Galena Mining

Activities and Cashflow Report For Quarter Ended 31 December 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 31 December 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


HIGHLIGHTS:

  • Abra Project construction completed on time in December 2022. Project construction expenditure within 1% of budget.
  • Ore commissioning commenced and first concentrate produced in January 2023.
  • Focus now on completing plant commissioning and ramping up production.
  • Underground development achieved a record 1,122m advance during the Quarter with the decline reaching 1,268mRL. (282m vertical below the surface and 45m below top of the orebody).
  • Cash balance at Quarter-end A$41.0M.
ABRA BASE METALS MINE (60%-OWNED)

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted, and construction of the processing plant and surface infrastructure was completed in December 2022. First production of its lead-silver concentrate occurred in January 2023 with first product shipment scheduled for the March 2023 quarter.

Project construction / development

Abra Project construction works were completed by the end of the Quarter and ore commissioning commenced with first ore feed into the plant and first concentrate produced as part of the plant commissioning process in early January 2023 (see Galena ASX announcements of 10 January 2023 and 13 January 2023). Abra construction completed within 1% of forecast construction costs.

Operational Readiness

By the end of the quarter 90% of the operational staff have been employed along with both internal and external maintenance service providers. All site critical spares have been identified and procured. Site reagents and other consumables have been established.

Underground power, ventilation, and the installation of the second egress (ladderways) have enabled multiple ore headings to be operational and the primary pumping station will be completed in the March quarter.

The site assay laboratory was nearing completion by the end of the quarter and final commissioning in January is expected to significantly improve assay turn around and controls.

Applications are being lodged for regulatory approvals, licences or permits as they are required for completion of construction, commissioning and commencement of operations.

Underground mining – During the Quarter, 1,122 metres of development was completed and at Quarter-end total development reached 3,592 metres consisting of 1,978 metres of decline development and 1,614 metres of lateral development. The decline reached 1,268mRL, 45 metres below the top of the Abra orebody and 282 metres vertically below the surface.

During December, several ore drives commenced on the 1,280 and 1,300mRL levels which will deliver the required ore for plant commissioning in January 2023. At the end of the Quarter, a total of 26,000t of ore had been stockpiled on the ROM pad in preparation for ore processing commissioning and the commencement of concentrate production.

During the quarter a total of 75 (10,777m) underground diamond holes were completed for grade control and mine planning purposes. Mine planning and scheduling work was completed with this information in preparation for the production activities in 2023.

On 24 December 2022, the primary ventilation fan motor failed, and alternative ventilation fans were installed to resume underground work. Five days of mining activities were lost during this time and this delay is not expected to delay the plant processing commissioning during January 2023.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Ore-processing equipment.

Junior Silver Exploration: Risks and Opportunities for Investors

In the dynamic world of resource investing, silver-focused junior mining and exploration companies present a unique opportunity for investors seeking exposure to both precious and industrial metals. As global demand for silver continues to surge, particularly in green technologies, these agile explorers are poised to play a crucial role in meeting future supply needs.

Silver's dual nature, as both a precious metal and an industrial commodity, places it at the forefront of technological innovation and economic growth. Its unparalleled electrical conductivity, thermal properties and light-sensitive characteristics make it indispensable in a variety of applications, from solar panels to electric vehicles (EVs).

The growing demand for clean energy solutions has significantly boosted silver's industrial usage. Solar panel manufacturing, in particular, has become a major consumer of silver, with each panel requiring a substantial amount of the metal. Similarly, the EV revolution relies heavily on silver for various components, including battery management systems and charging infrastructure.

Keep reading...Show less

First Majestic Announces Shareholder Approval in Connection with Gatos Silver Acquisition

First Majestic Silver Corp. (NYSE: AG) (TSX: AG) (FSE: FMV) (the "Company" or "First Majestic") is pleased to announce that, in connection with the Company's acquisition of Gatos Silver, Inc. (NYSE: GATO) (TSX: GATO) ("Gatos Silver"), the Company's shareholders have approved the issuance of up to 190,000,000 First Majestic common shares ("First Majestic Shares") to holders of shares of common stock of Gatos Silver ("Gatos Silver Shares") in exchange for the acquisition by the Company of all of the outstanding shares of Gatos Silver (the "Transaction"). Approximately 98.44% of the votes cast at the special meeting of the Company's shareholders that was held today were voted in favour of the resolution approving the issuance of up to 190,000,000 First Majestic Shares.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Silver Crown Royalties

Silver Crown Royalties


Keep reading...Show less

SilverCrest Announces Mailing and Filing of Meeting Materials for Special Meeting of Securityholders to Approve Proposed Plan of Arrangement with Coeur Mining

The Board of Directors of SilverCrest unanimously recommends that Securityholders vote FOR   the Arrangement Resolution.

Securityholders are encouraged to vote in advance of the proxy cutoff of   10:00 a.m. ( Vancouver time) on February 4, 2025 .

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

SilverCrest Announces Mailing and Filing of Meeting Materials for Special Meeting of Securityholders to Approve Proposed Plan of Arrangement with Coeur Mining

The Board of Directors of SilverCrest unanimously recommends that Securityholders vote FOR   the Arrangement Resolution.

Securityholders are encouraged to vote in advance of the proxy cutoff of   10:00 a.m. ( Vancouver time) on February 4, 2025 .

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Silver nuggets.

Endeavour Silver Hits Updated 2024 Production Guidance After Disruption at Guanaceví Mine

Endeavour Silver (TSX:EDR,NYSE:EXK) shared its 2024 production results, reporting output for the period of 4,471,824 ounces of silver and 39,047 ounces of gold, or 7.6 million silver equivalent ounces.

The company met its updated annual production guidance, which it adjusted following operational challenges.

"After operating at reduced capacity due to the Guanaceví trunnion failure in August, and subsequently resuming full capacity in December, we are satisfied with our production performance in Q4 and producing at the top range of our updated production guidance," CEO Dan Dickson said in Thursday's (January 9) press release.

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×