HMW Plant in Transit to Site, Phase 1 on Track

HMW Plant in Transit to Site, Phase 1 on Track

Highlights:

  • Nano-filtration plant has been assembled and tested off-site and is now in transit to Hombre Muerto West (HMW)

  • Phase 1 construction activities at HMW continue to advance toward completion, ahead of expected first production of lithium chloride in H1 2026

PERTH, AU / ACCESS Newswire / December 15, 2025 / Galan Lithium Limited (ASX:GLN,OTC:GLNLF) (Galan or the Company) is pleased to provide an update on the progress of its Phase 1 construction activities for HMW, as it advances towards its final stages.

Nano-Filtration Plant

Significant progress has been achieved on the nano-filtration plant, a critical component of the Phase 1 operation. In Sydney, general assembly of the nano-filtration plant has been completed, and pre-installation testing of the plant has also been successfully completed.

The nano-filtration plant is now in transit and is expected to arrive in South America in early 2026. Commissioning activities will commence immediately following the plant's arrival at the HMW site.

Figure 1. Load out of part of the nano-filtration plant

Figure 2. Nano-filtration pumping units loaded into containers for transport

Evaporation Ponds and Site Works

At HMW, evaporation Ponds 4 and 5 have been re-designed and scaled to support the Phase 1 production rate of 4,000 tonnes per annum of lithium carbonate equivalent ("LCE"). Liner installation on Pond 4 and 5 has been completed, and works are currently underway to subdivide areas of these ponds to optimize the concentration process of the lithium chloride product.

Figure 3. Liner installation team working on pond 4

Figure 4. Liner installation for ponds 4 and 5, adjacent to ponds 1-3.

Earthworks at the plant area have been completed, and the concrete foundation for the processing plant has been poured.

Key project infrastructure items, including power supply, electrical systems and pumps, have been ordered or procured in line with the Phase 1 construction schedule. Phase 1 of the HMW Project remains on track to be delivered within budget, with construction and procurement activities progressing in accordance with the Company's development plan.

The Company has also started to evaluate an option to expand the production capacity of Phase 1 HMW (4,000 tpa LCE) to the original Phase 1 capacity (around 5,400 tpa LCE) as studied in the 2023 HMW Phase 1 Definitive Feasibility Study.

Figure 5. Foundations for HMW plant site

Galan's Managing Director, Juan Pablo (JP) Vargas de la Vega, commented:

"Solid progress at Hombre Muerto West continues to reflect the strong commitment and teamwork of our entire team as well as our contractors and partners at Authium Ltd. Completing assembly and testing of the nano-filtration plant and advancing site works at HMW are important milestones as we move closer to first production. The project is transitioning into an exciting final phase of construction and commissioning. The momentum being built across the team gives us confidence as we move toward becoming a producing lithium company."

The Galan Board has authorised this release.

For further information contact:

COMPANY

Juan Pablo ("JP") Vargas de la Vega
Managing Director
jp@galanlithium.com.au
+ 61 8 9214 2150

MEDIA

Matt Worner
Vector Advisors
mworner@vectoradvisors.au
+61 429 522 924

SOURCE: Galan Lithium Limited



View the original press release on ACCESS Newswire

News Provided by ACCESS Newswire via QuoteMedia

GLN:AU
The Conversation (0)
Galan Lithium

Galan Lithium

Developing high-grade lithium brine projects in Argentina

Developing high-grade lithium brine projects in Argentina Keep Reading...
Successful Due Diligence Ends - $20M Placement To Proceed

Successful Due Diligence Ends - $20M Placement To Proceed

Galan Lithium (GLN:AU) has announced Successful Due Diligence Ends - $20m Placement To ProceedDownload the PDF here. Keep Reading...
Final At-The-Market Raise for 2025

Final At-The-Market Raise for 2025

Galan Lithium (GLN:AU) has announced Final At-The-Market Raise for 2025Download the PDF here. Keep Reading...
Quarterly Activities and Cash Flow Report

Quarterly Activities and Cash Flow Report

Galan Lithium (GLN:AU) has announced Quarterly Activities and Cash Flow ReportDownload the PDF here. Keep Reading...
Incentive Regime for HMW Project in Argentina

Incentive Regime for HMW Project in Argentina

Galan Lithium (GLN:AU) has announced Incentive Regime for HMW Project in ArgentinaDownload the PDF here. Keep Reading...
Trading Halt

Trading Halt

Galan Lithium (GLN:AU) has announced Trading HaltDownload the PDF here. Keep Reading...
Latest Intercepts Confirm Continuity Across Drill Program

Latest Intercepts Confirm Continuity Across Drill Program

Rapid Critical Metals (RCM:AU) has announced Latest Intercepts Confirm Continuity Across Drill ProgramDownload the PDF here. Keep Reading...
Spartan Metal's New Land Package includes Past Producing Yellow Jacket Tungsten Mine

Spartan Metal's New Land Package includes Past Producing Yellow Jacket Tungsten Mine

(TheNewswire) Vancouver, Canada TheNewswire - February 05, 2026 Spartan Metals Corp. ("Spartan" or the "Company") (TSX-V: W OTCQB: SPRMF | FSE: J03) is pleased to announce that within its recently staked land expansion of the Tungstonia Claim block at its 100% owned Eagle Project in eastern... Keep Reading...
NextSource Materials Executes Letter of Intent with One of the Major Japanese Anode Processors to Supply EV Anode Material to OEMs

NextSource Materials Executes Letter of Intent with One of the Major Japanese Anode Processors to Supply EV Anode Material to OEMs

TORONTO, ON / ACCESS Newswire / February 5, 2026 / NextSource Materials Inc. (TSX:NEXT,OTC:NSRCF)(OTCQB:NSRCF) ("NextSource" or the "Company") is pleased to announce that that it has executed a letter of intent ("LOI") with a one of the major Japanese anode material producers (the "Producer")... Keep Reading...
New Options Prospectus

New Options Prospectus

New Age Exploration (NAE:AU) has announced New Options ProspectusDownload the PDF here. Keep Reading...
SAGA Metals Achieves 100% Drilling Success in 2025-Reports Final Assays from Trapper South at Radar Critical Minerals Project in Labrador

SAGA Metals Achieves 100% Drilling Success in 2025-Reports Final Assays from Trapper South at Radar Critical Minerals Project in Labrador

Saga Metals Corp. ("SAGA" or the "Company") (TSXV: SAGA,OTC:SAGMF) (OTCQB: SAGMF) (FSE: 20H), a North American exploration company focused on critical mineral discoveries, is pleased to announce the assay results for the four (4) remaining diamond drill holes completed in Q4 2025 at the Trapper... Keep Reading...
NextSource Materials Executes Letter of Intent with Hanwa and JOGMEC for a US$30 Million Strategic Investment in UAE Battery Anode Facility

NextSource Materials Executes Letter of Intent with Hanwa and JOGMEC for a US$30 Million Strategic Investment in UAE Battery Anode Facility

Highlights:Strategic Japanese investment and partnership achieved through an executed LOI with Hanwa Co., Ltd. ("Hanwa") and Japan Organization for Metals and Energy Security ("JOGMEC") for a potential project-level equity investment in the UAE Battery Anode Facility ("BAF") of up to US$30... Keep Reading...

Interactive Chart

Latest Press Releases

Related News