Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


Highlights

  • Abra Project 87% complete at end of the Quarter (14% of construction works completed during the Quarter). Project focus remains on underground access to the orebody and completion of the processing plant and remaining surface infrastructure.
  • Underground development achieved 771m advance during the Quarter remaining on schedule with the decline reaching 1,300mRL. The decline is 13m below the top of the orebody and 250m below the surface.
  • Overall processing plant construction has reached 93% complete. Plant engineering and drafting work is 100% complete and site construction work is 90% complete.
  • All key overseas supplied equipment has arrived on site.
  • Completed oversubscribed placement to raise A$17.2M.
  • US$25M final debt drawdown was completed under the Taurus Debt Facilities.
  • Cash balance at Quarter-end A$60.5M.

ABRA BASE METALS MINE (60%-OWNED)

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted and under construction. First production of its high-value, high-grade lead- silver concentrate is currently scheduled for the first quarter of 2023 calendar-year.

Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.

G1A:AU
The Conversation (0)
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Boab Metals Limited

Analyst Report Highlights Boab Metals’ Valuation and Growth Prospects

Description:

A recent analyst report from East Coast Research underscores Boab Metals (ASX:BML) as a compelling investment opportunity, assigning a base-case valuation of AU$0.47 per share and a bull-case valuation of AU$0.51. This assessment reflects the company's robust fundamentals, particularly in terms of its Sorby Hills lead-silver-zinc project, which boasts a pre-tax NPV8 of A$411 million and an IRR of 37 percent.

Keep reading...Show less
Apollo Silver (TSXV:APGO)

Apollo Silver

Keep reading...Show less
Chris Marcus, silver bars.

Chris Marcus: Silver Market Tight, but Volatile — Price Drivers and Outlook

Chris Marcus, founder of Arcadia Economics, shares his latest thoughts on the silver market, outlining the white metal’s key price drivers right now.

He also shares his outlook for gold as its historic run continues.

Keep reading...Show less
Silver Dollar Extends Curlew Vein Strike Length to 700 Metres with Near Surface Intercepts at Ranger-Page

Silver Dollar Extends Curlew Vein Strike Length to 700 Metres with Near Surface Intercepts at Ranger-Page

Previously reported intercept of 162 g/t Ag, 15.5% Pb and 4.1% Zn over 3 metres interpreted to be the extension of the Curlew Vein from the Blackhawk Mine

Silver Dollar Resources Inc. (CSE: SLV) (OTCQX: SLVDF) (FSE: 4YW) ("Silver Dollar" or the "Company") is pleased to report geologic modeling results correlating to the recently reported near-surface drilling discoveries at the Ranger-Page Project located in northern Idaho's prolific Coeur d'Alene Mining District.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Futuristic 3D holographic visualization of resource and geophysical data analysis.

From Data to Discovery: How AI is Changing the Face of Modern Mining

Mineral exploration is one of the riskiest and most capital-intensive phases of the mining lifecycle. The process has traditionally relied heavily on historical geological records, field surveys and extensive drilling, often with low success rates and long time horizons. But a new wave of digital innovation is reshaping the landscape.

Artificial intelligence (AI) and advanced data analytics are increasingly at the forefront of a quiet revolution in mining, offering tools that enhance discovery potential, reduce exploration risk and deliver stronger returns for investors.

Historically, mineral exploration has been marked by high uncertainty and significant financial risk. Companies spend millions of dollars poring over old geological maps, conducting labor-intensive fieldwork and drilling test holes — all in hopes of finding an economically viable deposit. In fact, industry data suggests that only a tiny fraction of exploration projects — approximately one in a thousand — ever reaches production. This low success rate has often made early-stage mining investments difficult to assess and even harder to justify without deep technical insights or a strong appetite for risk.

Keep reading...Show less

Latest Press Releases

Related News

×