Galena Mining

Activities and Cashflow Report For Quarter Ended 31 December 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 31 December 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.


HIGHLIGHTS:

  • Abra Project construction completed on time in December 2022. Project construction expenditure within 1% of budget.
  • Ore commissioning commenced and first concentrate produced in January 2023.
  • Focus now on completing plant commissioning and ramping up production.
  • Underground development achieved a record 1,122m advance during the Quarter with the decline reaching 1,268mRL. (282m vertical below the surface and 45m below top of the orebody).
  • Cash balance at Quarter-end A$41.0M.
ABRA BASE METALS MINE (60%-OWNED)

Abra comprises a granted Mining Lease, M52/0776 and surrounding Exploration Licence E52/1455, together with several co-located General Purpose and Miscellaneous Leases. The Project is 100% owned by Abra Mining Pty Limited (“AMPL” the Abra Project joint-venture entity), which in turn is 60% owned by Galena, with the remainder owned by Toho Zinc Co., Ltd. (“Toho”) of Japan.

Abra is fully permitted, and construction of the processing plant and surface infrastructure was completed in December 2022. First production of its lead-silver concentrate occurred in January 2023 with first product shipment scheduled for the March 2023 quarter.

Project construction / development

Abra Project construction works were completed by the end of the Quarter and ore commissioning commenced with first ore feed into the plant and first concentrate produced as part of the plant commissioning process in early January 2023 (see Galena ASX announcements of 10 January 2023 and 13 January 2023). Abra construction completed within 1% of forecast construction costs.

Operational Readiness

By the end of the quarter 90% of the operational staff have been employed along with both internal and external maintenance service providers. All site critical spares have been identified and procured. Site reagents and other consumables have been established.

Underground power, ventilation, and the installation of the second egress (ladderways) have enabled multiple ore headings to be operational and the primary pumping station will be completed in the March quarter.

The site assay laboratory was nearing completion by the end of the quarter and final commissioning in January is expected to significantly improve assay turn around and controls.

Applications are being lodged for regulatory approvals, licences or permits as they are required for completion of construction, commissioning and commencement of operations.

Underground mining – During the Quarter, 1,122 metres of development was completed and at Quarter-end total development reached 3,592 metres consisting of 1,978 metres of decline development and 1,614 metres of lateral development. The decline reached 1,268mRL, 45 metres below the top of the Abra orebody and 282 metres vertically below the surface.

During December, several ore drives commenced on the 1,280 and 1,300mRL levels which will deliver the required ore for plant commissioning in January 2023. At the end of the Quarter, a total of 26,000t of ore had been stockpiled on the ROM pad in preparation for ore processing commissioning and the commencement of concentrate production.

During the quarter a total of 75 (10,777m) underground diamond holes were completed for grade control and mine planning purposes. Mine planning and scheduling work was completed with this information in preparation for the production activities in 2023.

On 24 December 2022, the primary ventilation fan motor failed, and alternative ventilation fans were installed to resume underground work. Five days of mining activities were lost during this time and this delay is not expected to delay the plant processing commissioning during January 2023.


Click here for the full ASX Release

This article includes content from Galena Mining, licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.


G1A:AU
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Galena Mining (ASX:G1A)

Galena Mining


Keep reading...Show less
Galena Mining

Abra Construction At 97% Complete – First Ore Stockpiled For January Processing

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 97% complete as of 30 November 2022. Processing plant commissioning is progressing quickly with practical completion now expected in December 2022. Ore currently being mined from underground is being stockpiled in readiness for processing to begin in January 2023. Concentrate production will commence January 2023.

Keep reading...Show less
Galena Mining

Abra Construction At 92% Complete – Reaches First Ore Underground

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 92% complete as of 31 October 2022. Underground mine has reached the first ore (see ASX announcement 14 November 2022) and plant commissioning continues in several key areas with the project focussed on achieving first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Abra Mine Reaches Ore

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the underground development at its Abra Base Metals Mine (“Abra” or the “Project”) has reached the Abra orebody. Commissioning has commenced in several key areas of the processing facility and the Power Station (Pacific Energy) completed full integration of the hybrid gas/solar/battery energy storage system (BESS) power station on 10 November. The project remains on track for first concentrate production in Q1 2023.
Keep reading...Show less
Galena Mining

Galena Mining Activities Report For Quarter Ended 30 September 2022

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) reports on its activities for the quarter ended 30 September 2022 (the “Quarter”), primarily focused on construction of its 60%- owned Abra Base Metals Mine (“Abra” or the “Project”) located in the Gascoyne region of Western Australia.

Keep reading...Show less
Boab Metals

Sorby Hills Project FEED Study

Boab Metals Limited (ASX: BML) (“Boab” or the “Company”) is pleased to announce the results of its Front-End Engineering & Design (“FEED”) Study for its 75% owned Sorby Hills Lead-Silver- Zinc Project (“Sorby Hills” or “the Project”), located in the Kimberley Region of Western Australia. The FEED Study augments and enhances the Sorby Hills Definitive Feasibility Study (“DFS”) released by the Company in January 2023.

Keep reading...Show less
Hands shaking with Paladin Energy and Fission Uranium logos.

Top Stories This Week: Expert Calls for US$50 Silver, Paladin Offers C$1.14 Billion for Fission

Strength in the US dollar briefly pushed the gold price below US$2,300 per ounce midway through the week, but the yellow metal soon bounced back, finishing Friday (June 28) at the US$2,325 level.

The latest US Personal Consumption Expenditures (PCE) price index data came out that day, and it shows that in May core PCE was up 0.1 percent month-on-month and 2.6 percent year-on-year — in line with expectations.

PCE is the US Federal Reserve's preferred measure of inflation, and can help shed light on its interest rate plans.

Keep reading...Show less
Eastern Metals

Thomson Project Sold for $200,000 Plus 1.5% Net Smelter Royalty

Divestment of non-core asset will streamline Eastern Metals’ asset portfolio, enabling it to focus on exploration of its high-potential Cobar and Arunta projects

Eastern Metals Ltd (ASX: EMS) (“Eastern Metals” or “the Company”) is pleased to announce that it has signed a binding Heads of Agreement (“HoA”) for the sale of the Thomson Project in New South Wales to Legacy Minerals Holdings Ltd (ASX: LGM, “Legacy Minerals”) for $200,000 in cash and a 1.5% Net Smelter Royalty (“NSR”).

Keep reading...Show less
Eastern Metals

Investor Presentation Gold Coast Investment Showcase

Eastern Metals Ltd (ASX:EMS) (“Eastern Metals” or “the Company”) is pleased to advise that its Chief Executive Officer, Ley Kingdom, will be presenting at Vertical Events’ Gold Coast Investment Showcase on Thursday 20 June 2024 at 11:30am AEST.

Keep reading...Show less

MAG Reports AGSM Results

MAG Silver Corp. (TSX NYSE American: MAG) ("MAG" or "MAG Silver") reports that at its Annual General and Special Meeting (the " AGSM ") held on June 17, 2024, MAG's shareholders (the " Shareholders ") approved by majority: to elect all eight directors standing for election, to re-appoint Deloitte LLP as auditors of the Company, and to support the Company's approach to executive compensation.

Detailed results of the total shares voted at the AGSM are set out below.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

Pan American Silver Provides Mid-Year Exploration Update

Pan American Silver Corp. (NYSE: PAAS) (TSX: PAAS) ("Pan American" or the "Company") releases new drill results for its Jacobina, El Peñon, La Colorada and Huaron properties, reflecting the potential for continued mineral resource replacement at these assets. In particular, drill results from La Colorada and El Peñon reveal the significant exploration potential to find additional mineralized structures in under-explored ground surrounding these operations, highlighting the potential for mineral resource growth close to existing mine infrastructure.

"At La Colorada, we discovered an entirely new set of vein structures with high silver grades to the east and southeast of the main NC2 vein. At El Peñon, drill results from the Pampa Sur zone bode well for potential mineral resource additions close to the existing mine infrastructure, with additional potential in the largely unexplored southern area of the mine," said Christopher Emerson, Pan American's Vice President of Exploration and Geology.

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
Galena Mining

Galena Mining Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×