Hudbay Announces Third Quarter 2023 Results

 

Hudbay Minerals Inc. ("Hudbay" or the "company") (TSX, NYSE:HBM) today released its third quarter 2023 financial results. All amounts are in U.S. dollars, unless otherwise noted.

 

  Delivering Record Third Quarter Operating and Financial Results  

 
  • Achieved record quarterly revenue of $480.5 million with strong consolidated copper production of 41,964 tonnes and record quarterly consolidated gold production of 101,417 ounces as higher grades from the Pampacancha deposit in Peru and the Lalor mine in Manitoba were realized together with the first full quarter of Copper Mountain production for Hudbay.
  •  
  • Reaffirmed full year 2023 production, cash cost and sustaining cash cost guidance for Hudbay's Peru and Manitoba operations. Issued Copper Mountain production, cash cost and capital expenditure guidance for the period since completion of the acquisition on June 20, 2023. Hudbay consolidated production, cash cost and capital guidance updated to include Copper Mountain contributions in 2023.
  •  
  • Delivered a significant increase in operating cash flow before change in non-cash working capital of $182.0 million in the third quarter, compared to $55.9 million in the second quarter.
  •  
  • Consolidated cash cost and sustaining cash cost per pound of copper produced, net of by-product credits 1 , in the third quarter, were $1.10 and $1.89, respectively, and both metrics improved by 31% compared to the second quarter.
  •  
  • Peru operations benefitted from significantly higher grades at the Pampacancha pit during the third quarter of 2023, resulting in 29,081 tonnes of copper production and 40,596 ounces of gold production in the third quarter. Peru cash cost per pound of copper produced, net of by-product credits i , in the third quarter declined to $0.83, in line with quarterly cadence expectations. Pampacancha began delivering on anticipated higher copper production and precious metal by-product credits in the third quarter. This strong performance is expected to continue in the fourth quarter, enabling the Peru operations to meet all metal production and cost guidance for 2023.
  •  
  • Manitoba operations produced 56,213 ounces of gold in the third quarter as production focused on mining the higher gold and copper grade zones at Lalor. Mill recoveries also increased meaningfully compared to the prior period as a result of changes to optimize the circuits at the Stall and New Britannia mills. Manitoba cash cost per ounce of gold produced, net of by-product credits i , was $670 during the third quarter and full year cash costs are expected to be within the annual guidance range.
  •  
  • First full quarter of Copper Mountain operations produced 9,303 tonnes of copper at a cash cost per pound of copper produced, net of by-product credits i , of $2.67. With integration activities well-advanced, continuous improvement methodologies applied at Hudbay's Constancia operations have started to be implemented in the Copper Mountain mill as the company continues its operational stabilization plans.
  •  
  • Third quarter net earnings and earnings per share were $45.5 million and $0.13, respectively. After adjusting for a non-cash gain of $32.4 million related to a quarterly revaluation of Hudbay's closed site environmental reclamation provision, among other items, third quarter adjusted earnings i per share were $0.07.
  •  
  • Cash and cash equivalents increased by $65.5 million to $245.2 million during the third quarter due to strong operating cash flows bolstered by higher copper and gold sales volumes from mining the high-grade zones of the Pampacancha deposit and higher gold and copper grade zones at Lalor.
  •  
  • Revenue, earnings and operating cash flow would have further benefitted from the sale of approximately 20,000 ounces of consolidated gold production that remained unsold at the end of the third quarter.
  •  

  Generating Free Cash Flow with Increased Production and Continued Financial Discipline  

 
  • Executed on planned higher production levels and achieved continued operating and capital cost efficiencies to generate significant free cash flow in the third quarter.
  •  
  • Achieved adjusted EBITDA i of $190.7 million in the third quarter, the highest quarterly level over the last five years and a 135% increase from the second quarter.
  •  
  • Increased cash and total liquidity by $175.8 million to $539.6 million, including increased availability under the company's credit facilities due to higher EBITDA levels, lower net debt and renegotiated covenants.
  •  
  • Net debt reduced to $1,132 million during the third quarter, which together with higher levels of adjusted EBITDA, has improved the company's net debt to EBITDA ratio i compared to the second quarter.
  •  
  • Deleveraging efforts continued subsequent to quarter-end into October 2023 with a $40 million repayment on the company's credit facilities, a $5 million principal repayment on the Copper Mountain bonds and the recommencement of deliveries under the gold forward sale and prepay agreement to reduce the gold prepayment liability.
  •  
  • On track to deliver annual discretionary spending reduction targets for 2023 with lower growth capital and exploration expenditures compared to 2022. As a result of a continued focus on discretionary spending reductions, total capital expenditures for 2023 (excluding Copper Mountain) are expected to be approximately $30 million lower than previous guidance levels, a further decrease from the $15 million reduction announced in the second quarter, representing a 10% reduction in total capital expenditures.
  •  

  Executing on Growth Initiatives and Prudent Financial Planning  

 
  • Post-acquisition plans to stabilize the Copper Mountain operations are underway with a focus on mining fleet ramp-up activities, accelerated stripping and increasing mill reliability. To date, approximately $9 million of the $10 million in targeted annualized corporate synergies have been achieved.
  •  
  • As previously announced, a new technical report for the Copper Mountain mine is expected to be released in the fourth quarter. The new technical report will include an updated mine plan and updated annual production and cost estimates. The new technical report will also include updated mineral reserve and resource estimates and mill throughput assumptions.
  •  
  • Successfully completed ramp up of the Stall recovery improvement program with significantly higher copper, gold and silver recoveries realized in the third quarter.
  •  
  • Released results of the de-risked and enhanced Copper World pre-feasibility study for Phase I in September 2023, which demonstrated a simplified mine plan with an extended 20-year mine life requiring only state and local permits, an after-tax net present value (8%) of $1.1 billion and a 19% internal rate of return at a copper price of $3.75 per pound.
  •  
  • Completed the acquisition of Rockcliff Metals Corp. ("Rockcliff") on September 14, 2023, which has increased the company's land position within trucking distance of the Snow Lake processing facilities by more than 250%.
  •  
  • Commenced initial drill program at the company's Mason project in Nevada to test high grade targets on satellite properties with 25% of the program completed and assay results pending.
  •  

"We delivered on our plan for significantly higher production, revenue and cash flow in the third quarter, marking an inflection point as we generate strong returns from our recent brownfield and growth investments across the business," said Peter Kukielski, President and Chief Executive Officer. "We are reaffirming our 2023 full year guidance with strong copper and gold grades from Pampacancha in Peru and higher gold grades at Lalor in Manitoba, while remaining disciplined with capital spending. This, together with the contribution from our first full quarter of operating Copper Mountain, led to meaningful cash flow generation and demonstrates Hudbay's resilient operating platform and continued focus on deleveraging."

 

  Summary of Third Quarter Results  

 

Consolidated copper production in the third quarter of 2023 was 41,964 tonnes, a 93% increase from the second quarter of 2023. Consolidated gold production in the quarter was 101,417 ounces, a 107% increase over the second quarter. Consolidated silver production in the third quarter was 1,063,032 ounces, a 74% increase over the second quarter. The significant increase in production was driven by meaningfully higher recoveries in Peru and Manitoba, mining of the higher copper and gold grade zones at the Pampacancha deposit, higher gold and copper grade zones at Lalor and incremental production from the Copper Mountain mine. Consolidated zinc production in the third quarter increased by 18% compared to the prior quarter primarily due to higher mill throughput and higher zinc grades. Annual production guidance ranges for 2023 have been reaffirmed for both Peru and Manitoba, and consolidated production guidance has been updated to include contributions from Copper Mountain.

 

Consolidated cash cost per pound of copper produced, net of by-product credits i , was $1.10 in the third quarter of 2023, compared to $1.60 in the second quarter. This improvement was driven by strong copper and gold production in Peru and Manitoba, which more than offset the higher mining, milling, G&A, freight and treatment and refining charges associated with now having three operations. Consolidated sustaining cash cost per pound of copper produced, net of by-product credits i , was $1.89 in the third quarter of 2023, compared to $2.73 in the second quarter. This decrease was primarily due to the same factors affecting consolidated cash cost, partially offset by higher cash sustaining capital expenditures. Both cash cost measures are expected to continue to be strong in the fourth quarter with higher expected copper production and continued strong contributions from precious metal by-product credits. Full year cash cost guidance ranges for 2023 are reaffirmed for each of Peru and Manitoba and consolidated cash cost and sustaining cash cost guidance ranges have been updated to include Copper Mountain. Consolidated all-in sustaining cash cost per pound of copper produced, net of by-product credits i , was $2.04 in the third quarter of 2023, lower than $2.98 in the second quarter, due to the same reasons outlined above as well as slightly higher corporate selling and administrative expenses.

 

Cash generated from operating activities in the third quarter of 2023 significantly increased to $151.9 million compared to $24.6 million in the second quarter. Operating cash flow before change in non-cash working capital was a record $182.0 million during the third quarter, reflecting an increase of $126.1 million over the prior quarter. The increase in operating cash flow was primarily the result of higher copper sales volumes from mining the high grade zones of the Pampacancha deposit, higher gold and copper grade zones at Lalor and an incremental contribution from the Copper Mountain mine.

 

Net earnings and earnings per share in the third quarter of 2023 were $45.5 million and $0.13, respectively, compared to net loss and loss per share of $14.9 million and $0.05, respectively, in the second quarter of 2023. The results were positively impacted by a non-cash gain of $32.4 million related to the quarterly revaluation of the environmental reclamation provision at the company's closed sites, partially offset by a $2.3 million one-time charge related to restructuring costs arising from the Copper Mountain acquisition.

 

Adjusted net earnings i and adjusted net earnings per share i in the third quarter of 2023 were $24.4 million and $0.07 per share, respectively, after adjusting for the non-cash gain related to the revaluation of the environmental provision, among other items. This compares to adjusted net loss and adjusted net loss per share of $18.3 million and $0.07 in the second quarter of 2023. Adjusted EBITDA i was $190.7 million, a 135% increase compared to $81.2 million in the second quarter. Revenue, earnings and cash would have further benefitted from the sale of approximately 20,000 ounces of consolidated gold production that was unsold at the end of the third quarter and is expected to be sold in the fourth quarter.

 

As at September 30, 2023, total liquidity increased to $539.6 million, including $245.2 million in cash and cash equivalents as well as undrawn availability of $294.4 million under the company's revolving credit facilities. Net debt declined during the quarter to $1,132 million as at September 30, 2023. Subsequent to quarter end, Hudbay repaid $40 million on its revolving credit facilities and made a $5 million principal repayment on the Copper Mountain bonds. Based on continued expected free cash flow generation in the fourth quarter of 2023, the company continues to expect to make progress on its deleveraging targets as outlined in the "3-P" plan for sanctioning Copper World. Current liquidity combined with cash flow from operations is expected to be sufficient to meet the company's liquidity needs for the foreseeable future.

 
                                   
  Consolidated Financial Condition ($000s)     Sep. 30, 2023    Jun. 30, 2023    Dec. 31, 2022  
Cash    245,217   179,734 225,665
Total long-term debt    1,377,443   1,370,682 1,184,162
Net debt 1    1,132,226   1,190,948 958,497
Working capital 2    128,463   (61,357) 76,534
Total assets    5,250,596   5,242,140 4,325,943
Equity 3    2,044,684   2,001,970 1,571,809
 

  1 Net debt is a non-IFRS financial performance measure with no standardized definition under IFRS. For further information, please see the "Non-IFRS Financial Performance Measures" section of this news release.
2 Working capital is determined as total current assets less total current liabilities as defined under IFRS and disclosed on the consolidated interim financial statements.
3 Equity attributable to owners of the company.

 
                                                 
  Consolidated Financial Performance   2     Three Months Ended  
    Sep. 30, 2023    Jun. 30, 2023    Sep. 30, 2022  
Revenue   $000s    480,456   312,166 346,171
Cost of sales   $000s    374,057   289,273 313,741
Earnings (loss) before tax   $000s    84,149   (30,731) (263)
Earnings (loss)   $000s    45,490   (14,932) (8,135)
Basic and diluted earnings (loss) per share   $/share    0.13   (0.05) (0.03)
Adjusted earnings (loss) per share 1   $/share    0.07   (0.07) (0.05)
Operating cash flow before change in non-cash working capital   $ millions    182.0   55.9 81.6
Adjusted EBITDA 1   $ millions    190.7   81.2 99.3
  1 Adjusted (loss) earnings per share and adjusted EBITDA are non-IFRS financial performance measures with no standardized definition under IFRS. For further information, please see the "Non-IFRS Financial Performance Measures" section.
 

 

 
                                                                                     
  Consolidated Production and Cost Performance   5    Three Months Ended  
    Sep. 30, 2023    Jun. 30, 2023    Sep. 30, 2022  
  Contained metal in concentrate and doré produced   1     
Copper   tonnes    41,964   21,715 24,498
Gold   ounces    101,417   48,996 53,179
Silver   ounces    1,063,032   612,310 717,069
Zinc   tonnes    10,291   8,758 9,750
Molybdenum   tonnes    466   414 437
  Payable metal sold      
Copper   tonnes    39,371   23,078 24,799
Gold 2   ounces    74,799   47,533 66,932
Silver 2   ounces    748,955   805,448 816,416
Zinc 3   tonnes    7,125   8,641 12,714
Molybdenum   tonnes    426   314 511
  Consolidated cash cost per pound of copper produced   4     
Cash cost   $/lb    1.10   1.60 0.58
Sustaining cash cost   $/lb    1.89   2.73 1.91
All-in sustaining cash cost   $/lb    2.04   2.98 2.16
 

  1 Metal reported in concentrate is prior to deductions associated with smelter contract terms.
2 Includes total payable gold and silver in concentrate and in doré sold.
3 For the three months ended September 30, 2023 and the three months ended June 30, 2023 this metric includes payable zinc in concentrate sold. For the three months ended September 30, 2022, this metric also included payable refined zinc metal sold.
4 Cash cost, sustaining cash cost and all-in sustaining cash cost per pound of copper produced, net of by-product credits, are non-IFRS financial performance measures with no standardized definition under IFRS. For further information, please see the "Non-IFRS Financial Performance Measures" section of this news release.
5 Includes production results from the Copper Mountain mine following the June 20, 2023 acquisition completion date.

 

  Peru Operations Review  

 
                                                                                                                                                                                     
  Peru Operations    Three Months Ended  
    Sep. 30, 2023    Jun. 30, 2023    Sep. 30, 2022  
  Constancia ore mined   1    tonnes    1,242,198   3,647,399 6,300,252
Copper   %    0.30   0.31 0.36
Gold   g/tonne    0.04   0.04 0.05
Silver   g/tonne    2.91   2.49 3.38
Molybdenum   %    0.01   0.01 0.01
  Pampacancha ore mined    tonnes    5,894,013   2,408,495 2,488,928
Copper   %    0.53   0.36 0.29
Gold   g/tonne    0.30   0.34 0.23
Silver   g/tonne    4.22   2.81 4.30
Molybdenum   %    0.02   0.02 0.01
Total ore mined   tonnes    7,136,211   6,055,894 8,789,180
Strip ratio 2    1.36   1.74 1.26
  Ore milled    tonnes    7,895,109   7,223,048 7,742,020
Copper   %    0.43   0.31 0.34
Gold   g/tonne    0.21   0.09 0.08
Silver   g/tonne    3.75   2.78 3.48
Molybdenum %   0.02   0.01 0.01
Copper recovery   %    85.2   80.0 84.5
Gold recovery   %    74.8   61.1 61.9
Silver recovery   %    73.2   65.1 65.2
Molybdenum recovery   %    37.2   40.5 41.0
  Contained metal in concentrate     
Copper   tonnes    29,081   17,682 22,302
Gold   ounces    40,596   12,998 12,722
Silver   ounces    697,211   419,642 564,299
Molybdenum   tonnes    466   414 437
  Payable metal sold     
Copper   tonnes    27,490   21,207 20,718
Gold   ounces    32,757   14,524 11,970
Silver   ounces    460,001   671,532 513,470
Molybdenum   tonnes    426   314 511
Combined unit operating cost 3,4,5   $/tonne    12.20   14.07 13.06
Cash cost 5   $/lb    0.83   2.14 1.68
Sustaining cash cost 5   $/lb    1.51   3.06 2.46
  1 Reported tonnes and grade for ore mined are estimates based on mine plan assumptions and may not reconcile fully to ore milled.
  2 Reflects combined mine, mill and general and administrative ("G&A") costs per tonne of ore milled. Reflects the deduction of expected capitalized stripping costs.
  3 Combined unit costs, cash cost and sustaining cash cost per pound of copper produced, net of by-product credits, are non-IFRS financial performance measures with no standardized definition under IFRS. For further information, please see the "Non-IFRS Financial Performance Measures" section of this news release.
  4 Excludes approximately $0.9 million, or $0.12 per tonne, of COVID-related costs during the three months ended September 30, 2022.
  5 Strip ratio is calculated as waste mined divided by ore mined.
 
 

During the third quarter of 2023, the Peru operations produced 29,081 tonnes of copper, 40,596 ounces of gold, 697,211 ounces of silver and 466 tonnes of molybdenum. The significant increases in copper and gold production compared to the second quarter were a result of higher copper, gold and silver grades from mining the high grade zones of the Pampacancha deposit, higher recoveries and higher throughput. Full year production in Peru is expected to continue to benefit from higher grades in the fourth quarter of 2023 and, as such, full year production of all metals in Peru remains on track to achieve the guidance ranges for 2023.

 

Total ore mined in the third quarter of 2023 increased by 18% compared to the second quarter, in line with the mine plan, despite a decline in ore mined from the Constancia pit associated with the commencement of phase five stripping activities. Ore mined from Pampacancha increased to 5.9 million tonnes during the third quarter at average grades of 0.53% copper and 0.30 grams per tonne gold.

 

Ore milled during the third quarter of 2023 was 9% higher than the second quarter primarily as a result of a scheduled plant maintenance shutdown in the second quarter. Milled copper and gold grades increased to 0.43% and 0.21 g/tonne, respectively, in the third quarter of 2023, representing a 39% and 133% increase, respectively, compared to the second quarter, due to a significant increase in the mining of higher grade copper-gold ore from Pampacancha.

 

Recoveries of copper, gold and silver during the third quarter of 2023 were 7%, 22% and 12% higher, respectively, than the second quarter and were in line with metallurgical models. Recoveries benefitted from the completion of the recovery uplift program in the second quarter as well as higher head grades and lower contaminants.

 

Combined mine, mill and G&A unit operating costs i in the third quarter of 2023 were 13% lower than the second quarter primarily as a result of lower milling costs and higher throughput as the second quarter was impacted by a scheduled plant maintenance shutdown.

 

Peru's cash cost per pound of copper produced, net of by-product credits i , in the third quarter of 2023 was $0.83 compared to $2.14 in the second quarter of 2023. This 61% improvement was primarily a result of higher by-product credits mainly from gold, higher pounds of copper produced and lower milling costs. This was partly offset by higher profit sharing expenses and higher treatment & refining and freight costs. This cost measure is declining meaningfully, as expected, in the second half of 2023 and the full year cash cost is expected to remain within the 2023 guidance range with continued higher copper production and contributions from precious metal by-product credits from Pampacancha expected in the fourth quarter of 2023.

 

Peru's sustaining cash cost per pound of copper produced, net of by-product credits i , in the third quarter of 2023 was $1.51, representing a 51% decline from the second quarter due to the same factors affecting cash cost noted above, partially offset by higher sustaining capital expenditures. However, total annual sustaining capital expenditures in Peru are expected to be $10 million lower than the original 2023 guidance levels primarily a result of lower capitalized stripping costs.

 

  Manitoba Operations Review  

 
                                                                                                                                                                                                
  Manitoba Operations Three Months Ended  
    Sep. 30, 2023    Jun. 30, 2023    Sep. 30, 2022  
  Lalor      
Ore mined   tonnes    367,491   413,255 347,345
Gold   g/tonne    5.08   4.07 4.57
Copper   %    1.02   0.81 0.71
Zinc   %    3.31   3.14 3.27
Silver   g/tonne    27.80   23.27 21.27
  New Britannia      
Ore milled tonnes   146,927   141,905 132,362
Gold g/tonne   6.93   5.82 7.70
Copper %   1.22   0.77 0.72
Zinc %   0.90   0.85 0.73
Silver g/tonne   23.88   25.79 20.11
Gold recovery - concentrate %   64.7   55.0 60.6
Copper recovery - concentrate %   97.4   91.2 92.3
Silver recovery - concentrate %   63.2   57.0 61.2
  Stall Concentrator     
Ore milled   tonnes    255,516   238,633 229,746
Gold g/tonne   3.70   3.12 2.81
Copper   %    0.77   0.85 0.67
Zinc   %    4.88   4.47 4.82
Silver   g/tonne    28.82   22.15 20.98
Gold recovery   %    67.8   59.9 61.3
Copper recovery   %    93.9   88.5 85.8
Zinc recovery   %    82.6   82.2 88.0
Silver recovery   %    64.9   60.3 55.7
  Total contained metal in concentrate and doré   1    
Gold   ounces    56,213   35,253 40,457
Copper   tonnes    3,580   2,794 2,196
Zinc   tonnes    10,291   8,758 9,750
Silver   ounces    264,752   180,750 152,770
  Total payable metal sold     
Gold 2   ounces    36,713   33,009 54,962
Copper   tonnes    2,925   1,871 4,081
Zinc 3   tonnes    7,125   8,641 12,714
Silver 2   ounces    197,952   133,916 302,946
Combined unit operating cost 4,5   C$/tonne    217   220 235
Gold cash cost 5   $/oz    670   1,097 216
Gold sustaining cash cost 5   $/oz    939   1,521 1,045
 

  1 Doré includes sludge, slag and carbon fines in three months ended September 30, 2023 and June 30, 2023.
2 Includes total payable precious metals in concentrate and doré sold.
3 Includes refined zinc metal and payable zinc in concentrate sold.
4 Reflects combined mine, mill and G&A costs per tonne of ore milled.
5 Combined unit operating cost, cash cost and sustaining cash cost per ounce of gold produced, net of by-product credits, are non-IFRS financial performance measures with no standardized definition under IFRS. For further information, please see the "Non-IFRS Financial Performance Measures" section of this news release.

 

During the third quarter of 2023, the Manitoba operations produced 56,213 ounces of gold, 3,580 tonnes of copper, 10,291 tonnes of zinc and 264,752 ounces of silver. Production of gold, copper, zinc and silver in the third quarter of 2023 was 59%, 28%, 18% and 46% higher, respectively, than the second quarter due to mining higher grade gold zones, generally higher recoveries at the New Britannia and Stall mills, and recovery of secondary gold products at New Britannia due to past processing inefficiencies. The improvements completed late in the quarter have resolved the past processing inefficiencies at New Britannia and gold is reporting to doré as designed. With the recent recovery improvements at the New Britannia and Stall mills and higher grades from Lalor in the third quarter, the company expects to achieve full year production guidance for all metals. Gold production is expected to trend toward the lower end of the guidance ranges while copper and zinc production are expected to trend to the upper end of the guidance ranges, as disclosed last quarter.

 

The company's Manitoba team continues to advance several key initiatives to support higher production levels, reduce dilution during the mining cycle and improve metal recoveries at the Snow Lake operations. The team at Lalor has placed a strong emphasis on enhancing the quality of ore production and minimizing dilution through improved blast designs, loading procedures, and effective grade control practices. Additionally, Hudbay successfully completed changes to optimize the circuits at the Snow Lake mills, resulting in increased copper, gold, and silver recoveries. Concurrently, the company is making improvements to the tailings deposition process at the Anderson facility and exploring the potential of transitioning the facility from subaqueous to subaerial tailings storage, potentially providing a more efficient use of impoundment space, addressing seasonal operational challenges and deferring capital expenditure for dam raise construction to future years.

 

At Lalor, the company successfully completed hoist rope replacements, biannual inspections and mine ventilation systems maintenance ahead of the winter season. Maintenance was also performed at the underground muck circuit and mine power centers during the quarter. Lalor production averaged 4,000 tonnes per day during the third quarter, which was lower than the prior quarter due to the mine maintenance activities. Copper, gold, silver and zinc grades mined during the third quarter of 2023 were 26%, 25%, 19% and 5% higher, respectively, than the second quarter.

 

The Stall mill processed 7% more ore in the third quarter of 2023 than in the second quarter as it drew down base metal ore stockpiles that built up at the end of second quarter. After the commissioning of the first phase of the Stall mill recovery improvement project in the second quarter of 2023, the third quarter was focused on optimizing circuits to achieve targeted recoveries by reducing primary grind size, refining the flotation circuit balance and mass pull, and reagent selection. These adjustments proved highly effective, resulting in notably higher recoveries for copper, gold and silver during the third quarter of 2023. Specifically, the Stall mill achieved its targeted gold recovery levels of approximately 68% in the third quarter, compared to 60% in the second quarter.

 

During the third quarter, the New Britannia mill consistently achieved elevated production levels averaging approximately 1,600 tonnes per day despite processing significantly higher copper head grades that can impact throughput due to copper flotation limitations. The company continues to advance process debottleneck initiatives at New Britannia that require minimal capital outlays as it pursues higher throughput targets, aligned with increased gold ore production from Lalor.

 

Combined mine, mill and G&A unit operating costs i decreased slightly in the third quarter compared to the second quarter, reflecting higher throughput.

 

Manitoba's cash cost per ounce of gold produced, net of by-product credits i was $670 in the third quarter, 39% lower than the second quarter, primarily as a result of higher gold production driven by higher grades and improved recoveries. Sustaining cash cost per ounce of gold produced, net of by-product credits i , for the third quarter was $939, a 38% decrease from the prior quarter primarily due to the same factors affecting cash cost. Total annual sustaining capital expenditures in Manitoba are expected to be $15 million lower than the original 2023 guidance levels primarily a result of lower capital development costs realized at Lalor as the team focuses on cost efficiencies.

 

Cash cost in the third quarter of 2023 was within the 2023 guidance range and is expected to continue to benefit from increasing gold production from higher grade stopes, continued throughput increases at Lalor and the full realization of higher recoveries from the Stall mill Phase I recovery improvement project in the fourth quarter. As a result, full year cash cost in Manitoba is expected to achieve the 2023 guidance range.

 

  British Columbia Operations Review  

 
                                                                                           
  British Columbia Operations Three Months Ended  
     Sep. 30, 2023  
  Ore mined   1    tonnes     3,792,568  
Waste mined   tonnes     11,233,917  
Strip ratio 2     2.96  
  Ore milled    tonnes     3,158,006  
Copper   %     0.36  
Gold   g/tonne     0.08  
Silver   g/tonne     1.40  
Copper recovery   %     80.9  
Gold recovery   %     56.1  
Silver recovery   %     71.3  
  Total contained metal in concentrate   2   
Copper   tonnes     9,303  
Gold   ounces     4,608  
Silver   ounces     101,069  
  Total payable metal sold    
Copper   tonnes     8,956  
Gold   ounces     5,329  
Silver   ounces     91,002  
Combined unit operating cost 3,4   C$/tonne     24.88  
Cash cost 4   $/lb     2.67  
Sustaining cash cost 4   $/lb     3.39  
  1 Reported tonnes and grade for ore mined are estimates based on mine plan assumptions and may not reconcile fully to ore milled.
  2 Strip ratio is calculated as waste mined divided by ore mined.
  3 Reflects combined mine, mill and G&A costs per tonne of ore milled. Reflects the deduction of expected capitalized stripping costs.
  4 Combined unit operating cost, cash cost and sustaining cash cost per pound of copper produced, net of by-product credits, are non-IFRS financial performance measures with no standardized definition under IFRS. For further information, please see the "Non-IFRS Financial Performance Measures" section of this news release.
 
 

During the third quarter of 2023, the British Columbia operations produced 9,303 tonnes of copper, 4,608 ounces of gold and 101,069 ounces of silver. The third quarter was the first full quarter of production from the Copper Mountain mine after the completion of the acquisition on June 20, 2023.

 

Total ore mined at Copper Mountain in the third quarter of 2023 was 3.8 million tonnes, in line with Hudbay expectations. Following the closing of the Copper Mountain transaction in late June, mine operations initiated a fleet production ramp up plan to capture the full value of existing idle capital equipment at the Copper Mountain site. This plan entails a fleet capacity/utilization ramp up from 14 trucks to 26 trucks over the third and fourth quarters, which is expected to result in a more than 30% increase in tonnes moved in 2023 compared to 2022. The company also commissioned a new Komatsu PC8000 electric shovel in September, which reduces carbon intensity by displacing existing diesel shovel production.

 

The mill processed a total of 3.2 million tonnes of ore during the third quarter, with mill availability averaging 83.5%. A scheduled mill shutdown occurred in September to facilitate liner replacement and a power transmission line upgrade. In coordination with BC Hydro, thermal upgrades to the site transmission line were completed to support 100MW of site supply for current and future site operations. Mill throughput for the quarter was impacted by excessive coarse material bypassing the comminution circuit and restricting flow through the tailings discharge line, causing high levels of unplanned downtime. This issue was rectified in August and the company has since seen continuous improvements in throughput. A key focus area for Hudbay is implementing improved maintenance management systems as part of Hudbay's stabilization plans for increasing mill availability.

 

Milled copper grades during the third quarter of 2023 were 0.36%, in line with expectations. Copper recoveries were 80.9% in the third quarter, an increase compared to 79.1% that was previously reported by Copper Mountain for the full year 2022. As part of the near-term stabilization plans at Copper Mountain, Hudbay expects to apply mill efficiency initiatives from the Constancia mill to the Copper Mountain mill in an effort to continue to improve concentrate quality and copper recoveries.

 

Combined mine, mill and G&A unit operating costs i in the third quarter of 2023 were C$24.88 per tonne milled. Combined unit operating costs per tonne milled are expected to decrease over time as the company continues its stabilization and optimization initiatives at Copper Mountain.

 

British Columbia's cash cost per pound of copper produced, net of by-product credits i , was $2.67 and sustaining cash cost per pound of copper produced, net of by-product credits i , was $3.39 in the third quarter. This indicates an improvement in cash costs when compared to the full year 2022 levels previously reported by Copper Mountain of $3.53 per pound and $4.20 per pound, respectively. The cash cost and sustaining cash cost measures are expected to remain within the post-acquisition guidance ranges for the balance of the year, as discussed below.

 

  Copper Mountain Stabilization Plans Underway and Consolidated Guidance Updated to Reflect Copper Mountain  

 

Since completing the acquisition of Copper Mountain on June 20, 2023, Hudbay has been focused on advancing its plans to stabilize the operation, including opening up the mine by adding additional mining faces and re-mobilizing idle haul trucks, optimizing the ore feed to the plant and implementing plant improvement initiatives. The company is also planning a campaign of accelerated stripping over the next two to three years to enable access to higher grade ore and to mitigate the substantially reduced stripping undertaken by Copper Mountain over the four years prior to completion of the acquisition.

 

Further details on the company's stabilization plans will be provided in a new technical report for the Copper Mountain mine, which is expected to be released in the fourth quarter of 2023. The new technical report will include an updated mine plan and updated annual production and cost estimates for the Copper Mountain mine, which will reflect Hudbay's stabilization and optimization initiatives, and the costs associated with the planned accelerated stripping. The new technical report will also include updated mineral reserve and resource estimates and mill throughput assumptions consistent with Hudbay's pre-acquisition internal assessments and in line with the mineral reserve and resource estimates and throughput assumptions disclosed in Copper Mountain's historical technical report dated February 25, 2019 (after accounting for mining depletion). Accordingly, Hudbay does not expect its mineral reserve and resource estimates and mill throughput expansion assumptions to be consistent with those disclosed in Copper Mountain's most recent technical report dated September 30, 2022. For further information, see, "Qualified Person and NI 43-101".

 

Hudbay is issuing inaugural Copper Mountain post-acquisition 2023 guidance for production and costs. The company has incorporated the Copper Mountain guidance into its consolidated production and cash cost guidance for the full year. Hudbay's production and cash cost guidance for Peru and Manitoba has otherwise been reaffirmed and remains unchanged.

 
                                                
  2023 Production and Cost Guidance     Peru Operations  
  (unchanged)   
  Manitoba Operations  
  (unchanged)   
  British Columbia Operations   2    Consolidated  
  (updated)   
Copper production 1   tonnes   91,000 - 116,000 9,000 - 12,000   18,500 - 20,500    118,500 - 148,500  
Gold production 1   ounces   83,000 - 108,000 175,000 - 205,000   8,000 - 10,000    266,000 - 323,000  
Silver production 1   ounces   2,210,000 - 2,650,000 750,000 - 1,000,000   190,000 - 210,000    3,150,000 - 3,860,000  
Zinc production 1   tonnes   28,000 - 36,000   28,000 - 36,000  
Molybdenum production 1   tonnes   1,300 - 1,600   1,300 - 1,600  
Cash cost 3   $1.05 - $1.30/lb $500 - $800/oz   $2.40 - $2.85/lb    $0.80 - $1.10/lb  
Sustaining cash cost 3      $1.80 - $2.25/lb  
 

  1 Metal reported in concentrate and doré is prior to refining losses or deductions associated with smelter terms.
2 British Columbia operations represented on a 100% basis and for the period since the acquisition completion date of June 20, 2023.
3 Cash cost and sustaining cash cost per pound of copper produced, net of by-product credits, and gold cash cost per ounce of gold produced, net of by-product credits, are non-IFRS financial performance measures with no standardized definition under IFRS. For further information, please see the "Non-IFRS Financial Performance Measures" section of this news release. Canadian dollar costs are converted into U.S. dollars using an exchange rate of 1.35 C$/US$.

 

  Generating Free Cash Flow with Increased Production and Continued Financial Discipline  

 

Hudbay delivered positive free cash flow during the third quarter of 2023 as the company executed its plan for higher copper and gold grades from Pampacancha and higher gold grades at Lalor. The company continues to expect to see significantly higher production levels in the second half of 2023, compared to the first half of 2023, as a result of these higher grades in Peru and Manitoba, along with the contribution of production from the newly acquired Copper Mountain mine.

 

During the third quarter, the company drew $90 million from its revolving credit facilities to finance the redemption of $87 million of principal and interest from Copper Mountain's bonds, which improved the company's ability to deleverage and repay debt sooner than waiting for bond maturity in 2026.

 

The company increased its cash and cash equivalents to $245.2 million and reduced its net debt to $1,132 million as at September 30, 2023, compared to $179.7 million and $1,190 million, respectively, as at June 30, 2023. The $58 million decline in net debt, together with higher levels of adjusted EBITDA i in the third quarter, have improved the company's net debt to EBITDA ratio compared to the second quarter thereby improving its credit facility availability. Subsequent to quarter-end, Hudbay continued its deleveraging efforts with a $40 million repayment on its credit facilities and a $5 million principal repayment on the Copper Mountain bonds in October 2023. The company has also recommenced deliveries under the gold forward sale and prepay agreement in October 2023, further reducing the gold prepayment liability.

 

As an additional prudent measure to ensure free cash flow generation and continued financial discipline in 2023, during the third quarter, the Copper Mountain joint venture entered into forward sales contracts for a total of 2,000 tonnes of copper production over the five-month period from August through December 2023 at an average price of $3.86 per pound. During the second quarter of 2023, Hudbay entered into a zero-cost collar program for approximately 10% of copper production expected from Peru and Manitoba in the second half of 2023. The program entails hedging 15.9 million pounds of copper from July to December 2023 at an average floor price of $3.95 per pound and an average cap price of $4.28 per pound. As at September 30, 2023, 2.6 million pounds of copper forwards and 7.9 million pounds of copper collars were outstanding.

 

The company remains on track to deliver annual discretionary spending reduction targets for 2023. As a result of continued financial discipline and capital cost efficiencies achieved to-date, total capital expenditures for Peru, Manitoba and Arizona in 2023 are expected to be approximately $30 million lower than previous guidance levels, representing a 10% reduction from the original 2023 total capital expenditure guidance. This represents a further decrease from the $15 million targeted reduction announced in the second quarter. With the issuance of Copper Mountain post-acquisition guidance, the company expects capital expenditures at its British Columbia operations to total approximately $35 million in 2023.

 
                                          
  2023 Capital Expenditure Guidance   1   (in $ millions)    Original    Updated  
  Sustaining capital:    
Peru 160   150  
Manitoba 75   60  
  Growth capital:    
Peru 10   10  
Manitoba 15   15  
Arizona 30   25  
Capitalized exploration 10   10  
  Total    300    270  
  2023 British Columbia Guidance   1,2     New  
Sustaining capital   33  
Growth capital   2  
  Total    35  
 

  1 Excludes capitalized costs not considered to be sustaining or growth capital expenditures and right-of-use lease additions. Includes capitalized stripping costs. Converted into U.S. dollars using an exchange rate of 1.35 C$/US$.
2 British Columbia operations represented on a 100% basis and for the period since the acquisition completion date of June 20, 2023.

 

  De-risked Copper World with Enhanced Phase I Pre-Feasibility Study  

 

On September 8, 2023, Hudbay released the results of the enhanced pre-feasibility study ("PFS") for Phase I of the 100%-owned Copper World project in Arizona. Highlights of the PFS include:

 
  • Phase I, which is a standalone operation requiring only state and local permits for an extended 20-year mine life, has an after-tax net present value (8%) of $1.1 billion and generates a 19% internal rate of return at a copper price of $3.75 per pound.
  •  
  • Average annual copper production over the first ten years of approximately 92,000 tonnes at cash costs and sustaining cash costs of $1.53 and $1.95 per pound of copper i , respectively.
  •  
  • Extended Phase I mine life to 20 years, with the potential for further expansion, compared to 16 years in the previous study with an 18% increase to total copper production and higher mill head grades.
  •  
  • Lowered initial capital cost estimate to approximately $1.3 billion ($1.1 billion net of existing stream agreement), compared to $1.9 billion in the previous preliminary economic assessment, due to the deferral of the construction of a concentrate leach facility to year 4 with the potential to be fully funded from operating cash flows or benefit from future government incentives for critical minerals processing.
  •  
  • Simplified project flow sheet includes a 60,000 ton per day sulfide concentrator that will produce copper concentrate as a final product until the addition of a concentrate leach facility and a solvent extraction and electrowinning plant in year 5 that will allow the project to produce copper cathodes. The production of copper cathodes will reduce the project's carbon footprint, make Copper World the third largest domestic copper cathode producer in the United States 2 and bolster the country's green energy independence with "Made in America" copper.
  •  
  • Total GHG emissions are expected to be 14% lower compared to an operation that only produces copper concentrate.
  •  
  • Significant benefits for the community and local economy in Arizona through payment of more than $850 million in U.S. federal and state taxes and the creation of an estimated 400 direct and 3,000 indirect jobs.
  •  
  • Copper World is one of the highest-grade open pit copper projects in the Americas 3 with proven and probable mineral reserves of 385 million tonnes at 0.54% copper.
  •  
  • Together with the pre-feasibility study, Hudbay has updated the mineral resource estimates for the project, which increases the global measured and indicated mineral resources (inclusive of mineral reserves) to 1.2 billion tonnes at 0.42% copper, representing a 4% increase in total in-situ copper. This confirms significant upside at Copper World with an intended Phase II expansion of mining activities onto federal land to further enhance the project economics and extend the mine life well beyond 20 years.
  •  

The first key state permit required for Copper World, the Mined Land Reclamation Plan ("MLRP), was initially approved by the Arizona State Mine Inspector in October 2021 and was subsequently amended to reflect a larger private land project footprint. This approval was challenged in state court, but the challenge was dismissed in May 2023 as having no basis. In late 2022, Hudbay submitted the applications for an Aquifer Protection Permit and an Air Quality Permit to the Arizona Department of Environmental Quality ("ADEQ"). Based on ongoing feedback and dialogue with the ADEQ, the company expects to receive these two outstanding state permits in mid-2024.

 

Hudbay intends to initiate a minority joint venture partner process prior to commencing a definitive feasibility study, which will allow the potential joint venture partner to participate in the funding of definitive feasibility study activities as well as in the final Copper World project design. The opportunity to sanction Copper World is not expected until 2025 based on current estimated timelines. The decision to sanction Copper World will ultimately be evaluated against other competing investment opportunities as part of Hudbay's capital allocation process.

 

  Completion of Rockcliff Acquisition  

 

On September 14, 2023, Hudbay successfully completed its previously announced acquisition of Rockcliff, pursuant to which Hudbay acquired all of the issued and outstanding common shares of Rockcliff that it did not already own (the "Rockcliff Transaction") by way of a court-approved plan of arrangement. As a result of closing the Rockcliff Transaction, Rockcliff is now a wholly-owned subsidiary of Hudbay.

 

The enterprise value to Hudbay, net of Rockcliff's cash, was approximately $13 million. Hudbay issued 0.006776 of a Hudbay common share in exchange for each Rockcliff common share previously held and, in aggregate, issued 2,675,324 Hudbay common shares under the Rockcliff Transaction to former Rockcliff shareholders. The Rockcliff shares were delisted from the CSE and Rockcliff has ceased to be a reporting issuer under Canadian securities laws.

 

Rockcliff was one of the largest landholders in the Snow Lake area, with approximately 1,800 square kilometres across all its properties. The Rockcliff Transaction has the potential to further extend mine life at the Snow Lake operations by consolidating Hudbay's ownership in the Talbot copper-gold deposit and more than tripling the company's prospective land package in the Snow Lake region. Prior to the Rockcliff Transaction, Rockcliff was the 49% joint venture partner of the Talbot deposit. The Talbot deposit and the additional Rockcliff exploration properties provide further optionality and potential future feed sources for the Stall and New Britannia mills.

 

  Other Exploration Update  

 

  Constancia In-Mine Exploration  

 

Hudbay continues to execute a limited drill program and technical evaluations at the Constancia deposit to confirm the economic viability of adding an additional mining phase to the current mine plan that would convert a portion of the mineral resources to mineral reserves. The results from this drill program and technical and economic evaluations are expected to be incorporated in the next annual mineral reserve and resource update in March 2024.

 

  Maria Reyna and Caballito Exploration  

 

Hudbay controls a large, contiguous block of mineral rights with the potential to host satellite mineral deposits in close proximity to the Constancia processing facility, including the past producing Caballito property and the highly prospective Maria Reyna property. The company commenced early exploration activities at Maria Reyna and Caballito after completing a surface rights exploration agreement with the community of Uchucarcco in August 2022. Hudbay has completed technical activities necessary to support drill permit application, including surface investigation work, baseline environmental and archaeological activities, and the company continues to advance community engagement activities. Surface mapping and geochemical sampling confirm that both Caballito and Maria Reyna host sulfide and oxide rich copper mineralization in skarns, hydrothermal breccias and large porphyry intrusive bodies.

 

  Snow Lake Exploration  

 

Hudbay continues to compile results from ongoing infill drilling at Lalor, which will be incorporated into the next annual mineral resource and reserve estimate update in March 2024.

 

The company is also preparing plans for exploration activities on the newly acquired land in Snow Lake, which is expected to include geophysical and drilling programs on the Cook Lake claims and the former Rockcliff claims located within trucking distance of the existing Snow Lake processing infrastructure. A majority of the Cook Lake and former Rockcliff claims have been untested by modern deep geophysics, which was the discovery method for the Lalor deposit. Hudbay intends to explore these claims in hopes of finding a new anchor deposit to maximize and extend the life of the Snow Lake operations beyond 2038.

 

  Mason Exploration  

 

The Mason project is a large greenfield copper deposit located in the historic Yerington District of Nevada and is one of the largest undeveloped copper porphyry deposits in North America. Hudbay completed a PEA in 2021 which demonstrated robust project economics from a 27-year mine life operation. There is an opportunity to further enhance the project economics through exploration for higher grade satellite deposits on the prospective land package near Mason, including Mason Valley. The Mason Valley property hosts several historical underground copper mines that were in production in the early 1900s. Much of the Mason Valley property is located on Hudbay's wholly owned private lands within 15 kilometres of the planned processing infrastructure for the Mason project and contains highly prospective skarn mineralization.

 

For the first time since Hudbay acquired Mason, the company initiated a drill program in September 2023 to test these satellite deposits, including high-grade skarn targets and a large porphyry target below the historical mines. The drill program is approximately 25% complete at the end of October with assay results pending.

 

  Website Links  

 

Hudbay:

 

   www.hudbay.com   

 

Management's Discussion and Analysis:
  https://www.hudbayminerals.com/MDA1123   

 

Financial Statements:
  https://www.hudbayminerals.com/FS1123   

 

  Conference Call and Webcast  

 
          
Date: Thursday, November 9, 2023
Time: 9:00 a.m. ET
Webcast:    www.hudbay.com   
Dial in: 1-646-307-1591 or 1-800-599-5188
  
 

  Qualified Person and NI 43-101  

 

The technical and scientific information in this news release related to the company's material mineral projects has been approved by Olivier Tavchandjian, P. Geo, Senior Vice President, Exploration and Technical Services. Mr. Tavchandjian is a qualified person pursuant to National Instrument 43-101 – Standards of Disclosure for Mineral Projects ("NI 43-101").

 

As disclosed in this news release, Hudbay expects to file a new technical report for the Copper Mountain mine in the fourth quarter of 2023. The new technical report will include an updated mine plan and updated annual production and cost estimates. The new technical report will also include updated mineral reserve and resource estimates and mill throughput assumptions consistent with Hudbay's pre-acquisition internal assessments and in line with the mineral reserve and resource estimates and throughput assumptions disclosed in Copper Mountain's historical technical report dated February 25, 2019 (after accounting for mining depletion). Accordingly, Hudbay does not expect its mineral reserve and resource estimates and mill throughput expansion assumptions to be consistent with those disclosed in Copper Mountain's most recent technical report dated September 30, 2022. Investors are cautioned they should not rely on any of Copper Mountain's previously issued technical reports.

 

  Non-IFRS Financial Performance Measures  

 

Adjusted net earnings (loss), adjusted net earnings (loss) per share, adjusted EBITDA, net debt, cash cost, sustaining and all-in sustaining cash cost per pound of copper produced, cash cost and sustaining cash cost per ounce of gold produced, combined unit costs and ratios based on these measures are non-IFRS performance measures. These measures do not have a meaning prescribed by IFRS and are therefore unlikely to be comparable to similar measures presented by other issuers. These measures should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS and are not necessarily indicative of operating profit or cash flow from operations as determined under IFRS. Other companies may calculate these measures differently.

 

Management believes adjusted net earnings (loss) and adjusted net earnings (loss) per share provides an alternate measure of the company's performance for the current period and gives insight into its expected performance in future periods. These measures are used internally by the company to evaluate the performance of its underlying operations and to assist with its planning and forecasting of future operating results. As such, the company believes these measures are useful to investors in assessing the company's underlying performance. Hudbay provides adjusted EBITDA to help users analyze the company's results and to provide additional information about its ongoing cash generating potential in order to assess its capacity to service and repay debt, carry out investments and cover working capital needs. Net debt is shown because it is a performance measure used by the company to assess its financial position. Cash cost, sustaining and all-in sustaining cash cost per pound of copper produced are shown because the company believes they help investors and management assess the performance of its operations, including the margin generated by the operations and the company. Cash cost and sustaining cash cost per ounce of gold produced are shown because the company believes they help investors and management assess the performance of its Manitoba operations. Combined unit cost is shown because Hudbay believes it helps investors and management assess the company's cost structure and margins that are not impacted by variability in by-product commodity prices.

 

The following tables provide detailed reconciliations to the most comparable IFRS measures.

 

  Adjusted Net Earnings (Loss) Reconciliation  

 
                                                                                                                                        
   Three Months Ended   
 
  (in $ millions)    Sep. 30, 2023    Jun. 30, 2023    Sep. 30, 2022  
Profit (loss) for the period   45.5    (14.9 ) (8.1 )
Tax expense (recovery)   38.7    (15.8 ) 7.8  
  Profit (loss) before tax    84.2    (30.7 ) (0.3 )
  Adjusting items     
Mark-to-market adjustments 1   1.3    0.6   (4.2 )
Foreign exchange (gain) loss   (0.6    )   1.4   (4.8 )
Inventory adjustments     0.9   2.1  
Variable consideration adjustment - stream revenue and accretion      3.9  
Re-evaluation adjustment - environmental provision 2   (32.4    )   (4.7 ) (6.4 )
Acquisition related costs   0.1    6.8   
Evaluation expenses      0.1  
Restructuring charges 3   2.3     5.1  
Loss on disposal of plant and equipment and non-current assets     0.3   (6.0 )
  Adjusted earnings (loss) before income taxes    54.9    (25.4 ) (10.5 )
Tax (expense) recovery   (38.7    )   15.8   (7.8 )
Tax impact on adjusting items   8.2    (8.7 ) 5.9  
  Adjusted net earnings (loss)    24.4    (18.3 ) (12.4 )
  Adjusted net earnings (loss) $/share    0.07    (0.07 ) (0.05 )
  Basic weighted average number of common shares outstanding (millions)    346.7    272.2   261.9  
 

  1 Includes changes in fair value of the gold prepayment liability, Canadian junior mining investments, other financial assets and liabilities at fair value through profit or loss and share-based compensation expenses.
2 Changes from movements to environmental reclamation provisions are primarily related to the Flin Flon operations, which were fully depreciated as of June 30, 2022, as well as other Manitoba non-operating sites.
3 Includes closure costs for Flin Flon operations in 2022 and restructuring charges for British Columbia in 2023.

 

 

 

  Adjusted EBITDA Reconciliation  

 
                                                                                           
   Three Months Ended  
  (in $ millions)    Sep. 30, 2023    Jun. 30, 2023    Sep. 30, 2022  
Profit (loss) for the period   45.5    (14.9 ) (8.1 )
Add back:    
Tax expense (recovery)   38.7    (15.8 ) 7.8  
Net finance expense   30.9    30.5   20.6  
Other expenses   8.9    13.9   6.3  
Depreciation and amortization   113.8    88.7   89.8  
Amortization of deferred revenue and variable consideration adjustment   (16.8    )   (18.1 ) (15.3 )
   221.0    84.3   101.1  
  Adjusting items (pre-tax):     
Re-evaluation adjustment - environmental provision   (32.4    )   (4.7 ) (6.4 )
Inventory adjustments     0.9   2.1  
Share-based compensation expense 1   2.1    0.7   2.5  
  Adjusted EBITDA    190.7    81.2   99.3  
 

  1 Share-based compensation expenses reflected in cost of sales and selling and administrative expenses.

 

  Net Debt Reconciliation  

 
                           
  (in $ thousands)   
   Sep. 30, 2023    Jun. 30, 2023    Dec. 31, 2022  
Total long-term debt   1,377,443    1,370,682   1,184,162  
Cash   (245,217    )   (179,734 ) (225,665 )
Net debt   1,132,226    1,190,948   958,497  
 

  Copper Cash Cost Reconciliation  

 
                          
   Consolidated     Three Months Ended  
  Net pounds of copper produced   1     
  (in thousands)    Sep. 30, 2023    Jun. 30, 2023    Sep. 30, 2022  
Peru   64,112   38,982 49,167
British Columbia   20,510  
Manitoba   7,893   6,160 4,841
  Net pounds of copper produced    92,515   45,142 54,008
 

  1 Contained copper in concentrate.

 
                                                                                                                                   
   Consolidated     Three Months Ended  
   Sep. 30, 2023    Jun. 30, 2023    Sep. 30 2022  
  Cash cost per pound of copper produced    $000s     $/lb   $000s $/lb $000s $/lb
Mining   104,547     1.13    73,335   1.62   75,856   1.40  
Milling   88,021     0.95    69,869   1.55   68,616   1.27  
G&A   36,107     0.39    20,975   0.47   23,262   0.43  
Onsite costs   228,675     2.47    164,179   3.64   167,734   3.11  
Treatment & refining   32,882     0.36    26,670   0.59   21,852   0.40  
Freight & other   26,853     0.29    17,766   0.39   22,078   0.41  
Cash cost, before by-product credits   288,410     3.12    208,615   4.62   211,664   3.92  
By-product credits   (187,023    )    (2.02    )   (136,417 ) (3.02 ) (180,464 ) (3.34 )
  Cash cost, net of by-product credits    101,387     1.10    72,198   1.60   31,200   0.58  
 

 

 
                                                                                                                                                                       
   Consolidated     Three Months Ended  
   Sep. 30, 2023    Jun. 30, 2023    Sep. 30 2022  
  Supplementary cash cost information    $000s    $/lb   1   $000s $/lb 1 $000s $/lb 1
By-product credits 2 :       
Zinc   17,099     0.18   21,896   0.48 43,606   0.81
Gold 3   129,954     1.41   86,026   1.91 101,650   1.88
Silver 3   16,724     0.18   17,281   0.38 16,066   0.30
Molybdenum & other   23,246     0.25   11,214   0.25 19,142   0.35
  Total by-product credits    187,023     2.02   136,417   3.02 180,464   3.34
Reconciliation to IFRS:       
Cash cost, net of by-product credits   101,387     72,198    31,200   
By-product credits   187,023     136,417    180,464   
Treatment and refining charges   (32,882    )    (26,670 )   (21,852 )  
Share-based compensation expense   149     60    114   
Inventory adjustments      906    2,074   
Change in product inventory   3,374     15,114    29,726   
Royalties   1,253     2,578    2,204   
Depreciation and amortization 4   113,753     88,670    89,811   
  Cost of sales   5    374,057     289,273    313,741   
 

  1 Per pound of copper produced.
2 By-product credits are computed as revenue per financial statements, amortization of deferred revenue and pricing and volume adjustments
3 Gold and silver by-product credits do not include variable consideration adjustments with respect to stream arrangements. Variable consideration adjustments are cumulative adjustments to gold and silver stream deferred revenue primarily associated with the net change in mineral reserves and resources or amendments to the mine plan that would change the total expected deliverable ounces under the precious metal streaming arrangement. For the three months ended September 30, 2023 the variable consideration adjustments amounted to nil, the three months ended June 30, 2023 - $nil, and for the three months ended September 30, 2022 - $2,286.
4 Depreciation is based on concentrate sold.
5 As per IFRS financial statements excluding impairment adjustments.

 

 

 
          
   Peru     Three Months Ended  
  (in thousands)    Sep. 30, 2023    Jun. 30, 2023    Sep. 30 2022  
  Net pounds of copper produced   1    64,112   38,982 49,167
 

  1 Contained copper in concentrate.

 
                                                                                                                                  
   Peru     Three Months Ended  
   Sep. 30, 2023    Jun. 30, 2023    Sep. 30 2022  
  Cash cost per pound of copper produced    $000s    $/lb   $000s $/lb $000s $/lb
Mining   33,875     0.53    31,654   0.81   35,197   0.72  
Milling   46,996     0.73    54,676   1.40   52,043   1.06  
G&A   20,912     0.33    14,867   0.38   13,421   0.27  
Onsite costs   101,783     1.59    101,197   2.59   100,661   2.05  
Treatment & refining   19,143     0.30    17,097   0.44   10,814   0.22  
Freight & other   17,040     0.26    12,424   0.32   12,905   0.26  
Cash cost, before by-product credits   137,966     2.15    130,718   3.35   124,380   2.53  
By-product credits   (84,793    )    (1.32    )   (47,193 ) (1.21 ) (41,659 ) (0.85 )
  Cash cost, net of by-product credits    53,173     0.83    83,525   2.14   82,721   1.68  
 

 

 
                                                                                                                                                           
   Peru     Three Months Ended  
    Sep. 30, 2023   
 
  Jun. 30, 2023   
 
  Sep. 30 2022  
  Supplementary cash cost information    $000s    $/lb   1   $000s $/lb 1 $000s $/lb 1
By-product credits 2 :       
Gold 3   51,459     0.80   21,638   0.55 12,793   0.26
Silver 3   10,088     0.16   14,341   0.37 9,967   0.20
Molybdenum   23,246     0.36   11,214   0.29 18,899   0.39
Total by-product credits   84,793     1.32   47,193   1.21 41,659   0.85
Reconciliation to IFRS:        
Cash cost, net of by-product credits   53,173     83,525    82,721   
By-product credits   84,793     47,193    41,659   
Treatment and refining charges    (19,143   
 
  )    (17,097 )   (10,814 )  
Share-based compensation expenses    45   
 
   29    (16 )  
Change in product inventory    4,137   
  
 
   27,078    (2,497 )  
Royalties    1,015   
 
   2,479    1,740   
Depreciation and amortization 4    80,625   
 
   67,340    56,614   
  Cost of sales   5     204,645   
 
   210,547    169,407   
 

  1 Per pound of copper produced.
2 By-product credits are computed as revenue per financial statements, including amortization of deferred revenue and pricing and volume adjustments.
3 Gold and silver by-product credits do not include variable consideration adjustments with respect to stream arrangements.
4 Depreciation is based on concentrate sold.
5 As per IFRS financial statements.

 

 

 
          
   British Columbia     Three Months Ended  
  (in thousands)     Sep. 30, 2023   
  Net pounds of copper produced   1     20,510   
 

  1 Contained copper in concentrate.

 
                                                       
   British Columbia       Three Months Ended  
    Sep. 30, 2023  
  Cash cost per pound of copper produced   $000s $/lb
Mining   29,251     1.43   
Milling   24,102     1.17   
G&A   5,050     0.25   
Onsite costs   58,403     2.85   
Treatment & refining   4,905     0.24   
Freight & other   3,693     0.18   
Cash cost, before by-product credits   67,001     3.27   
By-product credits   (12,234    )    (0.60    )  
  Cash cost, net of by-product credits    54,767     2.67   
 

 

 
                                                     
   British Columbia     Three Months Ended  
   Sep. 30, 2023   
 
  Supplementary cash cost information   $000s $/lb 1
By-product credits 2 :   
Gold   10,120     0.50  
Silver   2,114     0.10  
Total by-product credits   12,234     0.60  
Reconciliation to IFRS:   
Cash cost, net of by-product credits   54,767    
By-product credits   12,234    
Treatment and refining charges   (4,905    )   
Change in product inventory   3    
Royalties   237    
Depreciation and amortization 4   6,255    
  Cost of sales   5    68,591    
 

  1 Per pound of copper produced.
2 By-product credits are computed as revenue per financial statements, including amortization of deferred revenue and pricing and volume adjustments.
3 Depreciation is based on concentrate sold.
4 As per consolidated interim financial statements.

 

 

 

  Sustaining and All-in Sustaining Cash Cost Reconciliation  

 
                                                                                                                                    
   Consolidated     Three Months Ended  
   Sep. 30, 2023    Jun. 30, 2023    Sep. 30 2022  
  All-in sustaining cash cost per pound of copper produced    $000s  
  $/lb   $000s
$/lb $000s
$/lb
Cash cost, net of by-product credits   101,387    1.10   72,198 1.60 31,201 0.58
Cash sustaining capital expenditures   72,193    0.78   48,253 1.07 69,588 1.29
Royalties   1,253    0.01   2,578 0.06 2,204 0.04
  Sustaining cash cost, net of by-product credits    174,833    1.89   123,029 2.73 102,993 1.91
Corporate selling and administrative expenses & regional costs   10,971    0.12   9,603 0.21 11,384 0.21
Accretion and amortization of decommissioning and community agreements 1   3,309    0.03   1,792 0.04 2,099 0.04
  All-in sustaining cash cost, net of by-product credits    189,113    2.04   134,424 2.98 116,476 2.16
Reconciliation to property, plant and equipment additions:       
Property, plant and equipment additions   77,454    47,574   72,237  
Capitalized stripping net additions   21,762    21,640   22,645  
Total accrued capital additions   99,216    69,214   94,882  
Less other non-sustaining capital costs 2   37,968    28,006   39,807  
Total sustaining capital costs   61,248    41,208   55,075  
Capitalized lease cash payments - operating sites   7,199    4,374   8,852  
Community agreement cash payments   1,953    1,290   2,491  
Accretion and amortization of decommissioning and restoration obligations 3   1,793    1,381   3,170  
Cash sustaining capital expenditures   72,193    48,253   69,588  
 

  1 Includes accretion of decommissioning relating to non-productive sites, and accretion and amortization of current community agreements.
2 Other non-sustaining capital costs include Arizona capitalized costs, capitalized interest, capitalized exploration and growth capital expenditures.
3 Includes amortization of decommissioning and restoration PP&E assets and accretion of decommissioning and restoration liabilities related to producing sites.

 

 

 
                                         
   Peru     Three Months Ended  
   Sep. 30, 2023    Jun. 30, 2023    Sep. 30 2022  
  Sustaining cash cost per pound of copper produced    $000s    $/lb   $000s $/lb $000s $/lb
Cash cost, net of by-product credits   53,173    0.83   83,525 2.14 82,721 1.68
Cash sustaining capital expenditures   42,607    0.66   33,425 0.86 36,507 0.74
Royalties   1,015    0.02   2,479 0.06 1,740 0.04
  Sustaining cash cost per pound of copper produced    96,795    1.51   119,429 3.06 120,968 2.46
 

 

 
                                         
   British Columbia     Three Months Ended  
    Sep. 30, 2023   
  Sustaining cash cost per pound of copper produced      $000s    $/lb    
Cash cost, net of by-product credits     54,767    2.67    
Royalties     237    0.01    
Cash sustaining capital expenditures     14,487    0.71    
  Sustaining cash cost per pound of copper produced      69,491    3.39    
 

  1 Only includes exploration costs incurred for locations near to existing mine operations.

 

 

 

  Gold Cash Cost and Sustaining Cash Cost Reconciliation  

 
          
   Manitoba     Three Months Ended   
 
  (in thousands)    Sep. 30, 2023    Jun. 30, 2023    Sep. 30 2022  
  Net ounces of gold produced   1    56,213   35,253 40,457
 

  1 Contained gold in concentrate and doré.

 
                                                                                                                                  
   Manitoba     Three Months Ended  
   Sep. 30, 2023    Jun. 30, 2023    Sep. 30, 2022  
  Cash cost per ounce of gold produced    $000s    $/oz   $000s $/oz $000s $/oz
Mining   41,421     737    41,681   1,182   40,659   1,005  
Milling   16,923     301    15,193   431   16,573   410  
G&A   10,145     180    6,108   173   9,841   243  
Onsite costs   68,489     1,218    62,982   1,786   67,073   1,658  
Treatment & refining   8,834     157    9,573   271   11,038   273  
Freight & other   6,120     109    5,342   152   9,173   226  
Cash cost, before by-product credits   83,443     1,484    77,897   2,209   87,284   2,157  
By-product credits   (45,779    )    (814    )   (39,218 ) (1,112 ) (78,565 ) (1,941 )
  Gold cash cost, net of by-product credits    37,664     670    38,679   1,097   8,719   216  
 

 

 
                                                                                                                                                                       
   Manitoba     Three Months Ended  
   Sep. 30, 2023    Jun. 30, 2023    Sep. 30 2022  
  Supplementary cash cost information    $000s    $/oz   1    $000s    $/oz   1    $000s    $/oz   1  
By-product credits 2 :       
Copper   24,158     430   14,382   408 28,617   707
Zinc   17,099     304   21,896   621 43,606   1,077
Silver 3   4,522     80   2,940   83 6,099   151
Other        243   6
Total by-product credits   45,779     814   39,218   1,112 78,565   1,941
Reconciliation to IFRS:       
Cash cost, net of by-product credits   37,664     38,679    8,719   
By-product credits   45,779     39,218    78,565   
Treatment and refining charges   (8,834    )    (9,573 )   (11,038 )  
Inventory adjustments      906    2,074   
Share-based compensation expenses   104     31    130   
Change in product inventory   (766    )    (11,964 )   32,223   
Royalties   1     99    464   
Depreciation and amortization 4   26,873     21,330    33,197   
  Cost of sales   5    100,821     78,726    144,334   
 

  1 Per ounce of gold produced.
2 By-product credits are computed as revenue per financial statements, amortization of deferred revenue and pricing and volume adjustments.
3 Silver by-product credits do not include variable consideration adjustments with respect to stream arrangements.
4 Depreciation is based on concentrate sold.
5 As per IFRS financial statements, excluding impairment adjustments.

 

 

 
                                         
   Manitoba     Three Months Ended  
   Sep. 30, 2023   
 
  Jun. 30, 2023   
 
  Sep. 30 2022   
 
  Sustaining cash cost per pound of gold produced    $000s    $/oz    $000s    $/oz    $000s    $/oz  
Gold cash cost, net of by-product credits   37,664    670   38,679 1,097 8,719 216
Cash sustaining capital expenditures   15,100    269   14,828 421 33,081 818
Royalties   1     99 3 464 11
  Sustaining cash cost per pound of gold produced    52,765    939   53,606 1,521 42,264 1,045
 

 

 

  Combined Unit Cost Reconciliation  

 
                                                                                                                                         
   Peru     Three Months Ended  
  (in thousands except ore tonnes milled and unit cost per tonne)  
  Combined unit cost per tonne processed    Sep. 30, 2023    Jun. 30, 2023    Sep. 30 2022  
Mining   33,875    31,654   35,197  
Milling   46,996    54,676   52,043  
G&A 1   20,912    14,867   13,421  
Other G&A 2   (5,440    )   458   1,342  
   96,343    101,655   102,003  
Less: Covid related costs      929  
Unit cost   96,343    101,655   101,074  
Tonnes ore milled   7,895    7,223   7,742  
  Combined unit cost per tonne    12.20    14.07   13.06  
Reconciliation to IFRS:    
Unit cost   96,343    101,655   101,074  
Freight & other   17,040    12,424   12,905  
Covid related costs      929  
Other G&A   5,440    (458 ) (1,342 )
Share-based compensation expenses   45    29   (16 )
Change in product inventory   4,137    27,078   (2,497 )
Royalties   1,015    2,479   1,740  
Depreciation and amortization   80,625    67,340   56,614  
  Cost of sales   3    204,645    210,547   169,407  
 

  1 G&A as per cash cost reconciliation above.
2 Other G&A primarily includes profit sharing costs.
3 As per IFRS financial statements, excluding impairment adjustments.

 

 

 
                                                                   
   British Columbia     Three Months Ended  
  (in thousands except unit cost per tonne)  
  Combined unit cost per tonne processed     Sep. 30, 2023   
Mining    29,251   
Milling    24,102   
G&A 1    5,050   
Unit cost    58,403   
USD/CAD implicit exchange rate    1.35   
Unit cost - C$    78,566   
Tonnes ore milled    3,158   
  Combined unit cost per tonne - C$     24.88   
Reconciliation to IFRS:    
Unit cost    58,403   
Freight & other    3,693   
Change in product inventory    3   
Royalties    237   
Depreciation and amortization    6,255   
  Cost of sales   2     68,591   
 

 

 
   
  1 G&A as per cash cost reconciliation above
  2 Other G&A primarily includes profit sharing costs.
  3 As per consolidated interim financial statements.
 

 

 
                                                                                                                                         
   Manitoba     Three Months Ended  
  (in thousands except tonnes ore milled and unit cost per tonne)  
  Combined unit cost per tonne processed    Sep. 30, 2023    Jun. 30, 2023    Sep. 30 2022  
Mining   41,421    41,681   40,659  
Milling   16,923    15,193   16,573  
G&A 1   10,145    6,108   9,841  
Less: Other G&A related to profit sharing costs   (3,308    )   (682 ) (1,784 )
Unit cost   65,181    62,300   65,289  
USD/CAD implicit exchange rate   1.34    1.34   1.31  
Unit cost - C$   87,363    83,659   85,225  
Tonnes ore milled   402,443    380,538   362,108  
  Combined unit cost per tonne - C$    217    220   235  
Reconciliation to IFRS:    
Unit cost   65,181    62,300   65,289  
Freight & other   6,120    5,342   9,173  
Other G&A related to profit sharing   3,308    682   1,784  
Share-based compensation expenses   104    31   130  
Inventory adjustments     906   2,074  
Change in product inventory   (766    )   (11,964 ) 32,223  
Royalties   1    99   464  
Depreciation and amortization   26,873    21,330   33,197  
  Cost of sales   2    100,821    78,726   144,334  
 

  1 G&A as per cash cost reconciliation above.
2 As per IFRS financial statements, excluding impairment adjustments.

 

  Forward-Looking Information  
  
This news release contains forward-looking information within the meaning of applicable Canadian and United States securities legislation. All information contained in this news release, other than statements of current and historical fact, is forward-looking information. Often, but not always, forward-looking information can be identified by the use of words such as "plans", "expects", "budget", "guidance", "scheduled", "estimates", "forecasts", "strategy", "target", "intends", "objective", "goal", "understands", "anticipates" and "believes" (and variations of these or similar words) and statements that certain actions, events or results "may", "could", "would", "should", "might" "occur" or "be achieved" or "will be taken" (and variations of these or similar expressions). All of the forward-looking information in this news release is qualified by this cautionary note.

 

Forward-looking information includes, but is not limited to, statements with respect to the expected production and cash flow generation during the fourth quarter and the remainder of the second half of the year, the expected timing and implications of an updated Copper Mountain mine technical report, expectations regarding the updated mine plan, mineral reserve and resource estimates and mill throughput assumptions in the new Copper Mountain mine technical report, expectations regarding how the new Copper Mountain mine technical report will compare to Copper Mountain's historical disclosure, the ability of the company to stabilize and optimize the Copper Mountain mine operation, expectations regarding the results and findings of the Copper World PFS, including the production, operating cost, capital cost and cash cost estimates, the projected valuation metrics and rates of return, the cash flow and EBITDA projections, the estimated timelines and pre-requisites for sanctioning the Copper World project and the pursuit of a potential minority joint venture partner, expectations regarding the permitting requirements for the Copper World project and permitting related litigation (including expected timing for receipt of such applicable permits), the expected benefits of the Rockcliff Transaction and other Manitoba growth initiatives; statements regarding the company's production, cost and capital and exploration expenditure guidance, expectations regarding reductions in discretionary spending, capital expenditures and net debt, expectations regarding the impact of inflationary pressures on the company's cost of operations, financial condition and prospects, the company's future deleveraging strategies and the company's ability to deleverage and repay debt as needed, expectations regarding the company's cash balance and liquidity, the company's ability to increase the mining rate at Lalor, the anticipated benefits from completing the Stall recovery improvement program, the potential improvements to the tailings deposition process at the Anderson facility and any facility transitions related thereto, expectations regarding the ability to conduct exploration work on the Maria Reyna and Caballito properties and to advance related drill plans, the ability to continue mining higher-grade ore in the Pampacancha pit and the company's expectations resulting therefrom, expectations regarding the ability for the company to reduce greenhouse gas emissions, the company's evaluation of opportunities to reprocess tailings, expectations regarding the prospective nature of the Maria Reyna and Caballito properties, the anticipated impact of brownfield growth projects on the company's performance, anticipated expansion opportunities and extension of mine life in Snow Lake and the ability for Hudbay to find a new anchor deposit near the company's Snow Lake operations, anticipated drill programs and exploration activities and any results expected therefrom, anticipated mine plans, anticipated metals prices and the anticipated sensitivity of the company's financial performance to metals prices, events that may affect its operations and development projects, anticipated cash flows from operations and related liquidity requirements, the anticipated effect of external factors on revenue, such as commodity prices, estimation of mineral reserves and resources, mine life projections, reclamation costs, economic outlook, government regulation of mining operations, and business and acquisition strategies. Forward-looking information is not, and cannot be, a guarantee of future results or events. Forward-looking information is based on, among other things, opinions, assumptions, estimates and analyses that, while considered reasonable by the company at the date the forward-looking information is provided, inherently are subject to significant risks, uncertainties, contingencies and other factors that may cause actual results and events to be materially different from those expressed or implied by the forward-looking information.

 

The material factors or assumptions that Hudbay has identified and were applied in drawing conclusions or making forecasts or projections set out in the forward-looking information include, but are not limited to:

 
  • the consistency of the new technical report for the Copper Mountain mine with the mineral reserve and resource estimates and throughput assumptions disclosed in Copper Mountain's historical technical report dated February 25, 2019 (after accounting for mining depletion);
  •  
  • the ability to achieve production and cost guidance;
  •  
  • the ability to achieve discretionary spending reductions without impacting operations;
  •  
  • no significant interruptions to operations due to social or political unrest in the regions Hudbay operates, including the navigation of the complex political and social environment in Peru;
  •  
  • no interruptions to the company's plans for advancing the Copper World project, including with respect to timely receipt of applicable permits;
  •  
  • the ability for the company to successfully complete the integration and optimization of the Copper Mountain operations and develop and maintain good relations with key stakeholders;
  •  
  • the ability to ramp up exploration in respect of the Maria Reyna and Caballito properties and to advance related drill plans;
  •  
  • the success of mining, processing, exploration and development activities;
  •  
  • the scheduled maintenance and availability of the company's processing facilities;
  •  
  • the accuracy of geological, mining and metallurgical estimates;
  •  
  • anticipated metals prices and the costs of production;
  •  
  • the supply and demand for metals the company produces;
  •  
  • the supply and availability of all forms of energy and fuels at reasonable prices;
  •  
  • no significant unanticipated operational or technical difficulties;
  •  
  • the execution of the company's business and growth strategies, including the success of its strategic investments and initiatives;
  •  
  • the availability of additional financing, if needed;
  •  
  • the company's ability to deleverage and repay debt as needed;
  •  
  • the ability to complete project targets on time and on budget and other events that may affect the company's ability to develop its projects;
  •  
  • the timing and receipt of various regulatory and governmental approvals;
  •  
  • the availability of personnel for the company's exploration, development and operational projects and ongoing employee relations;
  •  
  • maintaining good relations with the employees at the company's operations, including in British Columbia;
  •  
  • maintaining good relations with the labour unions that represent certain of the company's employees in Manitoba and Peru;
  •  
  • maintaining good relations with the communities in which the company operates, including the neighbouring Indigenous communities and local governments;
  •  
  • no significant unanticipated challenges with stakeholders at the company's various projects;
  •  
  • no significant unanticipated events or changes relating to regulatory, environmental, health and safety matters;
  •  
  • no contests over title to the company's properties, including as a result of rights or claimed rights of Indigenous peoples or challenges to the validity of the company's unpatented mining claims;
  •  
  • the timing and possible outcome of pending litigation and no significant unanticipated litigation;
  •  
  • certain tax matters, including, but not limited to current tax laws and regulations, changes in taxation policies and the refund of certain value added taxes from the Canadian and Peruvian governments; and
  •  
  • no significant and continuing adverse changes in general economic conditions or conditions in the financial markets (including commodity prices and foreign exchange rates).
  •  

The risks, uncertainties, contingencies and other factors that may cause actual results to differ materially from those expressed or implied by the forward-looking information may include, but are not limited to, risks related to the anticipated mine plan and mineral reserve and resource estimates for the Copper Mountain mine and the possibility that they could result in an indicator of impairment, the failure to effectively complete the integration and optimization of the Copper Mountain operations, political and social risks in the regions Hudbay operates, including the navigation of the complex political and social environment in Peru, risks generally associated with the mining industry and the current geopolitical environment, including future commodity prices, currency and interest rate fluctuations, energy and consumable prices, supply chain constraints and general cost escalation in the current inflationary environment, uncertainties related to the development and operation of the company's projects, the risk of an indicator of impairment or impairment reversal relating to a material mineral property, risks related to the Copper World project, including in relation to permitting, litigation, project delivery and financing risks, risks related to the Lalor mine plan, including the ability to convert inferred mineral resource estimates to higher confidence categories, dependence on key personnel and employee and union relations, risks related to political or social instability, unrest or change, risks in respect of Indigenous and community relations, rights and title claims, operational risks and hazards, including the cost of maintaining and upgrading the company's tailings management facilities and any unanticipated environmental, industrial and geological events and developments and the inability to insure against all risks, failure of plant, equipment, processes, transportation and other infrastructure to operate as anticipated, compliance with government and environmental regulations, including permitting requirements and anti-bribery legislation, depletion of the company's reserves, volatile financial markets and interest rates that may affect the company's ability to obtain additional financing on acceptable terms, the failure to obtain required approvals or clearances from government authorities on a timely basis, uncertainties related to the geology, continuity, grade and estimates of mineral reserves and resources, and the potential for variations in grade and recovery rates, uncertain costs of reclamation activities, the company's ability to comply with its pension and other post-retirement obligations, the company's ability to abide by the covenants in its debt instruments and other material contracts, tax refunds, hedging transactions, as well as the risks discussed under the heading "Risk Factors" in the company's most recent Annual Information Form and under the heading "Financial Risk Management" in the company's most recent management's discussion and analysis.

 

Should one or more risk, uncertainty, contingency or other factor materialize or should any factor or assumption prove incorrect, actual results could vary materially from those expressed or implied in the forward-looking information. Accordingly, you should not place undue reliance on forward-looking information. Hudbay does not assume any obligation to update or revise any forward-looking information after the date of this news release or to explain any material difference between subsequent actual events and any forward-looking information, except as required by applicable law.

 

  Note to United States Investors  

 

This news release has been prepared in accordance with the requirements of the securities laws in effect in Canada, which may differ materially from the requirements of United States securities laws applicable to U.S. issuers.

 

  About Hudbay  

 

Hudbay (TSX, NYSE: HBM) is a copper-focused mining company with three long-life operations and a world-class pipeline of copper growth projects in tier-one mining-friendly jurisdictions of Canada, Peru and the United States.

 

Hudbay's operating portfolio includes the Constancia mine in Cusco (Peru), the Snow Lake operations in Manitoba (Canada) and the Copper Mountain mine in British Columbia (Canada). Copper is the primary metal produced by the company, which is complemented by meaningful gold production. Hudbay's growth pipeline includes the Copper World project in Arizona, the Mason project in Nevada (United States), the Llaguen project in La Libertad (Peru) and several expansion and exploration opportunities near its existing operations.

 

The value Hudbay creates and the impact it has is embodied in its purpose statement: "We care about our people, our communities and our planet. Hudbay provides the metals the world needs. We work sustainably, transform lives and create better futures for communities." Hudbay's mission is to create sustainable value and strong returns by leveraging its core strengths in community relations, focused exploration, mine development and efficient operations.

 

  For further information, please contact:  

 

Candace Brûlé
Vice President, Investor Relations
(416) 814-4387
investor.relations@hudbay.com  

 

 
1 Adjusted net earnings (loss) and adjusted net earnings (loss) per share; adjusted EBITDA; cash cost, sustaining cash cost and all-in sustaining cash cost per pound of copper produced, net of by-product credits; cash cost and sustaining cash cost per ounce of gold produced, net of by-product credits; combined unit costs, net debt and any ratios based on these measures are non-IFRS financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the "Non-IFRS Financial Performance Measures" section of this news release.

2 Sourced from Wood Mackenzie (Q2 2023 dataset).

3 Sourced from S&P Global, August 2023.

 

 

 

  Primary Logo 

 

News Provided by GlobeNewswire via QuoteMedia

HBM:CA,HBM
The Conversation (0)
Spools of copper wire.

Top 5 Junior Copper Stocks on the TSXV in 2025

The copper price climbed to a record high of US$5.64 per pound on the COMEX during the second quarter of 2025.

The price rise comes on the back of escalating trade tensions and economic chaos from the United States’ new tariff policy.

While copper was initially spared from tariffs at the start of the year, US President Donald Trump announced the US would be imposing a 50 percent tariff on all copper products entering the US. The announcement sparked speculative buying by US metals traders, who sought to position themselves ahead of the yet-to-be-announced tariff deadline.

How has this affected small-cap copper-focused companies on the TSX Venture Exchange? Read on to learn about the five best-performing junior copper stocks since the start of 2025.

Data for this article was gathered on July 17, 2025, using TradingView's stock screener, and copper companies with market caps of over C$10 million at that time were considered.

Keep reading...Show less
Pile of raw copper nuggets on a dark background.

Barrick Backs Hercules in Leviathan-Linked Copper Expansion

Hercules Metals (TSXV:BIG,OTCQB:BADEF) has entered into a transformative agreement with Barrick Mining (TSX:ABX,NYSE:B) to acquire a vast package of unpatented copper claims surrounding its Leviathan discovery in western Idaho.

Hercules will have the option to acquire a 100 percent interest in more than 74,000 acres of claims, collectively known as the Olympus belt, that flank both sides of the company’s existing Hercules property.

If exercised, the deal would expand Hercules’ total land position from 26,000 acres to over 100,000 acres, granting it control over a 73 kilometer stretch of highly prospective terrain.

The transaction is structured as an option agreement through Hercules’ US subsidiary, Anglo-Bomarc, with Barrick Gold Exploration, a wholly owned subsidiary of Barrick Mining.

Keep reading...Show less
Rows of fine copper bars with text that reads '5 Top Canadian Mining Stocks This Week.'

Top 5 Canadian Mining Stocks This Week: St. Augustine Gains 67 Percent

Welcome to the Investing News Network's weekly look at the best-performing Canadian mining stocks on the TSX, TSXV and CSE, starting with a round-up of Canadian and US news impacting the resource sector.

Statistics Canada released its monthly mineral production report for May 2025 on Monday (July 21). The data shows that the production of both copper and silver increased from April. Copper output rose to 36.3 million kilograms from 35.85 million in April, and silver increased to 26,502 kilograms from 25,412. Meanwhile, gold production decreased marginally to 16,518 kilograms from 16,640 the previous month.

However, shipments were up across the board. Copper shipments rose to 34.34 million kilograms compared to 30.01 million kilograms in April. Silver increased to 26,376 kilograms, up considerably from 22,106 kilograms a month earlier. Gold shipments saw a slighter gain, rising to 14,858 kilograms from 14,660 kilograms in April.

Keep reading...Show less
Silhouetted miners work in a dimly lit tunnel; "Weekly Editor's Picks" text overlay.

Editor's Picks: Miners Rescued, US Mine Waste Strategy, Ontario Expands CIMF

Here's a quick recap of some of the most impactful resource sector news items for the week.

The period saw three miners rescued after 60 hours underground at the Red Chris mine in BC, the US announce a mine waste recovery strategy and the Ontario government add C$7 million to boost critical minerals innovation.

Keep reading...Show less
Traffic light with green signal against a blue sky.

Teck Greenlights Highland Valley Expansion After Beating Q2 Profit Estimates

Teck Resources (TSX:TECK.A,TSX:TECK.B,NYSE:TECK) has secured board approval for a multi-billion-dollar life extension of its Highland Valley copper mine in British Columbia, setting the stage for a two-decade boost in copper output.

The Vancouver-based miner said Thursday (July 24) that construction on the Highland Valley Copper Mine Life Extension Project (HVC MLE) will begin in August, following receipt of environmental and permitting approvals in June.

Keep reading...Show less
Blackstone Minerals

Blackstone Minerals


Keep reading...Show less

Latest Press Releases

Related News

×