
July 20, 2022
GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to provide initial production guidance for its 60% owned Abra Base Metals Mine (“Abra” or the “Project”) having achieved the construction milestone of 75% complete. The guidance for the CY2023 ramp-up year and future life of mine averages are based on the most recently updated mine plan incorporating updated mine designs and the latest cost information.
HIGHLIGHTS
- Abra Project construction is now 75% complete – Galena confirms first concentrate production remains on-target for Q1 2023 and provides initial production targets based on latest mine plan
- CY2023 mill throughput expected to be 0.8-1.0Mtpa resulting in ramp-up year lead production of 53-68kt
- Following ramp-up, life of mine average annual production expected to average 93,000 tonnes of lead and 553,000 ounces of silver, with lead ‘C1’ direct cash cost of US$0.50/lb
- Plant processing throughput and mine plan increased to 1.3Mtpa in the current mine plan (vs. 1.2Mtpa in 2019 Feasibility Study)1
Managing Director, Tony James commented, “With first concentrate production on target for the March 2023 quarter, we provide this update on near-term and life of mine plan and targets. During the construction period of the project, we have worked very closely with our partner Toho Zinc and our key service providers to reach the 75% build mark. For the remainder of 2022 we plan to safely complete the mine construction and commission Abra as a world-class lead-silver mine.”
The guidance provided today is based on the knowledge and confidence gained from additional drilling, Mineral Resource estimation, and advancing construction at Abra, and preparation for commissioning ahead of a planned safe and efficient start-up.
Grade control drilling commenced in June 2022 and ongoing drilling and evaluation over the next 3 months will likely offer further opportunity for additional optimisation of the mine plan.
The forecast life of mine production now averages 93,000tpa lead metal production and 553,000ozpa silver. An 8% increase in mine and mill production is offset by a 6% reduction in lead grade to produce slightly less metal in direct comparison to the 2019 Feasibility Study (“FS”)1. A suitable ramp up profile has been adopted for the CY2023 prior to reaching steady state production which is anticipated to occur in the December quarter 2023.
Table 1 below outlines the current expected production forecast for CY2023 and the Updated Life of Mine outcomes in direct comparison the FS completed in 2019.
Table Notes
1. Key outcomes and metrics shown reference 100% of Project. Abra Project is owned 60% by Galena & 40% by Toho Zinc.
2. Includes a by-product credit for net silver revenue of US$0.04/lb (A$0.06/lb).
3. Current lead metal price and exchange rate.
Table 1 - Updated Abra key operating and financial metrics.
The Abra mine construction is progressing as planned. Progress reached 73% complete as of 30 June 2022 and has since past 75% complete. Processing plant construction activities reached 79% complete with concrete civils passing 95% complete and structural steel passing 42% complete. During June and early July several key equipment items arrived on site and the only remaining items coming from overseas are the flotation cells and the regrind mill. These items are currently in shipping with the flotation cells expected to arrive on 12 August and the regrind mill expected to arrive on 1 September. Figures 1 to 4 included in this announcement provide additional photographs of the Abra work completed to date.
Click here for the full ASX Release
This article includes content from GALENA MINING LTD., licensed for the purpose of publishing on Investing News Australia. This article does not constitute financial product advice. It is your responsibility to perform proper due diligence before acting upon any information provided here. Please refer to our full disclaimer here.
G1A:AU
The Conversation (0)
12 September 2022
Galena Mining
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job."
Galena Mining CEO Tony James said, “People have been just sitting and watching how we would perform this year, a perceived difficult construction period. But we've done a great job." Keep Reading...
17h
After Major Gold Payout, Bian Ximing Turns Bearish Sights on Silver
A Chinese billionaire trader known for profiting from gold’s multi-year rally has turned sharply bearish on silver, building a short position now worth nearly US$300 million as prices slide.Bian Ximing, who earned billions riding gold’s multi-year rally and later turned aggressively bullish on... Keep Reading...
03 February
Silver Supply Tight, Demand Rising — What's Next? First Majestic's Mani Alkhafaji
Mani Alkhafaji, president of First Majestic Silver (TSX:AG,NYSE:AG), discusses silver supply, demand and price dynamics, as well as how the company is positioning for 2026.He also shares his thoughts on when silver stocks may catch up to the silver price: "You've got to give it a couple of... Keep Reading...
03 February
Rio Silver’s Path to Near-Term Cashflow
Rio Silver (TSXV:RYO,OTCPL:RYOOF) President and CEO Chris Verrico outlines the company’s transition into a pure-play silver developer. With the silver price reaching historic highs, Rio Silver is capitalizing on its strategic position in Peru — the world’s second largest silver producer — to... Keep Reading...
02 February
When Will Silver Stocks Catch Up to the Silver Price?
The silver price remains historically high despite a recent pullback, and many silver stocks haven't kept pace. Silver's strong performance over the past year is the result of a perfect storm of factors, including an entrenched supply deficit, growing industrial demand, a weakening US dollar and... Keep Reading...
Latest News
Interactive Chart
Latest Press Releases
Related News
TOP STOCKS
American Battery4.030.24
Aion Therapeutic0.10-0.01
Cybin Corp2.140.00






