Steppe Gold Commences Procurement of Long Lead Capital Items to Kick Start Phase 2 Fresh Rock Expansion

Steppe Gold Limited (TSX: STGO) ("Steppe Gold" or the "Company") is pleased to provide an update on its Phase 2 fresh rock expansion.

The Company has now commenced procurement of major capital items for the Phase 2 fresh rock expansion, targeting annual production of 150,000 oz Au Eq, at the 100%-owned ATO Gold Mine.

The first major purchase is a new crushing plant. The new crusher will have a crushing capacity of 1,000t/hr, more than three times the current crusher capacity, and it will fully support planned mining rates for the fresh rock phase where we have estimated throughput rates of 2-2.5m t.p.a. Construction of foundations and installation of the new crusher will start in early April and it is scheduled to be operational by July 2021. The new crushing unit comprises 2 primary jaw crushers and a cone crushing circuit.

Sourced from a leading international supplier, the crushing plant will cost around US$5m in total, inclusive of civil construction work, installation and testing. The crushing plant purchase is being partly financed by a $2.9m loan from a leading Mongolian commercial bank.

In conjunction with the start of procurement of long lead items the Company continues discussions with Mongolian and international lenders on a multi-tranche project debt facility to finance the Phase 2 expansion, expected to include a grinding circuit, a leach/CIP plant, and a flotation circuit. Metallurgical testing is progressing well with encouraging results and the bankable feasibility study is on track for completion in summer 2021.

Steppe Gold President and CEO, Mr Bataa Tumur-Ochir commented, "We are very pleased to kick start the capital procurement program for our Stage 2 fresh rock expansion at the ATO Gold Mine. We have prioritised the expansion of crushing capacity as it will also significantly accelerate stacking rates at the heap leach phase of the project and this is expected to support increased gold production in late 2021 and 2022. We have also started design work to expand the camp capacity and plans are advancing for value added power solutions. With a strong balance sheet and encouraging demand from lenders we expect to accelerate capital works on our Phase 2 expansion through the second half of 2021 as we target fresh rock production of 150,000 oz Au Eq starting in 2023. "

Steppe Gold Limited

Steppe Gold is Mongolia's premier precious metals company.

For Further information, please contact:

Bataa Tumur-Ochir, CEO and President

Shangri-La office, Suite 1201, Olympic street
19A, Sukhbaatar District 1,
Ulaanbaatar 14241, Mongolia
Tel: +976 7732 1914

Cautionary Note Regarding Forward-Looking Statements:

The above contains forward-looking statements that are subject to a number of known and unknown risks, uncertainties and other factors that may cause actual results to differ materially from those anticipated in our forward-looking statements. Factors that could cause such differences include: changes in world commodity markets, equity markets, costs and supply of materials relevant to the mining industry, change in government and changes to regulations affecting the mining industry. Forward-looking statements in this release include, among other things, statements regarding the trading of the Common Shares and business, economic, and political conditions in Mongolia. Although we believe the expectations reflected in our forward-looking statements are reasonable, results may vary, and we cannot guarantee future results, levels of activity, performance or achievements. We disclaim any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable law.

The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of the content of this news release.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/78404

News Provided by Newsfile via QuoteMedia

The Conversation (0)
Steppe Gold

Steppe Gold

Mongolia’s Premiere Precious Metals Company

Mongolia’s Premiere Precious Metals Company Keep Reading...
Jeff Clark, gold and silver bars.

Jeff Clark: Gold, Silver Going Higher, I'm "Aggressively Buying"

Jeff Clark, founder of the Gold Advisor, shares his thoughts on gold's fall below the US$4,000 per ounce level, emphasizing that he sees it as a buying opportunity. "The bottom line for me is ... we're going to go a lot higher, so that's why I'm investing," he said.Don't forget to follow us... Keep Reading...
Jeff Valks, mine site.

Jeff Valks: Investing in Juniors? Focus on This, Not the Gold Price

Jeff Valks, senior analyst at the Gold Advisor, gives his take on gold's fall below US$4,000 per ounce and whether it impacts his approach to investing in junior miners. "When I'm looking at the juniors and looking at the junior price tag, I try to tell people (to) separate the spot price from... Keep Reading...
Facade of New York Stock Exchange with tall columns and three flags below.

Barrick Names North American Gold Spinoff, Files NYSE IPO

Barrick Mining's (TSX:ABX,NYSE:B) North American gold spinoff now has a confirmed name and ticker. The miner announced on Tuesday (November 10) that it has named the new company American Barrick Gold, and that American Barrick has filed a registration statement with the US Securities and... Keep Reading...
Wooden blocks with letters "M&A" on chessboard with black and white chess pieces facing each other.

Altius to Add Copper, Lithium Royalties with TNR Gold Deal

Altius Minerals (TSX:ALS,OTCQX:ATUSF) has agreed to acquire TNR Gold (TSXV:TNR,OTCPL:TRRXF) to expand its copper and lithium exposure in Argentina, picking up royalties on McEwen Copper’s Los Azules project and Ganfeng Lithium's (HKEX:1772,OTCPL:GNENF) producing Mariana operation.“This... Keep Reading...
View from a helicopter departing HiView Resources’ and Omega Pacific’s 2026 exploration camp

Toodoggone: Gold, Silver and Copper District in British Columbia

BC's Toodoggone district is reemerging as a hub for gold, copper and silver.The Toodoggone is continuing to gain attention and renewed exploration. With a history of mining activity demonstrated by past-producing, ongoing development of advanced-stage projects and new discoveries, the district... Keep Reading...
iMetal Resources Files Gowganda West Technical Report

iMetal Resources Files Gowganda West Technical Report

iMetal Resources Inc. (TSXV: IMR) (OTCQB: IMRFF) (FSE: A7VA) ("iMetal" or the "Company") is pleased to announce the filing of a technical report (the "Report"), dated effective October 15, 2026, for its flagship Gowganda West gold project. The Report is authored by R. Tim Henneberry, P.Geo., a... Keep Reading...

Interactive Chart

Latest Press Releases

Related News