Horizonte Minerals PLC - Araguaia remains on Schedule and on Budget

CONSTRUCTION HIGHLIGHTS:

  • Strong safety performance with zero lost time injuries ("LTI's") after over 990,000 hours worked
  • Construction is on-schedule with overall project progress approximately 28% complete
  • Construction is on-budget with approximately 75% of capital expenditure, over US$415m, awarded to date
  • Conditions related to the Senior Debt facility have been satisfied and first draw down has recently been completed
  • Ten-year renewable power contract secured at globally competitive prices, providing a foundation for future production costs in the lowest quartile globally

Horizonte Minerals Plc (AIM:HZM)(TSX:HZM) ("Horizonte" or the "Company") reports that it is continuing to make good progress on the construction of its 100%-owned Araguaia Nickel Project ("Araguaia" or "the Project") in Brazil which remains on-budget and on-schedule to commence production in Q1-2024

As of 30 November 2022, approximately 28% of the total Project construction programme has been completed. Earthworks are significantly advanced and due to be concluded in January 2023. The detailed engineering works are 87% complete and due to be concluded during Q1 2023. Approximately 75% of capital expenditure has been awarded to date, amounting to over US$415 million, and the key long lead items are running to schedule with the furnace shell due on site in late December and the rotary kiln due to be delivered in early Q1 2023.

Horizonte's Management will host a webinar on Thursday, 15 December 2022, at 10:00am GMT to discuss the construction progress. Investors and analysts are invited to access the webinar by registering in advance through the following link: https://www.investormeetcompany.com/horizonte-minerals/register-investor. Questions may be submitted at any time during the live presentation. A recording of the webinar will be available on the Company's website.

Jeremy Martin, CEO of Horizonte, commented:"We are very pleased with the construction progress achieved to date which places us in a strong position to deliver the project on-budget and on-schedule, and most importantly with a strong safety track record. We are also very pleased to have drawn from the Senior Debt facility, a core part of the overall funding package of Araguaia.

"Araguaia is expected to bring significant social and economic benefits to our host communities and local stakeholders and we were pleased to see our efforts recognized at the Brazilian Association of Human Resources awards held, in early December, by winning the ESG category for our local professional training program - Transforming Horizons.

"Overall, it has been a transformational year for the Company and I would like to thank our employees, contractors and key stakeholders for their strong efforts thus far to progress Araguaia's construction. I firmly believe that our collective efforts will enable us to quickly unlock significant value at Araguaia as we move closer to producing first nickel."

CONSTRUCTION PROGRESS SUMMARY

Health and Safety
The lost-time injury frequency rate ("LTIFR") at Araguaia in October 31, 2022 was 0.00 and the total recordable injury frequency rate ("TRIFR") was 1.45 based on a 12-month rolling average, which are calculated per million hours worked. We have continued our focus on embedding the critical risk controls with our growing workforce and reinforcement of the Horizonte Golden Rules. To complement these activities, we continued to implement tools to increase involvement and participation by our contracting partners in our safety systems and processes. Year to date over 1,600 internal safety audits have been conducted and over 1,550 safety plan observations have been completed.

In the quarter, the Company conducted a campaign of occupational hygiene monitoring where worker exposure to particulates, gases, noise and vibration were monitored. These activities, combined with routine medical surveillance, ensure that our workforce remain fit and healthy.

Construction activities
As seen in Figure 1, the reinforced primary crusher wall has now been completed, the next stage is to contour and hydroseed the pad sides and install the reinforced concrete base where the primary crusher will be mounted.

Figure 1: Reinforced primary crusher wall completed.

Horizonte Minerals PLC, Thursday, December 15, 2022, Press release picture

As seen in Figure 2, civil works are making good progress, where the electric arc furnace foundations have been successfully completed and the furnace baseplate, which is already on site, is due to be mounted in the coming weeks, marking the beginning of the electro-mechanical instillation phase. A timelapse video of the furnace foundation concrete pour totalling 2,707m3 of concrete can be found here: https://horizonteminerals.com/uk/en/videos_and_audio/

Figure 2: Showing the complete furnace foundation with the calcine transfer system foundation to the left of the furnace with the form work being prepared ahead of main concrete pour

Uma imagem contendo edifício, tapete Descrição gerada automaticamente

To date, 510 deep pile foundations, sunk to a depth of 18 meters, have been installed across the plant site, including for the rotary kiln support column foundations, calcination area, secondary crusher and homogenisation building, as seen in Figure 3.

Figure 3: Piling of the main steel supports for homogenisation building

Uma imagem contendo grama, velho, mesa, de madeira Descrição gerada automaticamente

The construction of the main 125 kilometre, 230kV powerline to power the process plant, is advancing along four work fronts. Pre-assembly of the tower structures is ongoing with drilling and concreting of the tower foundations progressing to schedule. Construction of the main substations at the mine site and connection point has commenced.

As shown in Figure 4 the furnace baseplate sections arrived on site with welding now complete, and the furnace shell is due to be delivered to site by the end of the year.

Figure 4: Store yard showing the furnace base plates and the steel beams (in blue) for the main furnace building structure

Horizonte Minerals PLC, Thursday, December 15, 2022, Press release picture

Environmental activities
In the Company's second quarter of active construction, environmental programs remained focussed on avoidance and mitigation of impacts. Fauna protection programs included active relocation of animals ahead of clearing for construction activity. To date over 140 individuals of 55 species have been rescued through this program. The Company's teams also continued collecting plant propagules (seeds, seedlings and similar) to ensure species and genetic diversity is maintained in the nursery plant generation programs. The biodiversity conservation centre construction and plant nursery expansion are now largely complete. The nursery is expected to deliver 50,000-60,000 native tree seedlings per year for rehabilitation and the generation of new green corridors.

As part of the Company's activities towards net positive impact on biodiversity, Horizonte commenced afforestation of pasture affected creek lines that had been impacted by long term agriculture and over-grazing. Associated with the Company's biodiversity objectives, a study of invasive plant species was completed, forming part of the ongoing update of Horizonte's Biodiversity Action Plan.

Social activities
In December 2022, Horizonte was proud to be recognised at the Brazilian Association of Human Resources awards as the winner in the ESG category for our local professional training program - Transforming Horizons. The program, conducted in partnership with Brazil's leading national industrial training provider, Serviço Nacional de Aprendizagem Industrial (SENAI) has delivered over 20 accredited training courses (12 completed to date), with over 200 graduates, 32% of whom are female and 14% are youth. In just seven months since inception, the Company has already employed 28 graduates at Araguaia.

POWER PURCHASE AGREEMENTS
In November, binding power purchase agreements were executed covering the first 10 years of Araguaia's production, locking in globally competitive prices, 30% below the Feasibility Power cost assumption. Representing approximately a third of Araguaia's operational cost, these competitive electricity prices will help establish the Company in the lowest cost quartile globally. Further, in line with the Company's target of operating in the lowest quartile of CO2 emissions, Horizonte will leverage the abundant hydropower available in Brazil. Through this, Horizonte is able to not only differentiate itself against global peers from a cost perspective, but also from an environmental standpoint.

PROJECT FINANCING ACTIVITIES
As announced on 8 December 2022, Horizonte satisfied all conditions precedent for the first utilization under the previously announced senior secured project finance debt facilities of US$346.2 million (the "Senior Debt Facilities") and is now in receipt of the first tranche of funds from the Senior Lenders.

This milestone demonstrated that the Company has made significant progress on the Project development schedule and that is has been able to satisfy to the Senior Lenders that the Company has:

  • made significant progress with construction, and in line with the schedule;
  • awarded all of the key material contracts, including equipment supply, Engineering Procurement and Construction Management (EPCM), port access and power supply;
  • have a long-term offtake in place for 100% of Araguaia's production from line 1 with a high quality counterparty in Glencore; and
  • have built out a high-quality team to deliver the Project.

Following the Company's announcement on 4 October 2022 regarding a proposed equity fundraise of approximately £61.7 million, Horizonte was pleased to announce an oversubscribed and upsized fundraise of approximately 70.5 million on 5 October 2022, which was finalised on 8 November 2022 following admission to AIM and the TSX of the newly issued shares.

For further information, visitwww.horizonteminerals.comor contact:

Horizonte Minerals plc
Jeremy Martin (CEO)
Simon Retter (CFO)
Patrick Chambers (Head of IR)

info@horizonteminerals.com
+44 (0) 203 356 2901

Peel Hunt LLP (Nominated Adviser & Joint Broker)
Ross Allister
David McKeown

+44 (0)20 7418 8900

BMO (Joint Broker)
Thomas Rider
Pascal Lussier Duquette
Andrew Cameron

+44 (0) 20 7236 1010

Tavistock (Financial PR)
Emily Moss
Cath Drummond
Adam Baynes

+44 (0) 20 7920 3150

ABOUT HORIZONTE MINERALS
Horizonte Minerals plc (AIM & TSX: HZM) is developing two 100%-owned, Tier 1 projects in Pará state, Brazil, the Araguaia Nickel Project and the Vermelho Nickel-Cobalt Project. Both projects are large scale, high-grade, low-cost, low-carbon and scalable. Araguaia is under construction with first metal scheduled for early 2024, when fully ramped up with Line 1 and Line 2, is forecast to produce 29,000 tonnes of nickel per year. Vermelho is at feasibility study stage and is expected to produce 25,000 tonnes of nickel and 1,250 tonnes of cobalt to supply the EV battery market. Horizonte's combined near-term production profile of over 60,000 tonnes of nickel per year positions the Company as a globally significant nickel producer. Horizonte's top three shareholders are La Mancha Investments S.à r.l., Glencore plc and Orion Resource Partners LLP.

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION

Except for statements of historical fact relating to the Company, certain information contained in this press release constitutes "forward-looking information" under Canadian securities legislation. Forward-looking information includes, but is not limited to, the ability of the Company to complete the acquisition of equipment as described herein, statements with respect to the potential of the Company's current or future property mineral projects; the ability of the Company to complete a positive feasibility study regarding the second RKEF line at Araguaia on time, or at all, the success of exploration and mining activities; cost and timing of future exploration, production and development; the costs and timing for delivery of the equipment to be purchased as described herein, the estimation of mineral resources and reserves and the ability of the Company to achieve its goals in respect of growing its mineral resources; the realization of mineral resource and reserve estimates and achieving production in accordance with the Company's potential production profile or at all. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking information is based on the reasonable assumptions, estimates, analysis and opinions of management made in light of its experience and its perception of trends, current conditions and expected developments, as well as other factors that management believes to be relevant and reasonable in the circumstances at the date that such statements are made, and are inherently subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking information, including but not limited to risks related to: the inability of the Company to complete the acquisition of equipment contemplated herein, on time or at all, the ability of the Company to complete a positive feasibility study regarding the implementation of a second RKEF line at Araguaia on the timeline contemplated or at all, exploration and mining risks, competition from competitors with greater capital; the Company's lack of experience with respect to development-stage mining operations; fluctuations in metal prices; uninsured risks; environmental and other regulatory requirements; exploration, mining and other licences; the Company's future payment obligations; potential disputes with respect to the Company's title to, and the area of, its mining concessions; the Company's dependence on its ability to obtain sufficient financing in the future; the Company's dependence on its relationships with third parties; the Company's joint ventures; the potential of currency fluctuations and political or economic instability in countries in which the Company operates; currency exchange fluctuations; the Company's ability to manage its growth effectively; the trading market for the ordinary shares of the Company; uncertainty with respect to the Company's plans to continue to develop its operations and new projects; the Company's dependence on key personnel; possible conflicts of interest of directors and officers of the Company, and various risks associated with the legal and regulatory framework within which the Company operates, together with the risks identified and disclosed in the Company's disclosure record available on the Company's profile on SEDAR at www.sedar.com, including without limitation, the annual information form of the Company for the year ended December 31, 2021, the Araguaia Report and the Vermelho Report. Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

SOURCE: Horizonte Minerals PLC



View source version on accesswire.com:
https://www.accesswire.com/731957/Horizonte-Minerals-PLC--Araguaia-remains-on-Schedule-and-on-Budget

News Provided by ACCESSWIRE via QuoteMedia

HZM:CA,HZM:LN
The Conversation (0)
Drill core samples in box.

Top 5 Canadian Mining Stocks This Week: Noble Mineral Exploration Gains 114 Percent on Nickel Assays

Welcome to the Investing News Network's weekly look at the best-performing Canadian mining stocks on the TSX, TSXV and CSE, starting with a round-up of Canadian and US news impacting the resource sector.

This week, the US Bureau of Labor Statistics released key inflation data, including its consumer and producer price index data on Wednesday (March 12) and Thursday (March 13). The reports show all items inflation was up 2.8 percent year-over-year in February, while core inflation — all items minus food and energy — was up 3.1 percent over that period. Both rose by 0.2 percent compared to January.

The numbers show that inflation has largely become stuck and is still far from the 2 percent target rate set by the US Federal Reserve. The data provides further insight into the health of the overall economy ahead of the Federal Open Market Committee meeting next week. The consensus among analysts is the Fed will choose to maintain its benchmark rate at 4.25 to 5 percent.

Keep reading...Show less
Cobalt, nickel and copper on periodic table.

Chalice Mining Makes Metallurgical "Breakthrough" at Gonneville Project

Chalice Mining ( ASX:CHN,OTC Pink:CGMLF) said on Monday (February 17) that it has made an important metallurgical breakthrough at its Gonneville projected, located in Western Australia.

The company said a hydrometallurgical process for nickel concentrate is no longer needed, as recent testwork results confirm that two saleable, smelter-grade flotation concentrates can be produced across the entire sulphide resource.

Managing Director and CEO Alex Dorsch said in a press release that this new information "materially reduces" capital and operating costs for Gonneville, also substantially reducing technical risk and process complexity.

Keep reading...Show less
"Anglo American" written on a phone screen with the words "buy" and "sell" behind it.

Anglo American to Sell Nickel Business to MMG for Up to US$500 Million

Anglo American (LSE:AAL,OTCQX:AAUKF) has agreed to sell its Brazil nickel operations to MMG Singapore Resources, a subsidiary of MMG (OTC Pink:MMLTF,HKEX:1208), for a cash consideration of up to US$500 million.

According to a Tuesday (February 18) press release, the transaction includes Anglo American’s Barro Alto and Codemin ferronickel operations, along with two development projects, Jacaré and Morro Sem Boné.

The purchase price comprises an upfront payment of US$350 million, a potential price-linked earnout of up to US$100 million and a further US$50 million contingent on a final investment decision for the development projects.

Keep reading...Show less
A small pile of nickel.

Nornickel's Net Profit Dips 37 Percent as Western Sanctions and Market Hurdles Persist

Moscow-based miner Norilsk Nickel (Nornickel) reported a 37 percent decline in net profit for 2024, citing ongoing western sanctions and lower metal prices as primary factors affecting its financial performance.

According to the company’s 2024 financial results, consolidated revenue fell 13 percent year-on-year to US$12.5 billion. EBITDA was down 25 percent to US$5.2 billion, with net profit dropping 37 percent to US$1.8 billion.

Company President Vladimir Potanin said that geopolitical restrictions, reduced access to western equipment and shifting trade patterns have negatively impacted the company’s ability to generate cashflow.

Keep reading...Show less
Blackstone Minerals Managing Director Scott Williamson.

Blackstone Minerals Expands Portfolio with Mankayan Copper-Gold Project Acquisition

In a strategic move that marks a significant expansion beyond the company's nickel-mining operations, Blackstone Minerals (ASX:BSX,OTC Pink:BLSTF,FWB:B9S) has announced a merger of equals with IDM International to acquire the Mankayan copper-gold project in the Philippines.

This acquisition positions Blackstone to leverage its expertise in the evolving mining landscape, driven by energy transition requirements, according to Blackstone Managing Director Scott Williamson.

"We can leverage (the) experience that we have from operating in Vietnam, which is a similar jurisdiction. We've operated in Vietnam for the last five or six years; we've been focused on nickel in Vietnam. Now we can use that team and our expertise in developing mines in Vietnam to the Mankayan project in the Philippines," he explained.

The Mankayan project is renowned for its high-grade copper and gold potential, supported by impressive historical drill results. Williamson emphasized the project's significance, indicating the potential for a substantial resource expansion.

Keep reading...Show less

Latest Press Releases

Related News

×