Mayfair Gold Provides Update on Project Work in the First Quarter of 2026 Advancing and Derisking the Fenn-Gib Gold Project

Mayfair Gold Provides Update on Project Work in the First Quarter of 2026 Advancing and Derisking the Fenn-Gib Gold Project

Mayfair Gold Corp. ("Mayfair", "Mayfair Gold", or the "Company") (NYSE American: MINE) (TSXV: MFG,OTC:MFGCF) is pleased to provide this update progress achieved for the first quarter 2026, and highlight key work streams for the remainder of 2026 at the Fenn-Gib Gold Project in Northern Ontario .

"The progress achieved in the first quarter reflects the disciplined, methodical approach we are taking as we advance and derisk the Fenn-Gib Gold project through the permitting process toward development. Each workstream is moving forward with clarity and purpose, and as the team grows, we continue to deliver the technical foundations required for a successful build," said Nick Campbell, President and CEO. "We look forward to maintaining this momentum as we enter the next phase of engineering, environmental assessment, and regulatory and stakeholder engagement."

Drew Anwyll, P.Eng., Chief Operating Officer, added: "We entered 2026 with a clear execution plan, and the progress achieved this quarter reflects both the strength of that approach and the quality and commitment of the team advancing the work. Multiple critical‑path activities are progressing in parallel, supported by a highly capable group focused on disciplined delivery. This work will allow us to maintain schedule confidence as we move toward detailed engineering later this year, and progress permitting and regulatory approvals. Our objective remains clear: to advance the Project efficiently targeting a construction decision in 2028, positioning us well ahead of our peers."

The aspects of the work advance in Q1 2026 include the following:

Compilation of Environmental Baseline Study work

Throughout Q1 2026, the Company advanced the integration and interpretation of the multi‑year environmental baseline studies initiated in 2023. Work this quarter focused on advancing and consolidating studies concerning fish and fish habitat, hydrology, hydrogeology, geochemistry, wildlife, and vegetation into technical packages to support the upcoming application into Ontario's One Project, One Process ("1P1P") framework and advancement of the Environmental Assessment ("EA") processes with the Province of Ontario.

Notification of Project Status

The Company submitted the Notification of Project Status ("NPS") during the first quarter signalling the intent to advance the project into production and is now awaiting formal guidance and next‑step requirements from the Ministry of Energy and Mines ("MEM"). Following the receipt of MEM's review of the NPS, their feedback will be integrated into the Company's permitting strategy to help align upcoming technical, environmental, and indigenous engagement workstreams with the identified communities.

Environmental Assessment

In the first quarter, the Company awarded the EA and permitting mandate to Egis Canada Ltd. ("Egis"), previously operating as Ecometrix Incorporated, for the Project. Building on the consolidated baseline interpretations completed to date, Egis will lead the preparation of the Ontario provincial EA as the Company initiates formal environmental approval activities later in 2026. This work will include the development of regulatory submissions, continued engagement with Indigenous communities and stakeholders, and the preparation of discipline‑specific technical reports.

Highway 101 Realignment

Work commenced in late Q1 on the environmental assessment process for the proposed Highway 101 realignment. TBT Engineering has initiated early coordination with the Ministry of Transportation of Ontario ("MTO") to confirm process requirements and advance initial scoping. Upcoming work will include route evaluation, environmental and geotechnical field studies, and continued collaboration with MTO to progress the preferred alignment. 

Advancement of Site Investigations and Site Drilling

During the quarter, the Company advanced expanded site investigation programs. Geotechnical fieldwork resumed in early 2026, advancing work initiated in 2025, for the proposed tailings storage facility ("TSF"), site infrastructure areas, and the process plant. In parallel, condemnation drilling commenced across priority infrastructure zones to confirm the absence of mineralization and delineate the final site layout. 

The Company also advanced pump testing activities to strengthen the understanding of groundwater conditions across the project area. These tests provide information on sub-surface water characteristics, hydraulic conductivity, and groundwater flow responses under sustained pumping that is vital to ongoing site engineering. The results will be incorporated into updated hydrogeological models to refine predictions of pit dewatering requirements, assess potential interactions with nearby water bodies, and support EA and permitting submissions.

Front-End Engineering and Design ("FEED") Initiated with Ausenco

In the first quarter, the Company commenced Front-End Engineering and Design (FEED) with Ausenco Engineering for the planned 4,800 tpd processing facility. This phase of work includes completing applicable financial trade‑off studies, advancing Process Design Criteria (PDC) and Piping and Instrumentation Diagrams (P&ID) to formalize Project design and will support advancing into detailed engineering in the second half of 2026. Q1 FEED activities focused on refining the comminution circuit and flotation layouts, integrating outcomes from third‑party reviews, and establishing the engineering basis to support continued advancement of the plant design.

Next Steps

The first quarter of 2026 also allowed the Team to advance the planning and coordination of the following work:

Metallurgical Testing

To support comminution circuit design and establish additional data for rock competency characterization, large‑diameter diamond drill core will be collected to generate expanded A×b rock hardness data. These results will refine parameters and inform equipment sizing and energy requirements for the operating plant. In parallel, follow‑on work from the tailings settlement testing program completed in Q1 will be undertaken to better define the settled density of tailings material within the TSF.

Advancing the Mineral Resource Estimate drilling program

In the first quarter, all remaining assays from the 2025 Mineral Resource Estimate (MRE) confirmation drilling program were received. With the full 2025 MRE confirmation dataset now complete, the geology team, together with the Mineral Resource Qualified Person, are advancing the development of an updated localized model and evaluation of preliminary ore block designs within the area drilled. Upon completion, the updated local model will be compared against the MRE used in the Pre‑Feasibility Study (PFS) to assess changes in grade distribution, geological continuity, and provide insight into any variability on future mine planning and operational predictability.

Ongoing Site Investigations and Geotechnical Programs

Site investigation activities will continue through the second quarter, including additional geotechnical drilling, test pitting, and material characterization across the TSF, plant site, and infrastructure locations. These programs will further refine foundation design parameters and support the advancement into the detailed engineering phase.

Power Supply to Site

The Company along with TWD Engineering are advancing work to define the preferred power‑to‑site solution, including evaluation of transmission routing and supply voltage, interconnection requirements, and technical specifications. Engagement with the relevant utilities and regulatory bodies including Hydro One Network ("HONI") and the Independent Electricity System Operator ("IESO") will continue as the Company progresses toward a finalized power supply strategy to support the Project.

Open Pit Geotechnical Drilling

Additional open pit geotechnical drilling is to commence in the third quarter. Initial geotechnical work completed in 2023 supported the open pit designs developed for the PFS. Building upon this foundation, the program will gather supplementary structural, geomechanical, and hydrogeological data to enhance the accuracy of open pit slope designs and facilitate pit optimization and operational stability evaluations. 

Mayfair is growing the core team to advance Fenn-Gib and support the ongoing initiatives to derisk the Project, support the Provincial permitting process and make preparations in advance of the start of construction.

Advertising Service Agreement

The Company also announces it has entered into a service agreement with Native Ads Inc. ("Native Ads") in connection with a digital advertising campaign. Native Ads will provide the Company with services which include sponsored articles, media buying, content distribution services and ad campaign analytics. Pursuant to the agreement, the company has agreed to pay US$172,000 to facilitate the program. The digital advertising campaign is planned for the 12-month term of the agreement, or until budget exhaustion. The majority of the campaign budget will be disbursed by Native Ads to satisfy its obligations under the agreement. Native Ads is led by Jon Malach and is an arms-length Delaware Corp. with a registered office located in New York. Native Ads has no present interest, directly or indirectly, in the securities of the Company.

About Mayfair Gold

Mayfair Gold is a Canadian gold development stage company focused on advancing the 100% controlled Fenn-Gib Project in the Timmins region of Northern Ontario. The PFS outlines the potential to develop Fenn-Gib into a new Canadian gold producer for initial development capital of C$450 million, with a base case payback period of 2.7 years and cumulative free cash flow of $896 million over the first six years of production based on a US$3,100/oz gold price. The Company is advancing permitting activities, detailed engineering and stakeholder engagement with the goal of starting construction in 2028 with initial production in 2030.

The content of this news release has been reviewed on behalf of the Company and approved by Drew Anwyll, P.Eng., Chief Operating Officer of Mayfair, a QP as defined in NI 43-101.

Cautionary Note Regarding Forward-Looking Information

This news release contains certain forward-looking information and forward-looking statements within the meaning of applicable securities legislation (collectively "forward-looking Information"). The use of the words "will" and "expected" and similar expressions are intended to identify forward-looking information. This information includes statements regarding the scope, timing and expected outcomes from future workstreams. Although Mayfair Gold believes that the expectations reflected in such forward-looking statements and/or information are reasonable, readers are cautioned that actual results may vary from the forward-looking information. The Company has based these forward-looking statements and information on the Company's current expectations and assumptions about future events. This information also involves known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking information, including the risks, uncertainties and other factors identified in the annual information form of the Company for the year ended December 31, 2025, available at www.sedarplus.ca. Furthermore, the forward-looking statements contained in this news release are made as at the date of this news release and Mayfair does not undertake any obligation to publicly update or revise any of these forward-looking statements except as may be required by applicable securities laws.

Neither the TSX Venture Exchange ("TSXV") nor its Regulation Services Provider (as that term is defined in the policies of the TSXV) accepts responsibility for the adequacy or accuracy of this news release.

Cision View original content to download multimedia:https://www.prnewswire.com/news-releases/mayfair-gold-provides-update-on-project-work-in-the-first-quarter-of-2026-advancing-and-derisking-the-fenn-gib-gold-project-302754876.html

SOURCE Mayfair Gold Corp.

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/April2026/27/c0682.html

News Provided by Canada Newswire via QuoteMedia

MFG:CC
Mayfair Gold Corp.

Mayfair Gold Corp. Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
Mayfair Gold (TSXV:MFG)

Mayfair Gold Corp.

Prudently advancing the Fenn-Gib gold project in the Timmins gold district of Ontario

Prudently advancing the Fenn-Gib gold project in the Timmins gold district of Ontario Keep Reading...

Investor Insight

Mayfair Gold is progressing its 100 percent-owned Fenn-Gib gold project toward production, with a development plan anchored by a robust 2026 pre-feasibility study (PFS). The company’s strategy emphasizes a smaller scale mine designed to accelerate permitting through Ontario’s One Project One Process platform and exploit near surface high-margin ounces in a capital efficient manner. The PFS only corresponds to 24 percent of the indicated gold resource leaving meaningful optionality for long term growth coupled with exploration upside across a broader land package.

Overview

Mayfair Gold (TSXV:MFG,NYSE American:MINE) is a development-stage company with the primary objective of advancing the Fenn-Gib gold project — a large, bulk-tonnage open-pit deposit located in one of Canada’s most prolific gold districts. The company’s technical team is executing on provincial permitting, Indigenous consultation, engineering and ongoing exploration to expand mineralization beyond the current pit constraints.

Mayfair Gold Fenn Gib Gold project location


Mayfair Gold’s flagship Fenn-Gib gold project is located within the established Timmins Gold District in Ontario, which has produced more than 100 million ounces of gold historically.

The PFS, prepared in accordance with NI 43-101 standards and filed in January 2026, outlines a base-case economic model with an after-tax NPV (5 percent) of C$652 million and an IRR of 24 percent, using conservative gold prices, and demonstrates rapid payback potential. Under a spot price scenario, project economics improve markedly, underscoring the asset’s leverage to higher gold prices. With over $200 million in annual free cash flow once in operation the company will have a robust source of capital to fund growth initiatives.

Company Highlights

  • Robust Pre-feasibility Study: The 2026 PFS highlights compelling returns on a modest initial throughput design while leveraging a large resource base.
  • High-grade Early Focus: The staged plan targets higher-grade, near-surface material to optimize permitting timelines, construction risk, financing, and ultimately accelerate value capture.
  • Strategic Location: Fenn-Gib sits on the highly prospective Timmins Gold District, Ontario — a tier-one mining jurisdiction with established infrastructure and a long history of mining-related activity and supportive communities.
  • Strong Financial Backing: The company has a committed shareholder base, including Muddy Waters, Heeney Capital, Oaktree and Nokomis. With a tight share structure and strong Insider ownership of 36% there is clear alignment for long-term shareholder value creation.
  • Exploration Optionality: Mineralization at Fenn-Gib remains open at depth and along strike, with multiple underexplored targets identified across the property. This includes a Southern Block that has not been explored but sits directly on the prolific Porcupine-Destor fault.
  • Long-term optionality: With a truncated timeline to production the company will be in an advantageous spot for growth initiatives that can be funded with free cash flow.
  • CEO Drew Anwyll is an experienced mine builder; he successfully permitted the Marathon PGM project in Ontario and was a senior executive during the construction, commissioning and start-up of Detour Lake, Canada’s largest gold mine.

Key Project

Fenn-Gib Gold Project

Fenn-Gib is Mayfair’s flagship asset, encompassing a significant indicated mineral resource of 181.3 million tonnes grading 0.74 g/t gold for 4.3 million contained ounces, and additional inferred ounces. The project benefits from excellent access via Highway 101 and proximity to regional mining services.

The 2026 PFS centers on a 4,800 tonnes-per-day open-pit operation designed to process approximately 1.04 million ounces of gold, representing 24 percent of the total resource and reflecting a conservative, execution-oriented approach. Highlights from the study include:

  • After-tax NPV (5 percent) of C$652 million and IRR of 24 percent at a base case gold price of US$3,100/oz.
  • After-tax NPV of C$1.37 billion and IRR of 38 percent at current spot gold prices.
    2.7-year payback period on initial capital costs under the base case (1.7 year payback at January 2026 prices)

Mayfair Gold 2026 Pre-feasibility Study Highlights

Mayfair Gold’s late-2025 grade control program at the Fenn-Gib Project confirmed about 1 million tonnes of ore-grade material, equal to roughly 25% of Phase 1’s planned design and consistent with probable reserves outlined in the PFS. Ongoing 2026 activities include encompassing process plant and infrastructure design optimization, evaluating grade control and condemnation drilling results. The company said it is focused on taking a practical path toward construction and production for Fenn-Gib in an expedited timeframe.

In addition to economic studies and active dialogue with Indigenous stakeholders, the company has executed engineering contracts with industry providers to support mine planning, processing design, environmental baseline work, and tailings/water management — positioning the project for upcoming acceptance into the 1P1P permitting framework in 2026 and potential construction decision in 2028.

Exploration Potential

Beyond the defined pit shell, Fenn-Gib hosts multiple zones including the Main Zone, Deformation Zone, and Footwall Zone, with geological continuity extending along strike and at depth. Newly identified targets such as the Southern Block along the Porcupine Destor-Fault present opportunities for future discovery drilling and resource expansion.

Management Team

Drew Anwyll — Chief Executive Officer

Drew Anwyll is a professional engineer with over 30 years of global mining experience in both project and operations leadership. His background includes senior technical and operating roles at Generation Mining, Detour Gold, Barrick Gold and Placer Dome. Anwyll’s track record includes leadership through permitting, construction, commissioning, and operational phases, anchoring Mayfair’s operational planning and execution.

Kevin Annett — Chief Financial Officer

Kevin Annett is a seasoned mining finance executive with over 15 years of experience spanning project construction, operations, and corporate leadership. He most recently served as Chief Financial Officer, North America at Barrick Mining Corporation, where he led financial strategy, planning, and governance for the company's largest region, with a strong focus on disciplined capital allocation and value creation. Earlier in his career, he held progressively senior roles across Barrick and Detour Gold.

Desmond Tranquilla – Chief Project Officer

Desmond Tranquilla is a seasoned mining executive and professional engineer with over 35 years of experience in project development, construction, operations, and strategic leadership. He previously served as Vice President, Projects at Canada Nickel Company, where he made significant contributions towards advancing the Crawford Nickel Project. He has also led significant potash expansions in Saskatchewan, alongside major developments such as Vale's C$1.6 billion Atmospheric Emission Reduction Project and the C$1.5 billion Detour Lake Mine Project.

Ruben Wallin – Senior Vice President, Sustainability

Ruben Wallin has over 30 years of experience in mining operations, environmental stewardship, permitting, government relations and community engagement. He recently served as Vice President, Sustainability at Generation Mining, where he played a key role in advancing the environmental approvals for the Marathon Project. Combining technical engineering education with corporate and site-level experience on major mining projects and operations, he also held positions with companies such as Placer Dome, Osisko and Detour Gold.

Zayem Lakhani — Vice President, Corporate Development and Strategy

Zayem Lakhani brings more than 17 years of expertise in investment management, equity research, and corporate development. Before joining Mayfair, he served as portfolio manager and head of Canadian equities at HSBC Global Asset Management, where he oversaw the investment process for approximately $4 billion in capital across diverse strategies. Lakhani brings a unique network and an investor’s perspective to help position the company’s story.

Brixton Metals Announces Closing of Non-Brokered Private Placement for Gross Proceeds of $1 Million

Brixton Metals Announces Closing of Non-Brokered Private Placement for Gross Proceeds of $1 Million

Not for distribution to United States Newswire Services or for dissemination in the United States Brixton Metals Corporation (TSX- V: BBB, OTCQX: BBBXF) (the "Company" or "Brixton") is pleased to announce that it has closed a non-brokered private placement offering (the "Offering") of national... Keep Reading...
Cerrado Gold Announces Third Quarter 2026 Financial Results

Cerrado Gold Announces Third Quarter 2026 Financial Results

Highlights: Gold equivalent production of 16,985 Gold Equivalent Ounces ("GEO") at AISC of $1,546/oz Au during Q3 2026; Adjusted EBITDA of $33.8 million for Q3 2026 and $90.8 million year-to-date Earnings of US$0.04 per basic share outstanding in Q3 2026 and US$0.16 per share Year to Date,... Keep Reading...
RED MOUNTAIN FUNDING TO ACCELERATE THE ARMIDALE PROJECT

RED MOUNTAIN FUNDING TO ACCELERATE THE ARMIDALE PROJECT

Red Mountain Mining (RMX:AU) has announced RED MOUNTAIN FUNDING TO ACCELERATE THE ARMIDALE PROJECTDownload the PDF here. Keep Reading...
Asara signs binding term sheet to acquire Siguiri Gold Corp

Asara signs binding term sheet to acquire Siguiri Gold Corp

Asara Resources (AS1:AU) has announced Asara signs binding term sheet to acquire Siguiri Gold CorpDownload the PDF here. Keep Reading...
Aurum hits thick gold intercepts at Boundiali BST1

Aurum hits thick gold intercepts at Boundiali BST1

Aurum Resources (AUE:AU) has announced Aurum hits thick gold intercepts at Boundiali BST1Download the PDF here. Keep Reading...
Omega Pacific Upsizes LIFE Offering to $1.5 Million

Omega Pacific Upsizes LIFE Offering to $1.5 Million

Omega Pacific Resources Ltd. (CSE: OMGA) (OTCQB: OMGPF) (FSE: Q0F) ("Omega Pacific" or the "Company") is pleased to announce that, in response to investor demand, it has increased the maximum size of its previously announced non-brokered private placement offering (the "LIFE Offering") of Units... Keep Reading...
Mayfair Gold Corp.

Mayfair Gold Corp. Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Interactive Chart

Latest Press Releases

Related News