african diamond slot

Oza-1 Well Re-Entry Update and Board of Directors Changes

  • Re-entry and testing operations at the Oza-1 well continue to move forward steadily, leading the way to advancing Decklar's overall re-entry and development plans for the Oza Oil Field.
  • Pulling of existing tubing and 5 ½ inch casing from the Oza-1 wellbore has been successfully completed, and the 9 ⅝ inch casing was cleaned out.
  • A cement bond log has been completed to confirm integrity of the cement behind casing, and cased hole reservoir logs have been completed and confirm the characteristics of the individual zones to be tested.
  • Surface testing facilities are currently being installed, and it is anticipated that testing activities on the L2.6 zone are expected to commence early next week with the initial perforation and flow operations.
  • It is anticipated that initial oil production testing will then commence, with all crude oil test volumes produced being immediately exported and sold through the existing production facilities and pipelines to the Bonny Export Terminal.

Decklar Resources Inc. (DKL-TSX Venture) ( the "Company" or "Decklar") is pleased to announce an update to operations at the Oza-1 well re-entry at the Oza Oil Field in Nigeria, being performed by the Company's wholly owned Nigeria-based subsidiary, Decklar Petroleum Limited.

Progress at Oza-1 in Final Preparation for Well Testing Operations

Re-entry operations at the Oza-1 well site continue to progress with completion of critical initial work activities including pulling the existing tubing and the 5 ½ inch casing that was inside the 9 ⅝ inch casing. The 9 ⅝ inch casing has been scrapped and circulated clean and over to brine completion fluid and a cement bond log has been run to confirm the integrity of the wellbore and cement behind the casing. Cased hole reservoir logs have been completed and analyzed and confirm the expected characteristics of the zones targeted for testing. Surface testing facilities and equipment are currently being installed, and it is anticipated that testing of the L2.6 zone will commence early next week. Perforation operations will begin with a testing tubing string run with straddle packers to enable testing of the three isolated individual zones that will be tested. Production testing operations are planned for the three known oil-bearing zones (L2.2, L2.4 and L2.6), and each targeted zone will be production flow tested independently. All test volumes produced will be exported and sold through the existing production facilities and pipelines. Once testing of all three zones is completed, it is anticipated that a final dual-tubing string completion will be installed, and two of the three zones tested will be placed into production based upon successful testing. All necessary approvals and permits are in place for the well re-entry, testing and completion.

As previously announced, once the Oza-1 re-entry is complete, the drilling rig is then expected to be skidded on the same drill pad as the Oza-1 well to a new drilling slot and a horizontal development well will be drilled in one of the three zones tested in the Oza-1 well. It is anticipated that this well will then be placed on production upon successful testing and completion. The Oza-1 well and new horizontal development well are expected to generate significant production levels and generate cash flow in a short time frame utilizing the existing infrastructure in place. The Oza Oil Field development is planned to then continue with one or two more re-entries on other existing wells and an additional development drilling program with a potential for eight to ten wells to be drilled to achieve full field development. Additional early production and central processing facilities will be added as required to accommodate increased production levels from field development activities.

The Company anticipates that operations are on track for initial production testing to commence immediately following perforating and running the testing string. The Oza Oil Field has significant export and production capacity through processing facilities and infrastructure already in place and operational, which will allow for the immediate export and sale of crude oil from the Oza-1 well.

Decklar also continues to pursue and advance evaluations and negotiations for additional proven undeveloped oil and gas fields in Nigeria that have significant reserves and near-term production potential, including the recently announced acquisition in the Asaramatoru oil field.

Company Director Change

Decklar announces that Mr. Alan LeBis has resigned his position as a Director of the Company. Mr. LeBis has been instrumental to the early development of Decklar, and the Company thanks him for his valuable input and advice during his tenure as a member of the Board.

The Company is also pleased to announce the appointment of Mr. Bill Foose to the Decklar Board of Directors. Mr. Foose has over 35 years of experience working in the international oil and gas production and processing equipment sector. He held various positions with Barton Instruments before starting OilPro Production Equipment in 1997. OilPro was heavily involved in providing production equipment for domestic and international projects throughout Africa, the Middle East and other oil producing countries. Many of OilPro's African projects were centered around Nigeria.   Mr. Foose previously served on the board of Sunocean Energy.

Duncan Blount, CEO of Decklar, stated "As we commence production testing on the Oza-1 well, we are at an exciting transitional point at which the Company becomes an oil producer. Thanks to the infrastructure already in place, the flow test from the Oza-1 well will go directly into the pipeline to the Bonny Export Terminal to generate near-term cash flow. We look forward to ramping up production as we continue towards full field development at the Oza Field. The cash flow from the Oza Field will support Decklar's strategy of consolidating and re-establishing production of high-margin, proven undeveloped conventional oil fields in Nigeria including the recently announced Asaramatoru field."

For further information:

Duncan T. Blount
Chief Executive Officer Telephone: +1 305 890 6516
Email: dblount@decklarresources.com

David Halpin
Chief Financial Officer Telephone: +1 403 816 3029
Email: davidhalpin@decklarpetroleum.com

Investor Relations: info@decklarresources.com

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Language

Certain statements made and information contained herein constitute "forward-looking information" (within the meaning of applicable Canadian securities legislation). All statements in this news release, other than statements of historical facts, are forward-looking statements. Such statements and information (together, "forward looking statements") relate to future events or the Company's future performance, business prospects or opportunities.

All statements other than statements of historical fact may be forward-looking statements. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as "seek", "anticipate", "plan", "continue", "estimate", "expect, "may", "will", "project", "predict", "potential", "targeting", "intend", "could", "might", "should", "believe" and similar expressions) are not statements of historical fact and may be "forward-looking statements". Forward-looking statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements. The Company believes that the expectations reflected in those forward-looking statements are reasonable, but no assurance can be given that these expectations will prove to be correct and such forward-looking statements should not be unduly relied upon. The Company does not intend, and does not assume any obligation, to update these forward-looking statements, except as required by applicable laws. These forward-looking statements involve risks and uncertainties relating to, among other things, changes in oil prices, results of exploration and development activities, uninsured risks, regulatory changes, defects in title, availability of materials and equipment, timeliness of government or other regulatory approvals, actual performance of facilities, availability of financing on reasonable terms, availability of third party service providers, equipment and processes relative to specifications and expectations and unanticipated environmental impacts on operations. Actual results may differ materially from those expressed or implied by such forward-looking statements.

The Company provides no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. The Company does not assume the obligation to revise or update these forward-looking statements after the date of this document or to revise them to reflect the occurrence of future unanticipated events, except as may be required under applicable securities laws.


Primary Logo

News Provided by GlobeNewswire via QuoteMedia

The Conversation (0)
Elixir Energy

Nomgon Operations Update

Elixir Energy Limited (“Elixir” or the “Company”) is pleased to provide an operations update on the work currently underway in its 100% owned Nomgon IX Coal Bed Methane (CBM) Production Sharing Contract (PSC) in the South Gobi Basin, Mongolia.

Keep reading...Show less
Green Hydrogen Market Projected To Reach $30 Billion By 2030, Growing At 61.1% CAGR From 2023 To 2030

Green Hydrogen Market Projected To Reach $30 Billion By 2030, Growing At 61.1% CAGR From 2023 To 2030

FN Media Group News Commentary - The green hydrogen market is experiencing rapid growth, driven by global efforts to reduce carbon emissions and advancements in electrolysis and renewables. Government support through policies and investments is also boosting growth. Its versatility and scalability make green hydrogen a key player in the transition to sustainable energy. The market is even being propelled by its increasing use in fuel cell electric vehicles (FCEVs) and high-energy-intensive industries like steel and ammonia production, further driving demand and market expansion. A report from MarketsAndMarkets said: "The green hydrogen market was valued at USD 1.1 billion in 2023 and is projected to reach USD $30.6 Billion by 2030, growing at 61.1% CAGR from 2023 to 2030." The report said: "Hydrogen's versatility has expanded beyond its traditional role in fuel cells for electric vehicles, now encompassing the production of alternative fuels like ammonia, methanol, and synthetic liquids. These energy carriers are gaining prominence and are poised to drive future demand. In developing economies, green hydrogen presents a pathway to a low-carbon future, offering a nearly carbon-free fuel option for marine transportation, hydrogen fuel cells in electric vehicles (EVs), and industrial backup power. The diverse array of applications positions the green hydrogen sector as a lucrative venture with significant growth potential. The market for green hydrogen in vehicle fuel cells is rapidly evolving, providing the convenience of fossil fuels without the associated emissions." Active companies in the markets this week include Charbone Hydrogen Corporation (OTCQB: CHHYF) (TSXV: CH), Bloom Energy (NYSE: BE), NANO Nuclear Energy Inc. (NASDAQ: NNE), Plug Power Inc. (NASDAQ: PLUG), FuelCell Energy, Inc . (NASDAQ: FCEL).

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Charbone Hydrogene Double la Capacite De Son Electrolyseur De La Phase 1 Pour Alimenter La Production D'hydrogene Vert A L'usine De Sorel-Tracy Quebec

Charbone Hydrogene Double la Capacite De Son Electrolyseur De La Phase 1 Pour Alimenter La Production D'hydrogene Vert A L'usine De Sorel-Tracy Quebec

(TheNewswire)

Charbone Hydrogen Corporation

La Société prépare et améliore activement sa chaîne d'approvisionnement en électrolyseurs entièrement intégrés avec des capacités allant jusqu'à 2,5 MW, 5,0 MW et 10,0 MW pour tous ses projets

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less
BPH Energy Limited  Investor Webinar Presentation

BPH Energy Limited Investor Webinar Presentation

Perth, Australia (ABN Newswire) - BPH Energy Ltd (ASX:BPH) is pleased to announce its participation in the ShareCafe Small Cap "Hidden Gems" Webinar, to be held Friday 21st of June 2024 from 12:30pm AEST.

David Breeze - Executive Director will provide an overview of the Company, BPH is a diversified company holding investments in medical technology and resources. BPH holds a significant interest (36%) in unlisted oil and gas exploration company Advent Energy Ltd.

This webinar can be viewed live via Zoom and will provide viewers the opportunity to hear from, and engage with, a range of ASX-listed leading micro/mid cap companies.

To access further details of the event and to register at no cost, please visit:
https://www.abnnewswire.net/lnk/50L95CS4

A recorded copy of the webinar will be made available following the event



About BPH Energy Limited:

BPH Energy Limited (ASX:BPH) is an Australian Securities Exchange listed company developing biomedical research and technologies within Australian Universities and Hospital Institutes.

The company provides early stage funding, project management and commercialisation strategies for a direct collaboration, a spin out company or to secure a license.

BPH provides funding for commercial strategies for proof of concept, research and product development, whilst the institutional partner provides infrastructure and the core scientific expertise.

BPH currently partners with several academic institutions including The Harry Perkins Institute for Medical Research and Swinburne University of Technology (SUT).



Source:
BPH Energy Limited

News Provided by ABN Newswire via QuoteMedia

Keep reading...Show less
Elixir Energy

Elixir Adds New Taroom Acreage

Elixir Energy Limited (“Elixir” or the “Company”) is pleased to announce that it has been appointed as Preferred Tenderer in relation to a new exploration area in Queensland: PLR2023-1-7 (see map below). The area lies immediately adjacent to the Company’s Project Grandis in the Taroom Trough.

Keep reading...Show less
One gas powered vehicle and one electric vehicle.

From Fossil Fuels to Renewables: How the Energy Transition is Transforming the Oil and Gas Industry

The oil and gas sector has long been one of the Earth's largest and most valuable industries, but it's undergoing major changes to compete in the green energy transition and remain profitable.

At last year's COP28 summit, nations signaled a definitive shift away from fossil fuels, marking a potential "beginning of the end" for the era. While ambitious, the reality is more complex. Oil and gas aren't disappearing anytime soon — in fact, the industry is projected to rake in revenue of US$5.3 trillion in 2024, with daily consumption of 103 million barrels.

Indeed, petroleum remains the lifeblood of transportation systems, powering billions of vehicles, while natural gas heats a significant portion of the world's homes. At the same time, the industry's substantial environmental impact — accounting for 15 percent of energy-related emissions on a worldwide scale — cannot be ignored.

Keep reading...Show less

Latest Press Releases

Related News

×