NextSource Materials Announces Solar and Battery Hybrid Power Plant Construction and Site Works Update

NextSource Materials Announces Solar and Battery Hybrid Power Plant Construction and Site Works Update

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or the "Company") is pleased to provide a site works update and to announce that a Madagascar subsidiary of CrossBoundary Energy ("CBE") has commenced the construction process for the solar and battery hybrid power plant for Phase 1 of the Molo Graphite Mine in Madagascar after the Company executed a definitive energy services agreement with CrossBoundary Energy's ("CBE") Madagascar subsidiary

Molo Mine Construction Update

Earthworks and civil construction at the mine site are progressing according to schedule and will be ready for the arrival of the processing plant and auxiliary buildings in June 2022. Completion of construction and plant commissioning is expected in Q3 2022, followed by a ramp up period of up to three months to achieve nameplate capacity.

Due to increases in global logistics costs the Company has increased the construction budget for Phase 1 of the Molo Graphite Mine by approximately $3.0 million. The Phase 1 capital cost budget is now $24.0 million plus an additional $3.0 million for working capital.

Construction of Solar and Battery Hybrid Power Plant

As announced on November 23, 2021, CBE was selected to build, own, and operate a solar, battery and thermal hybrid energy power plant ("Hybrid Plant") over a 20-year term. The Hybrid Plant will consist of a 2.6MW solar PV facility, a 1MWh battery energy storage system ("BESS") and a 3.1MW thermal facility (diesel generators). The Hybrid Plant will be located adjacent to the Molo mine site and will provide up to 33% of the mine's total Phase 1 electricity needs from renewable solar energy, with the remainder coming from thermal generators.

Construction of the Hybrid Plant has begun and all required licenses to initiate construction of the solar facility have been obtained. The thermal facility, solar facility and BESS are all expected to be installed and operational prior to initiating commissioning of the Molo processing plant in Q3 2022.

President and CEO, Craig Scherba commented,

"The solar facility and battery energy storage system is integral to our commitment to minimize our carbon emissions and build a sustainable mine. Over the life of the project, we will aim to further reduce our reliance on fossil fuels with the added benefit of lower costs and therefore better project economics."

During peak daylight hours, the solar facility and BESS will be capable of supplying up to 100% of the plant's power requirements. The thermal facility will be used in combination to provide uninterrupted power supply and always ensure 100% power availability to the mine.

NextSource and CBE are committed to optimizing the solar component throughout the contract to increase the percentage of renewable energy available to the mine.

About NextSource Materials Inc.

NextSource Materials Inc. is a strategic materials development company based in Toronto, Canada that is intent on becoming a fully integrated, global supplier of critical battery and technology materials needed to power the sustainable energy revolution.

The Company's Molo graphite project in Madagascar is one of the largest known and highest-quality graphite deposits globally, and the only one with SuperFlake® graphite. Construction of Phase 1 of the Molo Project is underway, with commissioning expected in Q3, 2022.

NextSource Materials is listed on the Toronto Stock Exchange (TSX) under the symbol "NEXT" and on the OTCQB under the symbol "NSRCF".

For further information contact: +1.416.364.4911

Brent Nykoliation, Executive Vice President, Corporate Development at brent@nextsourcematerials.com or Craig Scherba, President and CEO at craig@nextsourcematerials.com

Safe Harbour: This press release contains statements that may constitute "forward-looking information" or "forward-looking statements" within the meaning of applicable Canadian and United States securities legislation. Readers are cautioned not to place undue reliance on forward-looking information or statements. Forward looking statements and information are frequently characterized by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate", "potential", "possible" and other similar words, or statements that certain events or conditions "may", "will", "could", or "should" occur. Forward-looking statements include any statements regarding, among others, timing of on-site construction including completion of the civil and earthworks, timing of the delivery of the processing plant and installation thereof, delivery and installation of the auxiliary buildings and structures, delivery and construction of the Solar Battery System, shipping of all plant infrastructure to site, all re-assembly and commissioning of the Molo Project, initiation of a Feasibility Study and timing of its completion, production capacity, NPV, IRR and life of mine of the Molo mine, timing of the FEED Study and Feasibility Study, as well as the Company's intent on becoming a fully integrated global supplier of critical battery and technology materials. These statements are based on current expectations, estimates and assumptions that involve a number of risks, which could cause actual results to vary and, in some instances, to differ materially from those anticipated by the Company and described in the forward-looking statements contained in this press release. No assurance can be given that any of the events anticipated by the forward-looking statements will transpire or occur or, if any of them do so, what benefits the Company will derive there from. The forward-looking statements contained in this news release are made as at the date of this news release and the Company does not undertake any obligation to update publicly or to revise any of the forward-looking statements, whether because of new information, future events or otherwise, except as may be required by applicable securities laws. Although the forward-looking statements contained in this news release are based on what management believes are reasonable assumptions, the Company cannot assure investors that actual results will be consistent with them. These forward-looking statements are made as of the date of this news release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the Company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release.

SOURCE:NextSource Materials Inc.



View source version on accesswire.com:
https://www.accesswire.com/702455/NextSource-Materials-Announces-Solar-and-Battery-Hybrid-Power-Plant-Construction-and-Site-Works-Update

News Provided by ACCESSWIRE via QuoteMedia

NEXT:CA
NextSource Materials

NextSource Materials Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
NextSource Materials

NextSource Materials


Keep reading...Show less
NextSource Materials Provides Development Update on Battery Anode Facility in Mauritius Freeport Zone

NextSource Materials Provides Development Update on Battery Anode Facility in Mauritius Freeport Zone

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or the "Company") is pleased to announce progress with the development of its Battery Anode Facility (BAF) in the Freeport Zone of the port of Port-Louis, Mauritius

Following a comprehensive site selection process, the Company has signed a long-term lease agreement for a site in the Freeport Zone of Port-Louis for the location of its first BAF plant. The Company has integrated engineering improvements into the plant design and initiated the environmental permitting (EIA) process.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
NextSource Materials Provides Update on Molo Graphite Mine Commissioning

NextSource Materials Provides Update on Molo Graphite Mine Commissioning

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or "the Company") announces an update on the commissioning process at its Molo Graphite Mine ("Molo mine") in southern Madagascar

Since announcing first graphite production in June 2023, the Company has progressed methodically through debottlenecking and optimization activities to achieve the plant nameplate capacity of 17,000 tonnes per annum of SuperFlake® graphite concentrate.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
NextSource Materials Announces Robust Feasibility Study Results for Molo Mine Expansion to 150,000 Tonnes per Annum of SuperFlake Graphite Concentrate

NextSource Materials Announces Robust Feasibility Study Results for Molo Mine Expansion to 150,000 Tonnes per Annum of SuperFlake Graphite Concentrate

Highlights

  • Feasibility Study confirms highly attractive economics for a large-scale expansion of the Molo Mine and processing facility to a steady-state production rate of 150,000 tpa of graphite concentrate
  • Estimated capital cost of US$161.7 million (including contingency), with pre-tax NPV8 of US$424.1 million and a pre-tax IRR of 31.1%
  • Expansion significantly de-risked through application of NextSource's all-modular construction approach and sharing of infrastructure with existing operations
  • Discussions with OEMs and battery manufacturers indicate robust demand for the Company's product

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or "the Company") is pleased to announce the results of a Feasibility Study (the "FS") for a mine expansion of its 100%-owned Molo Graphite Mine in southern Madagascar

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
NextSource Announces Appointment of Martina Buchhauser to the Board and Results of 2023 Annual and Special Meeting of Shareholders

NextSource Announces Appointment of Martina Buchhauser to the Board and Results of 2023 Annual and Special Meeting of Shareholders

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or the "Company") is pleased to announce the appointment of Ms. Martina Buchhauser to the Board of Directors and results of the Annual and Special Meeting of Shareholders (the "Meeting") held virtually at 9:00 AM Toronto, Ontario, Canada on December 5, 2023

Ms. Buchhauser is a global leader with a profound knowledge of the automotive industry and its shift towards new and sustainable technologies and the imperative for a responsible and low carbon business. Her leadership journey has encompassed executive roles in Global Procurement and Supply Chain Networks at General Motors, MAN, BMW, and Volvo Cars, where she until recently served as the Chief Procurement Officer and on the management board. She is a senior advisor of H&Z Management Consulting and is a non-executive director on several company boards.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
NextSource Announces Appointment of Johnny Velloza as Interim Chief Operating Officer

NextSource Announces Appointment of Johnny Velloza as Interim Chief Operating Officer

NextSource Materials Inc. (TSX:NEXT)(OTCQB:NSRCF) ("NextSource" or the "Company") announces that Mr Robin Borley has resigned as Chief Operating Officer of the Company. NextSource is pleased to announce it has appointed Mr Johnny Velloza as Chief Operating Officer on an interim basis

Mr. Velloza has a wealth of technical and operating experience in the mining industry spanning 30 years during which he managed operational optimisation processes and large capital expansions across a range of commodities and in many jurisdictions. Mr. Velloza was previously Deputy CEO and COO of Gem Diamonds and CEO of Chemaf. Prior to this, he was with BHP Western Australia Iron Ore where, from 2013 to 2015, he was General Manager at Mining Area C, the largest iron ore mine in the BHP portfolio, leading a number of successful operational efficiency programs. He also acted as a Senior Exploration Manager in Zambia and in Chile for BHP from 2011-2013, Operations Manager at AngloGold Ashanti from 2009-2010 and held numerous managerial positions at De Beers from 2001-2009. Mr Velloza holds a Bachelor's degree in Mining Engineering from The University of Johannesburg and a Bachelor's degree in Business from The University of South Africa.

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
International Graphite

International Graphite Limited (ASX: IG6) – Trading Halt

Description

The securities of International Graphite Limited (‘IG6’) will be placed in trading halt at the request of IG6, pending it releasing an announcement. Unless ASX decides otherwise, the securities will remain in trading halt until the earlier of the commencement of normal trading on Wednesday, 24 April 2024 or when the announcement is released to the market.

Keep reading...Show less
International Graphite

WA Government Awards $6.5 Million to Australia’s First Downstream Graphite Plant

International Graphite Limited (ASX: IG6) is delighted to announce it has received an additional $6.5 million grant from the Western Australian Government to establish Australia’s first downstream graphite processing plant. The award builds on two years of establishment work and brings the Company’s total funding from the State’s Collie Just Transition Program to $8.5 million.

Keep reading...Show less
Altech Batteries

Altech – Launch of Share Purchase Plan

Altech Batteries Limited (Altech/the Company) (ASX: ATC and FRA: A3Y) is delighted to announce the opportunity for eligible shareholders of the Company to participate in an equity raising via a Share Purchase Plan (SPP) to raise up to $5 million.

Keep reading...Show less
International Graphite Managing Director and CEO Andrew Worland.

Strong Project Development Scenario for Springdale, International Graphite CEO Says

Purification testwork on graphite concentrates from International Graphite’s (ASX:IG6) Springdale graphite project achieved results ranging from 99.96 percent loss on ignition (LOI) to 99.97 percent LOI, which exceeds the purity requirements of major lithium-ion batteries. Andrew Worland, the company’s managing director and CEO, noted that the project has great attributes that make it stand out.

“It's got a significant resource ... so we'll be mining there for 50 (to) 60 years, and that's still with a lot of exploration potential for the asset,” he explained. "The other attributes of it that makes it unique and compelling for investors are its cost structure, and a lot of that has to do with Mother Nature, frankly. The mineralisation itself is a fine graphite, so we've got a very simple flotation process. ... We have one product, which means a simple flow sheet and lower capital cost."

International Graphite released key findings from its new Springdale-Collie integrated mine-to-market scoping study in January, saying they indicate a multi-decade operating life.

Keep reading...Show less

NMG Pays Accrued Interests and Grants Options

Nouveau Monde Graphite Inc. ("NMG" or the "Company") ( NYSE: NMG , TSX.V: NOU ) announces today the payment of accrued interests as part of a previously announced private placement announced by press release dated November 8, 2022 (the "2022 Private Placement").

Settlement of Accrued Interests

News Provided by Business Wire via QuoteMedia

Keep reading...Show less
NextSource Materials

NextSource Materials Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×