PFS Plant Location Study Results in Decision to Locate Carbonation Plant in Mining Centre of Copiapó

CleanTech Lithium PLC (AIM: CTL, Frankfurt:T2N, OTCQX:CTLHF), an exploration and development company advancing sustainable lithium projects in Chile, announces the results of a plant location study completed as part of the ongoing pre-feasibility study (PFS) for the Laguna Verde Project, which is due to complete later this year. The PFS is being led by Worley, a global professional services company of energy, chemicals and resources experts, from its Santiago office which has high-level experience in the lithium sector. Xi´an Lanshen New Material Technology Company ("Lanshen") has been selected to provide the lithium processing plant design and equipment, and Worley to design the balance of plant and infrastructure.


Highlights:

  • A plant location study was completed by Worley, which evaluated the optimal plant location configuration for the Laguna Verde project, based on a capacity of 20,000 tonnes per annum of battery grade lithium carbonate equivalent (LCE)
  • This provided a trade-off analysis between locating the entire plant at Laguna Verde versus splitting plant facilities between Laguna Verde and the nearby mining centre of Copiapó
  • The option of locating the DLE plant and eluate concentration stages at the Laguna Verde site, and the carbonation plant at Copiapó is highly favourable, resulting in the decision to proceed with this option
  • A concentrated eluate with 6% lithium, the maximum concentration before lithium salts begin to precipitate, will be transported to Copiapó for impurity removal and carbonation stages
  • This configuration results in a minor increase in volumes transported while taking advantage of Copiapó's well-developed infrastructure and better access to a skilled workforce
  • According to the Lanshen plant design, approximately 70% of the operational workforce will be employed at the carbonation plant, locating it in Copiapó provides major advantages in hiring a local work force including diversity outcomes such as greater female participation, while contributing to the local economy
  • The footprint at the project site, which is at 4300m above sea level, will be greatly reduced, from power supply, storage, camp and plant facilities, construction phase impacts, and environmental impacts
  • The carbonation plant in Copiapó would eventually be expanded to also treat concentrated eluate from the Viento Andino project
  • The PFS, now due for completion before the end of Q4 this year, will include updated capex and opex estimates and will further determine the optimal production development strategy

Steve Kesler, Executive Chairman and Interim Chief Executive Officer, CleanTech Lithium PLC, said:

"We undertook a plant location study as part of our ongoing PFS for the Laguna Verde project resulting in the decision to locate the DLE and eluate concentration stages at the project site, and the carbonation plant in Copiapó. This will have various benefits such as reducing the footprint and impacts at Laguna Verde, and taking advantage of existing infrastructure, power supply and skilled workforce in Copiapó. The plant at Copiapó can then be expanded to treat material from our Viento Andino project and potentially others. The decision on plant configuration will feed directly into the wider PFS which is due to be completed later this year."

Further Information

The Company engaged Worley, utilising its local Santiago based office, to undertake the PFS for the Laguna Verde project, and selected Lanshen as designer and supplier of the entire DLE processing plant. Worley recently performed various trade-off or options studies to consider the most favourable configuration of the project and a plant location option study which assessed three scenarios for location of the plant, of which two of the scenarios, labelled Scenario 1 and Scenario 3 in the report, provided the relevant trade-off comparison:

  • Scenario 1: Locating the entire plant based at the Laguna Verde project site
  • Scenario 3: Locating DLE and eluate concentration stages at the project site, and the impurity removal and carbonation (downstream plant) at Copiapó

Laguna Verde is connected to Copiapó via a 270km paved international highway, as shown in Figure 1. Copiapó is a major regional mining centre in Chile with a population of 175,000, having well established infrastructure, a skilled workforce, and existing supply hubs for reagents and other materials. While basing the entire plant at the project site is feasible and most lithium projects in the lithium triangle are proceeding on such a basis, the good transport link and relative proximity to Copiapó made a trade-off study valuable.

Figure 1: Regional Map

An analysis of the difference in transport volumes was undertaken showing a minimal overall difference between the two scenarios. For Scenario 3 where impurity removal and carbonation stages are in Copiapó, there will be no transport of reagents or bulk chemicals to Laguna Verde which has a positive environmental and community impact.

A qualitative assessment was then undertaken by the Company across the range of metrics as shown in Figure 2. There are only two metrics in which Scenario 1 where the entire plant is located at site has a significantly positive comparison. The first one is storage during the construction phase, in that it will require a single storage facility rather than storage at both locations for tools, materials and spare parts. The second is disposal of solids, which is largely Sodium Chloride (NaCl or table salt) that is dissolved in the eluate and removed in the impurity removal stage before carbonation. In Scenario 1, these would be re-dissolved in the spent brine and re-injected. In Scenario 3, the report assumed NaCl would need to be disposed in Copiapó at a cost. However there should be a ready market for NaCl and further evaluation of this is required.

A diagram of a work schedule Description automatically generated with medium confidence

Figure 2: Qualitative Comparison- All on site (1) and split plants (3)

Across a range of other metrics the Scenario 3 of locating the downstream plant at Copiapó has major advantages. According to Lanshen, approximately 70% of the operational labour force will work at the downstream plant, which provides a far superior option for skilled workforce based in Copiapó. The footprint at the project site will be greatly reduced, from power supply, storage, camp and plant facilities, construction phase impacts, and environmental impacts. The Board has accepted the study and the decision to split the plant facilities between the project site and Copiapó will be the basis for the PFS.

For further information contact:


CleanTech Lithium PLC


Steve Kesler/Gordon Stein/Nick Baxter

Jersey office: +44 (0) 1534 668 321

Chile office: +562-32239222


Or via Celicourt

Celicourt Communications

Felicity Winkles/Philip Dennis/Ali AlQahtani

+44 (0) 20 7770 6424

cleantech@celicourt.uk

Beaumont Cornish Limited (Nominated Adviser)

Roland Cornish/Asia Szusciak

+44 (0) 20 7628 3396

Fox-Davies Capital Limited (Joint Broker)

Daniel Fox-Davies

+44 (0) 20 3884 8450

daniel@fox-davies.com

Canaccord Genuity (Joint Broker)

James Asensio

+44 (0) 20 7523 4680

Beaumont Cornish Limited ("Beaumont Cornish") is the Company's Nominated Adviser and is authorised and regulated by the FCA. Beaumont Cornish's responsibilities as the Company's Nominated Adviser, including a responsibility to advise and guide the Company on its responsibilities under the AIM Rules for Companies and AIM Rules for Nominated Advisers, are owed solely to the London Stock Exchange. Beaumont Cornish is not acting for and will not be responsible to any other persons for providing protections afforded to customers of Beaumont Cornish nor for advising them in relation to the proposed arrangements described in this announcement or any matter referred to in it.

Notes

CleanTech Lithium (AIM:CTL, Frankfurt:T2N, OTCQX:CTLHF) is an exploration and development company advancing sustainable lithium projects in Chile for the clean energy transition. Committed to net-zero, CleanTech Lithium's mission is to produce material quantities of sustainable battery grade lithium products using Direct Lithium Extraction technology powered by renewable energy. The Company plans to be a leading supplier of 'green' lithium to the EV and battery manufacturing market.

CleanTech Lithium has two key lithium projects in Chile, Laguna Verde and Viento Andino, and hold licences in Llamara and Salar de Atacama, located in the lithium triangle, a leading centre for battery grade lithium production. The two major projects: Laguna Verde and Viento Andino are situated within basins controlled by the Company, which affords significant potential development and operational advantages. All four projects have direct access to existing infrastructure and renewable power.

CleanTech Lithium is committed to using renewable power for processing and reducing the environmental impact of its lithium production by utilising Direct Lithium Extraction with reinjection of spent brine. Direct Lithium Extraction is a transformative technology which removes lithium from brine, with higher recoveries than conventional extraction processes. The method offers short development lead times with no extensive site construction or evaporation pond development so there is minimal water depletion from the aquifer. www.ctlithium.com


Source

Click here to connect with CleanTech Lithium PLC (AIM:CTL, OTCQX:CTLHF, Frankfurt:T2N), to receive an Investor Presentation

CTLHF
CleanTech Lithium

CleanTech Lithium Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
CleanTech Lithium

CleanTech Lithium


Keep reading...Show less
CleanTech Lithium PLC Announces Notice of AGM

CleanTech Lithium PLC Announces Notice of AGM

CleanTech Lithium PLC Notice of Annual General Meeting

CleanTech Lithium PLC (AIM:CTL)(Frankfurt:T2N)(OTCQX:CTLHF) ("CleanTech Lithium" or the "Company"), an exploration and development company advancing sustainable lithium projects in Chile, will hold its Annual General Meeting ("AGM") at the offices of the Company at de Carteret House, 7 Castle Street, St Helier JE2 3BT on 26 November 2024 at 11:00AM GMT

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
CleanTech Lithium PLC Announces Interim Results

CleanTech Lithium PLC Announces Interim Results

Interim Results for six-month period ending 30 June 2024

CleanTech Lithium PLC (AIM:CTL)(Frankfurt:T2N)(OTCQX:CTLHF), an exploration and development companyadvancing sustainable lithium projects in Chile for the clean energy transition, is pleased to announce its unaudited Interim Results for the six-month period ended 30 June 2024 ("1H 2024" or "the Period").

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
CleanTech Lithium PLC Announces CEOL Update

CleanTech Lithium PLC Announces CEOL Update

Chilean Government prioritises Laguna Verde for CEOL

CleanTech Lithium PLC (AIM:CTL)(Frankfurt:T2N)(OTCQX:CTLHF), an exploration and development company advancing lithium projects in Chile for the clean energy transition, reports an announcement by the Chilean Government on the Expressions of Interest ("RFIs") process under which the Company made submissions in June 2024. This is part of the process for the awarding of a Special Lithium Operating Contract ("CEOL") to enter production

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
CleanTech Lithium PLC Announces Community Support for Laguna Verde Project

CleanTech Lithium PLC Announces Community Support for Laguna Verde Project

Indigenous community leader publicly endorses Laguna Verde project at key mining seminar in Santiago, Chile

CleanTech Lithium PLC (AIM:CTL)(Frankfurt:T2N)(OTCQX:CTLHF), an exploration and development company advancing sustainable lithium projects in Chile, participated in the Centre for Copper and Mining Studies ("CESCO") seminar in Santiago, a prominent annual seminar for the mining sector in Chile, and received public support from the local indigenous community for its Laguna Verde project. Executive Chairman and Interim CEO, Steve Kesler, presented and reinforced the Company is ready to begin project construction by 2026 upon the granting of a Special Lithium Operating Contract ("CEOL") by the Chilean Government

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
CleanTech Lithium PLC Announces Transfer of Loan Notes at Regal Funds

CleanTech Lithium PLC Announces Transfer of Loan Notes at Regal Funds

CleanTech Lithium PLC (AIM:CTL)(Frankfurt:T2N)(OTCQX:CTLHF), an exploration and development company advancing sustainable lithium projects in Chile, announces the transfer of AUD Loan Notes (Loan Notes) from one Regal Funds1 associate to another Regal Funds associate

On 1 July 2024, the Company announced that Regal Tactical Credit Fund (RTCF), of which Regal Funds Management Pty Ltd (RFM) is a trustee, subscribed for A$3,000,000 of the Loan Notes. The Company has recently received a request by RFM to transfer the beneficial ownership of the Loan Notes and Warrants held by RTCF to Regal Emerging Companies Opportunities Fund Pty Ltd (RECOF), of which RFM is also a trustee, to which it has consented

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
  Loyal Lithium Limited

Strategic Consolidation of Hidden Lake and Board Changes

Loyal Lithium Limited (ASX:LLI) (Loyal Lithium, LLI, or the Company) is pleased to announce the execution of a definitive agreement for the consolidation of the Hidden Lake Lithium Project, with Patriot Battery Metals (ASX:PMT) becoming a substantial LLI shareholder. Mr. Blair Way, Non- Executive Director and former President & CEO of Patriot Battery Metals, will join the Loyal Lithium Board of Directors, bringing valuable regional and industry expertise to guide the company's growth initiatives. The consolidation of the Hidden Lake Lithium Project provides Loyal Lithium with greater flexibility and optionality to deploy innovative exploration and development solutions.

Keep reading...Show less
Drilling Commences at the Barra Lithium Project in Brazil

Drilling Commences at the Barra Lithium Project in Brazil

Summit Minerals Limited (ASX:SUM) (“Summit” or the “Company”) is pleased to announce that Summit’s maiden drilling program has commenced at the recently acquired 100% owned Barra Lithium Project (“Barra”).

The Barra Lithium Project consists of four recently acquired tenements that are located within close proximity to the existing operating Miranda Lithium mine that is within the Borborema Pegmatitic Province (“BPP”) in northeast Brazil.

Keep reading...Show less
Lithium Universe

Lithium Universe


Keep reading...Show less
CleanTech Lithium (AIM:CTL)

Issue of Equity and TVR


Keep reading...Show less
CleanTech Lithium

CleanTech Lithium Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×