test holes — all in hopes of finding an economically viable deposit. In fact, industry data suggests that only a tiny fraction of exploration projects — approximately one in a thousand — ever reaches production. This low success rate has often made early-stage mining investments difficult to assess and even harder to justify without deep technical insights or a strong appetite for risk.

Keep reading...Show less
Silver bar surrounded by shiny silver nuggets on a black background.

Top 5 Canadian Silver Stocks of 2025

Silver-mining companies and juniors have seen support from a strong silver price in 2025. Since the start of the year, the price of silver has increased by over 11 percent as of April 11, and it reached a year-to-date high of US$34.38 per ounce on March 27.

Silver’s dual function as a monetary and industrial metal offers great upside. Demand from energy transition sectors, especially for use in the production of solar panels, has created tight supply and demand forces.

Demand is already outpacing mine supply, making for a positive situation for silver-producing companies.

Keep reading...Show less
Stacks of shiny silver bars labeled "FINE SILVER" and "999" purity.

ASX Silver Stocks: 5 Biggest Companies in 2025

Silver is often compared to gold due to its importance in jewellery and as a safe-haven investment.

However, silver has many industrial applications too, including in electronics, automobiles and silverware, as well as medicine and photography. Energy transition applications are a growing demand sector for silver too — the metal is valued for its conductive capacity, which makes it particularly useful in the production of photovoltaic panels.

Silver supply has tightened in recent years as industrial demand rises. This was one of several factors that helped the silver price break through the US$34 per ounce mark in October 2024 for the first time since 2012. Heading into the second quarter of 2025, silver once again tested the US$34 level, although it has pulled back to US$31 amid market volatility as of April 10.

Keep reading...Show less
First Majestic Announces 2024 Sustainability Report and Mailing of 2025 AGM Meeting Materials

First Majestic Announces 2024 Sustainability Report and Mailing of 2025 AGM Meeting Materials

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce the release of its 2024 Sustainability Report and the mailing of its meeting materials for the Company's upcoming 2025 Annual General Meeting of Shareholders (the "2025 AGM").

2024 SUSTAINABILITY REPORT

News Provided by Newsfile via QuoteMedia

Keep reading...Show less

Latest Press Releases

Related News

×