Galena Mining

Activities and Cashflow Report For Quarter Ended 31 December 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 31 December 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


HIGHLIGHTS:

  • Abra Project construction completed on time in December 2022. Project construction expenditure within 1% of budget.
  • Ore commissioning commenced and first concentrate produced in January 2023.
  • Focus now on completing plant commissioning and ramping up production.
  • Underground development achieved a record 1,122m advance during the Quarter with the decline reaching 1,268mRL. (282m vertical below the surface and 45m below top of the orebody).
  • Cash balance at Quarter-end A$41.0M.
ABRA BASE METALS MINE (60%-OWNED)
 

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted, and construction of the processing plant and surface infrastructure was completed in December 2022. First production of its lead-silver concentrate occurred in January 2023 with first product shipment scheduled for the March 2023 quarter.

Project construction / development

Abra Project construction works were completed by the end of the Quarter and ore commissioning commenced with first ore feed into the plant and first concentrate produced as part of the plant commissioning process in early January 2023 (see Galena ASX announcements of 10 January 2023 and 13 January 2023). Abra construction completed within 1% of forecast construction costs.

Operational Readiness

By the end of the quarter 90% of the operational staff have been employed along with both internal and external maintenance service providers. All site critical spares have been identified and procured. Site reagents and other consumables have been established.

Underground power, ventilation, and the installation of the second egress (ladderways) have enabled multiple ore headings to be operational and the primary pumping station will be completed in the March quarter.

The site assay laboratory was nearing completion by the end of the quarter and final commissioning in January is expected to significantly improve assay turn around and controls.

Applications are being lodged for regulatory approvals, licences or permits as they are required for completion of construction, commissioning and commencement of operations.

Underground mining – During the Quarter, 1,122 metres of development was completed and at Quarter-end total development reached 3,592 metres consisting of 1,978 metres of decline development and 1,614 metres of lateral development. The decline reached 1,268mRL, 45 metres below the top of the Abra orebody and 282 metres vertically below the surface.

During December, several ore drives commenced on the 1,280 and 1,300mRL levels which will deliver the required ore for plant commissioning in January 2023. At the end of the Quarter, a total of 26,000t of ore had been stockpiled on the ROM pad in preparation for ore processing commissioning and the commencement of concentrate production.

During the quarter a total of 75 (10,777m) underground diamond holes were completed for grade control and mine planning purposes. Mine planning and scheduling work was completed with this information in preparation for the production activities in 2023.

On 24 December 2022, the primary ventilation fan motor failed, and alternative ventilation fans were installed to resume underground work. Five days of mining activities were lost during this time and this delay is not expected to delay the plant processing commissioning during January 2023.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
The Conversation (0)
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Completion of Silver Acquisition & Appointment of New Managing Director

Completion of Silver Acquisition & Appointment of New Managing Director

Rapid Critical Metals Limited (‘Rapid,’ ‘RCM’ or ‘Company’) is pleased to advise that the Company has today completed the acquisition of Silver Metal Group Limited’s two wholly-owned subsidiaries, Conrad Resources Pty Ltd and Webbs Resources Pty Ltd (Transaction), the terms of which are contained in the Company’s announcement to ASX of 22 May, 2025. The Transaction was approved by shareholders at the Extraordinary General Meeting (EGM) held on 7 July, 2025.

Keep reading...Show less
Silver bars, stock market data and graph with "Weekly Editor's Picks" banner.

Editor's Picks: Silver Price Breaks US$39 Again, Rare Earths Stock Soars

The gold price saw both peaks and troughs this week, reacting to the release of June consumer and producer price index data out of the US, as well as renewed discussions about whether President Donald Trump may fire Federal Reserve Chair Jerome Powell.

Silver was the real precious metals star, pushing past the US$39 per ounce level once again.

Keep reading...Show less
Closeup of US silver coins with eagle and stars design on a black background.

Silver Price Update: Q2 2025 in Review

Silver took some luster from gold in Q2 as its price climbed to 14 year highs.

Many of the same contributors that affected the gold price were also in play for silver.

Uncertainty in financial markets, driven by a chaotic US trade and tariff policy, coincided with rising tensions in the Middle East and continued fighting between Russia and Ukraine, prompting investors to seek safe-haven assets.

Keep reading...Show less
Ted Butler, silver bars.

Ted Butler: Silver's Moment is Here, Time for Price to Outperform

Has silver's moment finally arrived?

Precious metals analyst Ted Butler believes the answer is "yes."

Keep reading...Show less
Mani Alkhafaji, silver bars.

Silver Price at New Base, What Comes Next? First Majestic's Mani Alkhafaji

Mani Alkhafaji, vice president of corporate of development and investor relations at First Majestic Silver (TSX:AG,NYSE:AG) discusses silver's recent price rise.

He notes that the gold-silver mining ratio is at seven to one, while the price ratio is at 90 to one.

Keep reading...Show less
Silver bar surrounded by shiny silver nuggets on a black background.

Top 5 Canadian Silver Stocks of 2025

Silver prices surged during the second quarter of 2025, surpassing the US$37 per ounce mark and reaching their highest levels in 14 years.

The price movements stem from a tightening supply and demand situation, which has seen above-ground inventories squeezed due to an increasing need from industrial sectors, particularly the growing photovoltaics industry.

However, demand has also increased due to heightened investor interest in alternative safe-haven assets, as gold prices reached record highs. The shifting sentiment comes amid uncertainty over a US trade policy that could reduce the world's gross domestic product by 1 percent.

Keep reading...Show less

Latest Press Releases

Related News

×