Precious Metals

MAG Silver Corp. (TSX NYSE American: MAG) ("MAG" or the "Company") is pleased to report second quarter (Q2) production of underground development and stope material from the Juanicipio Project (56% 44% Fresnillo plc ("Fresnillo") and MAG, respectively). As reported to MAG by the project operator Fresnillo, on a 100% basis, 154,069 tonnes of mineralized material from both underground development and initial stopes were processed during the three months ended June 30, 2022 at an average head grade of 567 silver grams per tonne.

Total Juanicipio production for the quarter, based on provisional estimates before offtake agreement adjustments, totaled 2,372,140 silver ounces and 5,609 gold ounces (MAG's attributable 44% interest: 1,043,742 silver ounces and 2,468 gold ounces). MAG expects to release its full financial and operational results on August 15, 2022.

Mineralized material from Juanicipio continues to be processed through the nearby Saucito and Fresnillo beneficiation plants (100% owned by Fresnillo). Approximately 60% of the tonnes processed in Q2 were processed at the Saucito beneficiation plant. The Saucito plant flowsheet better resembles that of the Juanicipio plant and provides valuable metallurgical information as we look forward to production commencement at Juanicipio. The lead (silver-rich) and zinc concentrates produced are treated at market terms under off-take agreements with Met-Mex Peñoles, S.A. de C.V. in Torreón, Mexico.

The revenue from current production, net of processing and treatment charges, is being used to offset initial project capital and sustaining capital cash requirements, reducing the need for capital contributions from Fresnillo and MAG. At the end of the quarter Juanicipio held cash balances of $37m up from $18m at the end of Q1.

Construction of the Juanicipio plant was delivered by Fresnillo on schedule during the fourth quarter of 2021. However, as previously disclosed, the mill commissioning timeline was extended until tie-in approval to the national power grid is obtained from the federal power authorities (see Press Release December 27, 2021). We are pleased to report good progress on the required power system shutdowns to enable the final tie-in of the Juanicipio sub-station to the national power grid, and commencement of electrical commissioning of the plant is expected to occur in the coming weeks.

"We are delighted with the progress reported by the Fresnillo team on the electricity shutdowns that pave the way for the final tie-in to the power grid. Commissioning of the new electrical system is expected over the next few weeks followed by the commissioning of the grinding mills. The rest of the process plant has been fully commissioned and awaits the energizing of the mills. Target ramp-up to 85-90% of nameplate capacity by year end remains within reach," said George Paspalas, MAG's President and CEO. "With over 100,000 tonnes of material stockpiled and continued advancement of underground development, the operations team are well positioned to deliver the first concentrates produced from the Juanicipio facility in H2 2022."

Qualified Person: Dr. Peter Megaw, Ph.D., C.P.G., has acted as the Qualified Person as defined in National Instrument 43-101 for this disclosure and supervised the preparation of the technical information in this release. Dr. Megaw has a Ph.D. in geology and more than 40 years of relevant experience focused on ore deposit exploration worldwide. He is a Certified Professional Geologist (CPG 10227) by the American Institute of Professional Geologists and an Arizona Registered Geologist (ARG 21613). Dr. Megaw is not independent as he is Chief Exploration Officer and a Shareholder of MAG.

About MAG Silver Corp. ( www.magsilver.com )

MAG Silver Corp. is a Canadian development and exploration company focused on becoming a top-tier primary silver mining company by exploring and advancing high-grade, district scale, silver-dominant projects in the Americas. Its principal focus and asset is the Juanicipio Project (44%), being developed with Fresnillo Plc (56%), the operator. The project is located in the Fresnillo Silver Trend in Mexico, the world's premier silver mining camp, where the operator is currently developing an underground mine and constructing a 4,000 tonnes per day processing plant. Underground mine production of mineralized development material commenced in Q3 2020, and an expanded exploration program is in place targeting multiple highly prospective targets at Juanicipio. MAG is also executing a multi-phase exploration program at the Deer Trail 100% earn-in Project in Utah and has recently acquired the Larder Project located in the historically prolific Abitibi region of Canada.

Neither the Toronto Stock Exchange nor the NYSE American has reviewed or accepted responsibility for the accuracy or adequacy of this press release, which has been prepared by management.

This release includes certain statements that may be deemed to be "forward-looking statements" within the meaning of the US Private Securities Litigation Reform Act of 1995. All statements in this release, other than statements of historical facts are forward looking statements, including statements that address our expectations with respect to the timing and success of plant pre-commissioning and commissioning activities, processing rates of development materials, future mineral production, and events or developments. Forward-looking statements are often, but not always, identified by the use of words such as "seek", "anticipate", "plan", "continue", "estimate", "expect", "may", "will", "project", "predict", "potential", "targeting", "intend", "could", "might", "should", "believe" and similar expressions. These statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements. Although MAG believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include, but are not limited to, impacts (both direct and indirect) of COVID-19, timing of receipt of required permits, changes in applicable laws, changes in commodities prices, changes in mineral production performance, exploitation and exploration successes, continued availability of capital and financing, and general economic, market or business conditions, political risk, currency risk and capital cost inflation. In addition, forward-looking statements are subject to various risks, including that data is incomplete and considerable additional work will be required to complete further evaluation, including but not limited to drilling, engineering and socio-economic studies and investment. The reader is referred to the MAG Silver's filings with the SEC and Canadian securities regulators for disclosure regarding these and other risk factors. There is no certainty that any forward-looking statement will come to pass, and investors should not place undue reliance upon forward-looking statements.

Please Note: Investors are urged to consider closely the disclosures in MAG's annual and quarterly reports and other public filings, accessible through the Internet at www.sedar.com and www.sec.gov .

LEI: 254900LGL904N7F3EL14


For further information on behalf of MAG Silver Corp. Contact Michael J. Curlook, VP Investor Relations and Communications Phone: (604) 630-1399 Toll Free: (866) 630-1399 Website: www.magsilver.com Email: info@magsilver.com

Primary Logo

News Provided by GlobeNewswire via QuoteMedia

MAG:CA,MAG
Galena Mining

Abra Construction 78% Complete at End of July

GALENA MINING LTD. (“Galena” or the “Company”) (ASX: G1A) is pleased to announce that the construction progress at its Abra Base Metals Mine (“Abra” or the “Project”) has reached 78% complete as of 31 July 2022. New milestones have been achieved with the commencement of the installation of the ball-mill components and total underground development passing 2km in early August.

Keep reading...Show less

MAG Silver Reports Second Quarter Financial Results

MAG Silver Corp. (TSX NYSE American: MAG) ("MAG", or the "Company") announces the Company's unaudited financial results for the three and six months ended June 30, 2022.  For details of the unaudited condensed interim consolidated financial statements and Management's Discussion and Analysis for the three and six months ended June 30, 2022, please see the Company's filings on SEDAR ( www.sedar.com ) or on EDGAR ( www.sec.gov ).

All amounts herein are reported in $000s of United States dollars ("US$") unless otherwise specified.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less

SILVERCORP REPORTS ADJUSTED EARNINGS OF $13.5 MILLION, $0.08 PER SHARE, AND CASH FLOW FROM OPERATIONS OF $40.2 MILLION FOR Q1 FISCAL 2023

Trading Symbol: TSX: SVM
NYSE AMERICAN: SVM

Silvercorp Metals Inc. ("Silvercorp" or the "Company") (TSX: SVM) (NYSE American: SVM) reported its financial and operating results for the three months ended June 30, 2022 ("Q1 Fiscal 2023"). All amounts are expressed in US Dollars, and figures may not add due to rounding.

HIGHLIGHTS FOR Q1 FISCAL 2023
  • Mined 300,104 tonnes of ore and milled 298,176 tonnes of ore, up 30% and 23% compared to the prior year quarter;

  • Sold approximately 1.9 million ounces of silver, 1,100 ounces of gold, 19.1 million pounds of lead, and 6.9 million pounds of zinc, representing increases of 17%, 10%, and 14% in silver, gold and lead sold, and a decrease of 5% in zinc sold, compared to the prior year quarter;

  • Revenue of $63.6 million , up 8% compared to $58.8 million in the prior year quarter;

  • Net income attributable to equity shareholders of $10.2 million , or $0.06 per share, compared to $12.2 million , or $0.07 per share in the prior year quarter;

  • Adjusted earnings attributable to equity shareholders of $13.5 million , or $0.08 per share, compared to $15.8 million , or $0.09 per share in the prior year quarter. The adjustments were made to remove impacts from impairment charges, share-based compensation, foreign exchange, mark-to-market equity investments, and the share of associates' operating results.

  • Cash flow from operations of $40.2 million , up 10% or $3.7 million compared to $36.5 million in the prior year quarter;

  • Cash cost per ounce of silver, net of by-product credits, of negative $1.57 compared to negative $1.43 in the prior year quarter;

  • All-in sustaining cost per ounce of silver, net of by-product credits, of $9.25 compared to $7.46 in the prior year quarter;

  • Spent and capitalized $3.1 million on exploration drilling, $9.7 million on underground development and $1.2 million on the construction of the new mill and tailings storage facility;

  • Paid $2.2 million of dividends to the Company's shareholders;

  • Spent $0.9 million to buy back 334,990 common shares of the Company under its Normal Course Issuer Bid, and subsequent to the quarter, bought back further 404,970 common shares of the Company for $1.0 million ; and

  • Strong balance sheet with $215.8 million in cash and cash equivalents and short-term investments, up $2.9 million or 1% compared to $212.9 million as at March 31, 2022 . The Company holds further equity investment portfolio in associates and other companies with a total market value of $147.4 million as of June 30, 2022 .

CONSOLIDATED FINANCIAL RESULTS

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less

SilverCrest Reports Q2, 2022 Financial Results

TSX: SIL | NYSE American: SILV

 SilverCrest Metals Inc. ("SilverCrest" or the "Company") is pleased to report the Company's unaudited financial results for the second quarter of 2022 ("Q2, 2022"). The unaudited condensed consolidated interim financial statements and management's discussion and analysis ("MD&A") for the three and six months ended June 30, 2022 are available under the Company's SEDAR profile on www.sedar.com or on SilverCrest's website www.silvercrestmetals.com . All amounts herein are presented in United States Dollars, unless otherwise stated.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Falcon Gold Corp

Falcon Gold Closes $300,000 Private Placement

FALCON GOLD CORP. (FG: TSX-V), (3FA: GR), (FGLDF: OTCQB); ("Falcon" or the "Company") announces the Company has closed its non-brokered private placement previously announced August 10th, 2022. and has issued 4,000,000 common shares for proceeds of $ 300,000. Each Unit priced at 7.5 cents consists of one common share and one common share purchase warrant priced at 10 cents for a 36-month term. The shares will be subject to a standard 4 month hold period (TSX.V Policy) no finders fees have been paid. Proceeds from the offering are for general working capital purposes and exploration expenditures.

The closing of the Private Placement is subject to TSX Venture Exchange approval.

Keep reading...Show less

Endeavour Silver - Withholding Sales for Inventory Impacts Quarterly Results

Second quarter 2022 results. Endeavour generated a second quarter adjusted net loss of $4.3 million, or $(0.02) per share, compared to adjusted net income of $2.4 million, or $0.01 per share, during the prior year period. We had projected a loss of $5.6 million, or $(0.03) per share. Including changes in the fair value of investments, the company reported a loss of $(0.07) per share. Endeavour retained inventory for future sale at higher prices. At quarter end, Endeavour held 1,399,356 ounces of silver and 2,580 ounces of gold in bullion inventory and 12,408 ounces of silver and 587 ounces of gold in concentrate inventory. Updating estimates. Endeavour increased its production forecast to a range of 7.6 million to 8.0 million from 6.7 million to 7.6 million silver equivalent ounces to reflect higher than planned ore-grades along the El Curso ore body at Guanacevi. While the company is experiencing cost inflation, cash and all-in sustaining costs expectations remain $9.00 to $10.00 per ounce and $20.00 to $21.00 per ounce, respectively. We increased our 2022 EPS estimate to $0.11 from $0.10 and reduced our 2023 estimate to $0.13 from $0.15 to reflect modestly lower commodity prices and margin. Read More >>