CENTURY LITHIUM FILES TECHNICAL REPORT ON THE FEASIBILITY STUDY OF THE CLAYTON VALLEY LITHIUM PROJECT, NEVADA

CENTURY LITHIUM FILES TECHNICAL REPORT ON THE FEASIBILITY STUDY OF THE CLAYTON VALLEY LITHIUM PROJECT, NEVADA

Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (Century Lithium or the Company) is pleased to announce the filing of the report " NI 43-101 Technical Report on the Feasibility Study of the Clayton Valley Lithium Project, Esmeralda County, Nevada USA", with effective date April 29 2024 (Feasibility Study or Report), to support the disclosure in the Company's news release dated April 29, 2024 (see news release ). The Report was prepared in accordance with National Instrument 43-101 (NI 43-101) by Wood Canada Limited (Wood), Global Resource Engineering, Ltd. (GRE) and WSP USA Environment and Infrastructure, Inc. (WSP). All currency amounts in this news release are presented in US dollars.

Century Lithium Files Technical Report on the Feasibility Study for the Clayton Valley Lithium Project, Nevada (CNW Group/Century Lithium Corp.)

"Century Lithium is pleased to file the report on the Feasibility Study of our Clayton Valley Lithium Project," said Bill Willoughby , President, and CEO. "The Report is the culmination of the dedicated work of our team of employees and consultants and highlights the economic benefits of the Project made possible by Century's unique use of chlor-alkali and direct lithium extraction processing. The filing of the report now marks another major milestone for the Company."

During the preparation of the Report, minor changes were made to the parameters used to determine the Mineral Resource and Reserve Estimates. The resulting economic analysis is effectively unchanged. Using a base case price of $24,000 /tonne of lithium carbonate, the Project after-tax cash flow has a 17.2% Internal Rate of Return (IRR) and a $3.16 billion Net Present Value (NPV) at an 8% discount rate.

RESOURCE AND RESERVES

The Mineral Resource and Reserve Estimates for the Project were updated for the Report and built using geologic data and 1,318 lithium assays from 45 core holes drilled between 2017 and 2022 and have an effective date of April 29, 2024 . The constrained Measured and Indicated Resource Estimate is 1,138.59 million tonnes (Mt) with an average grade of 966 parts per million (ppm) lithium and contains 1.099 Mt of lithium or 5. 852 Mt of lithium carbonate equivalent (LCE). The Proven and Probable Mineral Reserve Estimate was derived from the constrained Mineral Resources and contains 287.65 Mt with an average grade of 1,149 ppm lithium and contains 0. 330 Mt of lithium or 1. 759 Mt of LCE.

Mineral Resource Estimate

Domain

Tonnes Above
Cut-off (millions)

Li Grade (ppm)

Li Contained

(million t)

LCE (million t)

Measured

858.26

990

0.850

4.523

Indicated

280.33

891

0.250

1.329

Measured & Indicated

1,138.59

966

1.099

5.582

Inferred

187.28

820

0.154

0.817

1.The effective date of the Mineral Resource Estimate is April 29, 2024. The QP for the estimate is Ms. Terre Lane, MMSA, an employee of GRE and independent of Century.

2.The Mineral Resources are constrained by a pit shell with a 200 ppm Li cut-off and density of 1.505 g/cm3. The cut-off grade considers an operating cost of$20/t mill feed, process recovery of 78% and a long-term lithium carbonate price of $24,000/t.

3.The Mineral Resource estimate was prepared in accordance with 2014 CIM Definition Standards and the 2019 CIM Best Practice Guidelines.

4.Mineral Resource figures have been rounded.

5.One tonne of lithium = 5.323 tonnes lithium carbonate.

6.Mineral Resources are inclusive of Mineral Reserves.

Mineral Reserve Estimate

Domain

Tonnes Above Cut-
off (millions)

Li Grade (ppm)

Li Contained

(million t)

LCE (million t)

Proven

266.39

1,147

0.306

1.626

Probable

21.26

1,174

0.025

0.133

Proven & Probable

287.65

1,149

0.330

1.759

1.The effective date of the Mineral Reserve Estimate is April 29, 2024. The QP for the estimate is Ms. Terre Lane, MMSA, an employee of GRE and independent of Century.

2.The Mineral Reserve estimate was prepared in accordance with 2014 CIM Definition Standards and 2019 CIM Best Practice Guidelines.

3.Mineral Reserves are reported within the final pit design at a mining cut-off of 900 ppm. The mine operating cost is $5.44/t milled, processing cost of $40.9/t milled, G&A cost of $2.68/t milled and a credit for the NaOH sales of $28.95/t milled. The NaOH sales credit is proportionally applied to all the operating costs to get appropriate costs for the cut-off grade calculation. The cut-off grade considers a mine operating cost of $2.22/t, a process operating cost of $16.69/t milled, a G&A cost of $1.09/t milled, process recovery of 78% and a long-term lithium carbonate price of $24,000/t.

4.The cut-off of 900 ppm is an elevated cut-off selected for the mine production schedule as the elevated cut-off is 4.5 times higher than the break-even cut-off grade.

5. Mineral Reserve figures have been rounded.

6.One tonne of lithium=5.323 tonnes lithium carbonate

PROJECT SUMMARY

Century's Project centers on the mining and processing of a large, flat-lying lithium claystone deposit. Mineral Reserves are sufficient to support a mine life of approximately 40 years.

Mining is by mechanized surface excavation of claystone at production rates of 7,500 to 22,500 tonnes/day of mill feed, and 13,000 to 39,000 tonnes/year of lithium carbonate. Lithium recovery is through Century's patent-pending process that combines chloride leaching with direct lithium extraction to produce a marketable battery-quality product at the Project site.

The Report is available on SEDAR+ and on the Company's website.

QUALIFIED PERSON

Terre Lane , RM SME, MMSA, Principal Mining Engineer, GRE, is an independent qualified person as defined by National Instrument 43-101 and has approved the technical information in this release.

ABOUT Century Lithium CORP.

Century Lithium Corp. is an advanced stage lithium company, focused on developing its 100%-owned Clayton Valley Lithium Project in west-central Nevada, USA . Century Lithium recently completed a Feasibility Study on its Clayton Valley Lithium Project and is currently in the permitting stage, with the goal of becoming a domestic producer of lithium for the growing electric vehicle and battery storage market.

ON BEHALF OF Century Lithium CORP.
WILLIAM WILLOUGHBY , PhD., PE
President & Chief Executive Officer

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.

Cautionary Note Regarding Forward-Looking Statements

This release contains certain forward-looking statements within the meaning of applicable Canadian securities legislation. In certain cases, forward-looking statements can be identified by the use of words such as "plans", "expects" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved" and similar expressions suggesting future outcomes or statements regarding an outlook.

Forward-looking statements relate to any matters that are not historical facts and statements of our beliefs, intentions and expectations about developments, results and events which will or may occur in the future, without limitation, statements with respect to the potential development and value of the Project and benefits associated therewith, statements with respect to the expected project economics for the Project, such as estimates of life of mine, lithium prices, production and recoveries, capital and operating costs, IRR, NPV and cash flows, any projections outlined in the Feasibility Study in respect of the Project, the permitting status of the Project and the Company's future development plans.

These and other forward-looking statements and information are subject to various known and unknown risks and uncertainties, many of which are beyond the ability of the Company to control or predict, that may cause their actual results, performance or achievements to be materially different from those expressed or implied thereby, and are developed based on assumptions about such risks, uncertainties and other factors set out herein. These risks include those described under the heading "Risk Factors" in the Company's most recent annual information form and its other public filings, copies of which can be under the Company's profile at www.sedarplus.com . The Company expressly disclaims any obligation to update-forward-looking information except as required by applicable law. No forward-looking statement can be guaranteed, and actual future results may vary materially. Accordingly, readers are advised not to place reliance on forward-looking statements or information. Furthermore, Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/century-lithium-files-technical-report-on-the-feasibility-study-of-the-clayton-valley-lithium-project-nevada-302171797.html

SOURCE Century Lithium Corp.

News Provided by PR Newswire via QuoteMedia

LCE:CA
Century Lithium

Century Lithium Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Century Lithium (TSXV:LCE)

Century Lithium


Keep reading...Show less
CENTURY LITHIUM ANNOUNCES POSITIVE FEASIBILITY STUDY FOR THE CLAYTON VALLEY LITHIUM PROJECT, NEVADA

CENTURY LITHIUM ANNOUNCES POSITIVE FEASIBILITY STUDY FOR THE CLAYTON VALLEY LITHIUM PROJECT, NEVADA

FEASIBILITY STUDY HIGHLIGHTS

  • Large-Scale Nevada-based Lithium Project: three-phase production plan will generate a life-of-mine average of 34,000 tonnes per annum (tpa) of battery-quality lithium carbonate (Li 2 CO 3 )

  • Innovative Approach in Processing: patent-pending chloride leaching process combined with Direct Lithium Extraction (DLE), the Feasibility Study is supported by 2+ years of testing at the Company's Pilot Plant

  • Mineral Resource Estimate: Measured and Indicated resources totaling 1,207.33 million tonnes (Mt) at an average grade of 957 parts per million (ppm) lithium (Li) containing 1. 155 Mt of Li or 6. 148 Mt of lithium carbonate equivalent (LCE)

  • Long 40-Year Mine Life : Proven and Probable Mineral Reserve Estimate totaling 287.65 Mt at an average grade of 1,149 ppm Li containing 0. 330 Mt of lithium or 1. 759 Mt of LCE

  • Initial Project: Phase 1 Capital Cost $1.537 billion for production capacity of 13,000 tpa LCE

  • Designed for Expansion: Phase 2 $0.651 billion for 28,000 tpa LCE, and Phase 3 $1.336 billion for 41,000 tpa LCE; Project expansions are capitalized with Project cash flow

  • Low Operating Cost: average operating cost $8,223 /t of Li 2 CO 3 produced, or $2,766 /t after sales of surplus sodium hydroxide (NaOH)

  • After-tax IRR of 17.1% at $24,000 /t Li 2 CO 3 : $3.01 billion after-tax net present value (NPV) at 8% discount rate and a 17.1% after-tax internal rate of return (IRR), using price assumptions of $24,000 /t for Li 2 CO 3 and $600 /dry metric tonne (dmt) for NaOH

Century Lithium Corp. (TSXV : LCE ) (OTCQX: CYDVF ) (Frankfurt: C1Z ) (Century Lithium or the Company) is pleased to announce the results of a National Instrument 43-101 (NI 43-101) feasibility study (Feasibility Study, FS or Study) completed on its 100% owned Clayton Valley Lithium Project (Project) in Nevada, USA . The Feasibility Study was prepared by Wood Group USA Inc. (Wood) and Global Resource Engineering, Ltd. (GRE). All currency amounts in this news release are presented in U.S. dollars.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
CENTURY LITHIUM PROVIDES UPDATE ON THE FEASIBILITY STUDY

CENTURY LITHIUM PROVIDES UPDATE ON THE FEASIBILITY STUDY

Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (Century Lithium or Company) reports that the Feasibility Study on the Company's Clayton Valley Lithium Project (Project), in Nevada, USA under the direction of Wood PLC and Global Resource Engineering Ltd., is currently under review by the Qualified Persons, and the Company anticipates its announcement imminently.

Century Lithium Provides Update on the Feasibility Study (CNW Group/Century Lithium Corp.)

To date, the Company's Feasibility Study team has revised and updated estimates for a phased production approach at the Project. These revisions also included assessment and evaluation of the economic benefit of sales of the surplus sodium hydroxide produced by the chlor-alkali plant.

The Company's Lithium Extraction Facility (Pilot Plant) in Amargosa Valley, Nevada is now in its third year of testing the processing of lithium-bearing claystone from the Project. All data collected has been essential to the Feasibility Study. Century Lithium continues to work toward permitting the Project including the collection of baseline data collection for biology, surface and groundwater hydrology, and social impacts. Earlier this year, baseline reports were submitted by the Company's consultants and were accepted by the appropriate government agencies. Multiple reports have been completed which will aide in the preparation of a Plan of Operations to initiate the National Environmental Policy Act (NEPA) process.

About Century Lithium Corp.

Century Lithium Corp. (formerly Cypress Development Corp.) is an advanced stage lithium company, focused on developing its 100%-owned Clayton Valley Lithium Project in west-central Nevada, USA . Century Lithium is currently in the pilot stage of testing on material from its lithium-bearing claystone deposit at its Lithium Extraction Facility in Amargosa Valley, Nevada and progressing towards completing a Feasibility Study and permitting, with the goal of becoming a domestic producer of lithium for the growing electric vehicle and battery storage market.

ON BEHALF OF Century Lithium CORP.
WILLIAM WILLOUGHBY , PhD., PE
President & Chief Executive Officer

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.

Cautionary Note Regarding Forward-Looking Statements

This release includes certain statements that may be deemed to be "forward-looking statements". Forward-looking statements are subject to risks, uncertainties and assumptions and are identified by words such as " expects," "estimates," "projects," "anticipates," "believes," "could," "scheduled," and other similar words. All statements in this release, other than statements of historical facts, that address events or developments that management of the Company expects, are forward-looking statements. Although management believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance, and actual results or developments may differ materially from those in the forward-looking statements. The Company undertakes no obligation to update these forward-looking statements if management's beliefs, estimates or opinions, or other factors, should change. Factors that could cause actual results to differ materially from those in forward-looking statements, include market prices, exploration, and development successes, continued availability of capital and financing, and general economic, market or business conditions. Please see the public filings of the Company at www.sedar.com for further information.

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/century-lithium-provides-update-on-the-feasibility-study-302121633.html

SOURCE Century Lithium Corp.

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/April2024/19/c7578.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Century Lithium Corp. to Present at the Metals and Mining Virtual Investor Conference October 3rd

Century Lithium Corp. to Present at the Metals and Mining Virtual Investor Conference October 3rd

Century Lithium Corp (TSX:V: LCE; OTCQX: CYDVF), based in Vancouver, focused on developing its 100%-owned Clayton Valley Lithium Project in Nevada, USA., today announced that William Willoughby, President & CEO, will present live at the Metals and Mining Virtual Investor Conference, hosted by VirtualInvestorConferences.com, on October 3 rd 2023.

DATE : October 3 rd , 2023
TIME: 2:00 PM ET
LINK: https://bit.ly/44FOnTd
Available for 1x1 meetings: October 3

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
CENTURY LITHIUM OBTAINS PROVISIONAL PATENT

CENTURY LITHIUM OBTAINS PROVISIONAL PATENT

Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (Century Lithium or the Company) is pleased to report it has obtained a provisional patent with the U.S. Patent and Trademark Office, U.S. Department of Commerce. The provisional patent is titled System and Method for Extracting Lithium from Clay and Other Materials in a Chloride Solution Using Individualized Pretreatments . The patent pending process encompasses the Company's flowsheet, as developed at its Lithium Extraction Facility ("Pilot Plant") in Amargosa Valley, Nevada USA and protects the Company's intellectual property (IP) pertaining to the handling of solutions derived from the treatment of solid materials including clays from the Company's Clayton Valley Lithium Project (Project) in Nevada .

News Provided by PR Newswire via QuoteMedia

Keep reading...Show less
Century Lithium Reports on Testing with Saltworks and Production of Battery Grade Lithium Carbonate

Century Lithium Reports on Testing with Saltworks and Production of Battery Grade Lithium Carbonate

Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (Century Lithium or the Company) is pleased to report testing results at Saltworks Technologies, Inc. (Saltworks) in Richmond Canada and additional production of high-purity lithium carbonate (Li 2 CO 3 ) using product solutions from the Company's Lithium Extraction Facility (Pilot Plant) in Amargosa Valley, Nevada USA. The solutions tested at Saltworks were derived from leaching of claystone from the Company's 100%-owned Clayton Valley Lithium Project (Project) in Nevada ; and processed at the Pilot Plant via direct lithium extraction (DLE) to produce an intermediate concentrated lithium solution (DLE eluent).

Century Lithium Reports on Testing with Saltworks & Production of Battery Grade Lithium Carbonate (CNW Group/Century Lithium Corp.)

"It is very positive to see consistency in our high-purity, 99.87%, lithium carbonate product grades from our Pilot Plant this year" stated Bill Willoughby , President, and CEO of Century Lithium. "The highlight though, is the almost five-fold increase in lithium grade in the concentrated lithium solution generated at the Pilot Plant. This was achieved through collaboration with Koch Technology Solutions and their Li-Pro TM system, and its integration into Century Lithium's chloride-based leaching process."

Highlights
  • Repeated production of high-purity (99.87%) battery-grade lithium carbonate
  • Improved lithium concentrations in DLE eluent
  • Reduced volume of solution in downstream treatment and recycling
  • Potential to eliminate evaporation from the post DLE process flowsheet
  • Active testing underway to further improve DLE eluent grade
Lithium Carbonate Assay Results

Saltworks has once again produced battery-grade lithium carbonate (Li 2 CO 3 ) from the DLE eluent produced at the Pilot Plant. The table below is a comparison of Saltworks' 2023 results for Li 2 CO 3 , DLE eluent Batch 2, with the previously reported results from DLE eluent Batch 1 (see May 25 , 2023 news release ). Also shown are the constituent levels for battery grade Li 2 CO 3, as published by two major producers. The assays results were finalized by Saltworks and independently assayed by SGS Canada, Inc. These results show consistency in composition of both the DLE eluent produced by the Pilot Plant earlier in the year and the resulting Li 2 CO 3 product produced by Saltworks, achieving 99.871% content versus 99.875% reported previously.

Li 2 CO 3 Assay Results


Century Li 2 CO 3

Batch 2 (August 2023)

Century Li 2 CO 3

Batch 1 (May 2023)

Reference Grades

Li 2 CO 3

wt%

99.871

99.875

>99.5

H 2 O

wt%

0.05

0.03

0.2 to

Na

wt%

0.027

0.047

0.03 to

Ca

wt%

0.012

0.009

0.01 to

Fe

Wppm

3

3

Al

Wppm

3

Cu

Wppm

3

Ni

Wppm

Zn

Wppm

13

Cl

wt%

0.01

0.008

Notes: wt% (weight percent), wppm (weight parts per million), calculated Li 2 CO 3 purity based on sum of impurities measured
above detection limit. Reference grades are from published specifications from two major producers of battery grade Li 2 CO 3

Lithium in DLE Eluent

As recently reported (see August 9, 2023 news release ), Century Lithium collaborated with Koch Technology Solutions (KTS), a Koch Engineered Solutions' (KES) company, and integrated KTS' Li-Pro TM system into the DLE stage of the Pilot Plant. This work has increased the grades of the DLE eluent (intermediate lithium product solution) several fold. These changes are outlined in the table below, as reported by analyses from Saltworks.

DLE Eluate Assay Results





Batch

1

2

3

4

5

Lithium (Li) (ppm)

1,430

1,610

1,885

3,970

6,780

Sodium (Na) (ppm)

22,400

25,850

24,150

19,100

8,220

Total dissolved solids (TDS) (ppm)

77,450

77,850

82,600

78,300

79,300

Li:TDS

0.018

0.021

0.023

0.051

0.085

Li:Na

0.064

0.062

0.078

0.208

0.825

Notes: DLE eluent for Batch 1 and 2 used to produce Li 2 CO 3 cited above.

Batches 1, 2 and 3 are DLE eluents produced during the first quarter of 2023. Li 2 CO 3 production was carried out to completion in batches 1 and 2 but the processing of Batch 3 was put on hold due to its similarity to batches 1 and 2 and the improvements seen in the grades of batches 4 and 5. These improvements in lithium grade from 1,430 parts per million (ppm) to 6,780 ppm, increase in the ratio of lithium to total dissolved solids (TDS) from 0.018 to 0.085, and reduction in sodium from 25,850 ppm to 8,220 ppm all occurred with the introduction of KTS' Li-Pro TM system into the DLE stage of the Company's Pilot Plant.

Implications for Lithium Carbonate Production

The increase in lithium (Li) grade and the Li:TDS ratio has positive implications for the size and costs of the lithium carbonate production portion of the lithium extraction process at the Project. Within the Saltworks flowsheet, these higher values equate to a lower volume of solution to be treated and a proportionate decrease in the amount of water that must be removed (evaporated) prior to lithium carbonate precipitation. This will also affect the recycled solutions within the lithium carbonate production stage by reducing the volume of solutions moved in this stage and other leaching areas of the processing plant.

The information derived from the Pilot Plant, including the test results from the combination of Century Lithium's DLE process and KTS' Li-Pro TM system, and recent component changes at the Saltworks laboratory, is supplemental to the Feasibility Study for the project. The design basis for the Feasibility Study was established at a Li:TDS ratio of 0.02.

The Saltworks flowsheet targets a lithium grade of 10,000 to 20,000 ppm (10-20 g/L) for precipitation. Work with KTS at the DLE stage at the Pilot Plant has seen preliminary, internally assayed, lithium solution grades of over 8,000 ppm in the DLE eluent. Work is continuing within the DLE area to further increase lithium grades in solution, creating the scope to reduce solution volumes and the potential to eliminate a major evaporation step from the process flowsheet. As a supplement to the Feasibility Study, the Company is pursuing these potential cost and size savings with Saltworks.

Moving Forward

Work on the Feasibility Study continued throughout the six months ended June 30, 2023 , with more than 20,000 consultant hours expended since its commencement. Following receipt of initial values from our consultants, Wood PLC and thyssenkrupp nucera, the Company is conducting internal reviews to assess optimization and cost reduction opportunities; work which is underway. In June 2023 , the Company engaged Kiewit Industrial Group in Lone Tree, Colorado to assist with the review of project designs and estimates with attention to site development, material and supply costs, and construction methods. One optimization opportunity, reducing or eliminating the use of thickeners for tailings separation in the process configuration, was implemented and is under trial at the Pilot Plant.

The Company's collaboration with KTS is underway, utilizing KTS' Li-Pro TM equipment in the DLE section of the Pilot Plant, where lithium is selectively recovered from the leach solution while deleterious elements are rejected. Testing with KTS is expected to continue through the 3 rd quarter while KTS collects information to prepare an engineering design and cost estimate for a full-scale deployment of Li-Pro TM system which will supplement the Company's Feasibility Study.

Qualified Person

Todd Fayram , MMSA-QP and Daniel Kalmbach , CPG, are the qualified persons as defined by National Instrument 43-101 and have approved the technical information in this release.

About Century Lithium Corp.

Century Lithium Corp. (formerly Cypress Development Corp.) is an advanced stage lithium company, focused on developing its 100%-owned Clayton Valley Lithium Project in west-central Nevada, USA . Century Lithium is currently in the pilot stage of testing on material from its lithium-bearing claystone deposit at its Lithium Extraction Facility in Amargosa Valley, Nevada and progressing towards completing a Feasibility Study and permitting, with the goal of becoming a domestic producer of lithium for the growing electric vehicle and battery storage market.

ON BEHALF OF Century Lithium CORP.
WILLIAM WILLOUGHBY , PhD., PE
President & Chief Executive Officer

centurylithium.com

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.

Cautionary Note Regarding Forward-Looking Statements

This release includes certain statements that may be deemed to be "forward-looking statements". Forward-looking statements are subject to risks, uncertainties and assumptions and are identified by words such as " expects," "estimates," "projects," "anticipates," "believes," "could," "scheduled," and other similar words. All statements in this release, other than statements of historical facts, that address events or developments that management of the Company expects, are forward-looking statements. Although management believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance, and actual results or developments may differ materially from those in the forward-looking statements. The Company undertakes no obligation to update these forward-looking statements if management's beliefs, estimates or opinions, or other factors, should change. Factors that could cause actual results to differ materially from those in forward-looking statements, include market prices, exploration, and development successes, continued availability of capital and financing, and general economic, market or business conditions. Please see the public filings of the Company at www.sedar.com for further information.

Cision View original content to download multimedia: https://www.prnewswire.com/news-releases/century-lithium-reports-on-testing-with-saltworks-and-production-of-battery-grade-lithium-carbonate-301905334.html

SOURCE Century Lithium Corp.

Cision View original content to download multimedia: https://www.newswire.ca/en/releases/archive/August2023/21/c3469.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
South Star Battery Metals Announces Land Purchase, Construction Update, and the Approval of the Definitive Mining Licenses For Phases 1, 2 & 3 for its Santa Cruz Graphite Mine in Brazil

South Star Battery Metals Announces Land Purchase, Construction Update, and the Approval of the Definitive Mining Licenses For Phases 1, 2 & 3 for its Santa Cruz Graphite Mine in Brazil

Santa Cruz Graphite Mine Highlights:

  • Final payment of land purchase for Phase 1 Plant and Operations.
  • Approval of the Definitive Mining Licenses For Phases 1, 2 & 3. All mining and environmental licenses/permits are approved and in-hand for the future phased, modular expansion of Santa Cruz graphite production up to 50,000 tonnes/year.
  • Phase 1 construction is on schedule for substantial completion by the end of June 2024 followed by a 6-week plant commissioning and ramp-up period. Commercial sales are planned to start in September 2024. Name plate production capacity is expected to be reached in Q4 2024.

South Star Battery Metals Corp. ("South Star" or the "Company") (TSXV:STS)(OTCQB:STSBF) is pleased to announce the final payment of the previously announced (Aug. 02, 2022) land purchase required for construction of the Phase 1 mine and plant facilities. The farm totals approximately 325 hectares and is where all the plant facilities, mine and infrastructure installations are required for the first three years of operations at its Santa Cruz Graphite Project in Bahia, Brazil

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
QX Resources Ltd  Large Basin Confirmed in Drillholes at Liberty Lithium Brine

QX Resources Ltd Large Basin Confirmed in Drillholes at Liberty Lithium Brine

Perth, Australia (ABN Newswire) - QX Resources Limited (ASX:QXR) can confirm that the Liberty Lithium brine project in California, USA, is a large brine basin with numerous brine aquifers, shown in downhole sampling and geophysics in the second hole of the Company's two-hole diamond drill program (Table 1*).

- Drilling and geophysics indicate the existence of a large brine basin at Liberty Lithium Brine Project USA, with brine intersected over 400 m vertically.

o Geological similarities confirmed with the nearby Silver Peak lithium brine producer Albemarle, in Clayton Valley Nevada, with encouraging initial lithium assay results, aquifers and salinity.

- Lithium brine specialists have proposed additional drilling to intersect deep lithium brines in the centre of the basin, in a more favourable setting, further west of recent drilling.

- Discussions continue with various USA based battery supply participants who are keen to work with potential new lithium developers within the USA, including with Stardust who aim to IPO in June.

- QXR and IG Lithium Option Agreements are being amended to facilitate undertaking further drilling.

- QXR aims to provide an update soon on progress with gold exploration in Queensland.

Porous conglomerates saturated with brines were intersected beneath fine grained lake sediments with sandy layers. The geology intersected is very encouraging as it is similar to the producing sequences of Clayton Valley Nevada, where Albemarle's producing lithium brine deposit is located. Detailed downhole geophysics together with initial downhole brine sampling (packer sampling) shows increasing salinity with depth, together with large brine volumes, both encouraging for discovering a potentially economic lithium brine deposit in the properties.

Although the maximum lithium assay values were 50mg/l Li over 15 metres near the base of hole #2 (Table 2*), the salinity and conductivity increased with depth, at levels similar to known producers. Ingress of fresh water into the aquifers may explain the lower lithium values in drill holes #1 and #2 being located close to a range front fault on the edge of the basin. These initial holes were located near the edge of the basin in part for logistics and access reasons as well as the surface lithium anomaly.

Hole #2 also intersected thick porous brine horizons - critical for future success- which is considered encouraging, together with the geological similarity to Clayton Valley NV (Albemarle's Silver Peak mine). These similarities include basal porous conglomerate units containing brine beneath finer grained lake sediments.

However, the best producing horizons at Clayton Valley are tuff units within the sediment package which have not been intersected in drillholes to date, but which outcrop 4km to the southwest of hole #2 (Figure 4*).

Results were analysed by external lithium brine specialists to produce interpretations, including the globally recognised Hydrominex Geoscience Consulting. Lithium brine specialists have advised additional drilling is required to potentially intersect deep lithium brines in the centre of the basin, further west of drilling undertaken by QXR, based on lab results to date.

QXR Managing Director, Stephen Promnitz, said: "QXR has defined a new large scale brine basin, saturated with brines, at the Liberty Lithium Brine Project. A large near-surface brine field with lithium potential is rare to date in the USA. The geological setting, with conglomerates loaded with brines, is similar to Albemarle's producing deposit. We are yet to find tuff horizons similar to Clayton Valley, which are the best brine aquifers - although they do outcrop nearby, suggesting they may exist within the basin. Surface and downhole geophysics make it compelling for further drilling to the west, in the centre of the basin under deeper sediments, which may intersect higher grade lithium brine, compared to the drilling to date."

Next Steps

Applications for further drillholes were submitted some time ago. To provide operational flexibility, an amended drill program has been submitted to regulators for approval. Bulk volumes of brine will be submitted for testwork with selected direct lithium extraction (DLE) providers, as well as with lithium refiner Stardust Power Inc, with whom QXR holds at Letter of Intent (ASX announcement 29 Feb 2024). Stardust expects to list on NASDAQ in June via a c.US$490m deal and then plans to build a lithium refinery in Oklahoma.

Discussions continue with various USA based battery supply participants who are keen to work with potential new lithium developers within the USA.

QXR and IG Lithium are currently discussing amendments to the Option Agreements to facilitate the undertaking of further drilling.

Background

The Liberty Lithium Brine Project, located in SaltFire Flat, California, covers contiguous claims over 102km2 (25,300 acres), being one of the largest single lithium brine projects in the USA (Figure 1*). The Company entered an Option to Purchase Agreement and an Operating Agreement (Option Agreements) to earn a 75% interest in the large scale Liberty Lithium brine project in California, USA, from vendor IG Lithium LLC (ASX announcement 5 October 2023). Based on results received to date, the Company is currently in discussion with IG Lithium regarding potential renegotiation of the Option Agreements to allow a longer period of time to conduct additional drilling prior to any future commitments.

Two vertical diamond drill holes were completed (369m & 443 metres depth), spaced 4km apart (Figure 2, 3*).

Holes were centred over an extensive lithium brine surface anomaly and significant MT geophysical target, interpreted as a series of conductive brine bearing aquifers at depth. Brine horizons were intersected in both holes with numerous brine aquifers intersected in drillhole #2 (ASX announcement 8 Feb 2024).

QXR entered into a Letter of Intent with Stardust Power Inc., a development stage American manufacturer of battery-grade lithium products, to assess the lithium brines from the Liberty Lithium Brine Project. The parties intend to evaluate options to potentially supply Stardust Power with lithium brine products, dependent on results, on a non-exclusive basis for processing into battery-grade lithium materials for electric vehicles (ASX announcement 29 Feb 2024). The Company plans to share the results of the two hole drill program with Stardust as part of ongoing discussions.

Drillholes

Drillhole #1 (LLD23001) was completed at 369 metres depth. Target horizons were intersected at 49m depth and 329m depth. Fine grained sediments, gravels and coarse alluvial fan material were intersected down the length of the hole. An interpretation is that the drillhole went through the range front fault at 249m depth.

Drillhole #2 (LLD24002) was completed at 433 metres depth, located 4km to the south of drillhole #1. Both drillholes were centred over significant MT geophysical targets interpreted as a series of conductive brine bearing aquifers at depth. Both holes were positioned within an extensive lithium brine surface anomaly of over 10km defined in auger samples. An interpretation is that the drillhole went through the range front fault at 370m depth.

Figures 5 shows the increase in lithium and chloride concentration in brine with increasing depth. Figures 6-8* show interpretations of the possible geology on MT geophysical lines and the location of proposed drill holes.

The location of the proposed drill holes is also shown in Figure 9*.

Recommendations

Results were analysed by external lithium brine specialists to produce interpretations, including the globally recognised Hydrominex Geoscience Consulting, and others who have closely reviewed the geological setting of Albemarle's Silver Peak lithium brine producer in Clayton Valley, Nevada. Their recommendations included additional drilling further west of drilling undertaken by QXR, to potentially intersect deep lithium brines in the centre of the basin, based on lab results to date. Surface and downhole geophysics suggests that the basin is angled to the west with deeper sediments and brines to the west of recent drilling. Further, the geochemistry of the brine samples may suggest an ingress of fresh water into the aquifers, resulting in lower lithium grade in the two holes drilled to date, as the holes were drilled adjacent to a range front fault with significant fresh water inflows into the basin, along the basin edge.

*To view tables and figures, please visit:
https://abnnewswire.net/lnk/C58T0H5U



About QX Resources Ltd:

QX Resources Limited (ASX:QXR) is focused on exploration and development of battery minerals, with hard rock lithium assets in a prime location of Western Australia (WA), and gold assets in Queensland. The aim is to connect end users (battery, cathode and car makers) with QXR, an experienced explorer/developer of battery minerals, with an expanding mineral exploration project portfolio and solid financial support.

Lithium portfolio: QXR's lithium strategy is centred around WA's prolific Pilbara province, where it has acquired a controlling interest in four projects through targeted M&A - all of which sit in strategic proximity to some of Australia's largest lithium deposits and mines. Across the Pilbara, QXR's regional lithium tenement package (both granted or under application) now spans more than 350 km2.

Gold portfolio: QXR is also developing two Central Queensland gold projects - Lucky Break and Belyando - through an earn-in agreement with Zamia Resources Pty Ltd. Both gold projects are strategically located within the Drummond Basin, a region that has a >6.5moz gold endowment.

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Miguel Paucar Joins Lancaster Resources Advisory Board to Propel Corporate Growth and Sustainable Operations

Miguel Paucar Joins Lancaster Resources Advisory Board to Propel Corporate Growth and Sustainable Operations

Lancaster Resources Inc. (CSE:LCR) (OTCQB: LANRF) (FRA:6UF0) (" Lancaster "), a critical mineral exploration company, is pleased to announce the appointment of Miguel Paucar, B.Sc., M.Sc. to its Advisory Board. With over 28 years of extensive experience in the international mining sector, Miguel brings a wealth of knowledge and expertise from his work across diverse geographical regions including South Africa, Australia, Chile, Mexico, Peru, and Brazil. His career has encompassed significant roles in both underground and open-pit mining as well as geomechanics.

Miguel notably served as the Mining Director at Sigma Lithium from 2021 to 2022, where he spearheaded major advancements in lithium extraction technologies and sustainability practices. Under his leadership, the company implemented initiatives such as using 100% renewable energy and recycled water, producing "quintuple zero green" lithium with a focus on zero tailings dams and zero hazardous waste.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
ALX Resources Corp. Receives Analytical Results from the Gibbons Creek Uranium Project, Athabasca Basin, Saskatchewan

ALX Resources Corp. Receives Analytical Results from the Gibbons Creek Uranium Project, Athabasca Basin, Saskatchewan

alx resources corp. (TSXV: AL) (FSE: 6LLN) (OTC: ALXEF) ("ALX" or the "Company") is pleased to announce the results of the 2024 winter drilling program and upcoming summer 2024 exploration plans at its Gibbons Creek Uranium Project ("Gibbons Creek", or the "Project") located in the northern Athabasca Basin near the community of Stony Rapids, Saskatchewan.

Gibbons Creek is the subject of an option earn-in transaction with Trinex Lithium Ltd., a wholly-owned subsidiary of Trinex Minerals Limited ("Trinex"), which is a publicly-traded mineral exploration company listed on the Australian Securities Exchange. Under the terms of a definitive agreement signed in May 2024, Trinex can earn an initial 51% interest and up to a 75% participating interest in the Project in two stages over a period of five years by making cash payments and common shares payments to ALX, and by incurring exploration expenditures at the Project (see ALX news release dated May 8, 2024).

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Brunswick Exploration Launches Multinational Exploration Campaign

Brunswick Exploration Launches Multinational Exploration Campaign

Brunswick Exploration Inc. (" BRW " or the " Company ") is pleased to announce that it has started a helicopter-supported prospecting campaign in Quebec with additional programs in Labrador and Greenland to begin in July and August 2024, respectively. BRW plans to systematically test hundreds of new and outcropping S-type pegmatite targets across its portfolio.

Mr. Killian Charles, President and CEO of BRW, commented: "While we continue to focus our efforts into the Mirage Project, we are thrilled to start new, ambitious grassroots initiatives throughout Eastern Canada and Greenland. These initiatives are a core pillar of BRW's strategy and, as the lithium industry remains ripe for new discoveries, we will continue to leverage our exploration expertise to rapidly identify new targets and explore in sound jurisdictions."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
NextSource Materials Signs Mandate Letter for US$91 Million Debt Facility with International Finance Corporation

NextSource Materials Signs Mandate Letter for US$91 Million Debt Facility with International Finance Corporation

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or "the Company") is pleased to announce the signing of a Mandate Letter with International Finance Corporation ("IFC"), the private sector investment arm of the World Bank Group, to lead a senior debt facility totaling US$91 million (the "IFC Debt Facility") to fund an expansion of the Molo Graphite Mine (the "Molo mine") in southern Madagascar

In December 2023, the Company released the results of a Technical Feasibility Study (the "FS") that confirmed the positive economics of a large-scale expansion of the Molo mine and processing facility from its current production capacity of 17,000 tonnes per annum (tpa) to 150,000 tpa of SuperFlake® graphite concentrate. The FS estimated a capital cost of US$161.7 million (including contingency) plus working capital of US$25.2 million, resulting in a pre-tax NPV8 (using an 8% discount rate) of US$424.1 million and a pre-tax Internal Rate of Return (IRR) of 31.1%, and a NPV8 of US$370.0 and IRR of 29.0% on a post-tax basis.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less