Hombre Muerto West  Phase 1 Construction Update - Nanofiltration Plant Delivered to Site

Hombre Muerto West Phase 1 Construction Update - Nanofiltration Plant Delivered to Site

Highlights:

  • Nanofiltration plant successfully delivered to HMW site

  • Galan and Authium teams have commenced on-site assembly. Assembly expected to be completed over the coming weeks

  • Evaporation (sylvinite) ponds for Phase 1 operations completed

  • Overall Phase 1 construction now approximately 85% complete

  • First processed brine expected early Q2 2026. First lithium chloride concentrate targeted in H1 2026

PERTH, AU / ACCESS Newswire / February 15, 2026 / Galan Lithium Limited (ASX:GLN,OTC:GLNLF) (Galan or the Company) is pleased to provide an update on construction progress at its 100% owned Hombre Muerto West (HMW) Project in Catamarca Province, Argentina.

Commenting from the HMW site Galan's Managing Director, Juan Pablo (JP) Vargas de la Vega, said:

"Our HMW site team is very excited at the arrival of the nanofiltration plant. Over the past 2 years we have accumulated a lithium brine inventory of around 9,500 tonnes (LCE) in the HMW ponds. In the short term we plan to complete the nanofiltration plant assembly and commissioning, which will allow for the first processed lithium brine to be produced from HMW.

The nanofiltration plant has been designed, tested, constructed and transported on an accelerated project schedule. I would like to recognise Authium's and Galan's teams who have come together in a spirit of partnership to make this possible."

Nanofiltration Plant Delivered and Assembly Underway

The Company confirms that the nanofiltration plant for Phase 1 operations has successfully arrived at the HMW project site.

Galan's technical team, together with specialists from Authium Limited (Authium), have commenced on-site assembly of the plant. Installation and assembly activities are expected to continue over the coming weeks, after which commissioning activities will begin.

The nanofiltration plant is a key component of Galan's processing flowsheet and will enable the efficient treatment of brine as part of the Phase 1 production process.

Sylvinite Ponds Completed

Construction of the sylvinite ponds required for the commencement of Phase 1 operations has now been completed. These ponds have been designed to accelerate the evaporation of processed brine, which leads to quicker production of lithium chloride concentrate and product sales for Galan.

Following Galan's successful capital raising in January 2026, construction work on the evaporation ponds will continue after the nanofiltration plant has been commissioned, to allow for the expanded production rate of 5,200 tpa LCE.

Key Upcoming Milestones

Overall construction of Phase 1 at Hombre Muerto West is now approximately 85% complete, reflecting continued strong progress across processing infrastructure, evaporation ponds and supporting site facilities. As we execute the last phase of construction activities at HMW important milestones will include:

  • the completion of nanofiltration plant assembly;

  • commissioning and testing of brine processing systems;

  • first processed brine (targeted in the first half of 2026); and

  • first lithium chloride concentrate production (targeted in the first half of 2026).

The Galan Board has authorised this release.

For further information contact:

COMPANY
Juan Pablo ("JP") Vargas de la Vega
Managing Director
jp@galanlithium.com.au
+ 61 8 9214 2150

MEDIA
Matt Worner
Vector Advisors
mworner@vectoradvisors.au
+61 429 522 924

SOURCE: Galan Lithium Limited



View the original press release on ACCESS Newswire

News Provided by ACCESS Newswire via QuoteMedia

GLN:AU
The Conversation (0)
Galan Lithium

Galan Lithium

Developing high-grade lithium brine projects in Argentina

Developing high-grade lithium brine projects in Argentina Keep Reading...
Successful Due Diligence Ends - $20M Placement To Proceed

Successful Due Diligence Ends - $20M Placement To Proceed

Galan Lithium (GLN:AU) has announced Successful Due Diligence Ends - $20m Placement To ProceedDownload the PDF here. Keep Reading...
Final At-The-Market Raise for 2025

Final At-The-Market Raise for 2025

Galan Lithium (GLN:AU) has announced Final At-The-Market Raise for 2025Download the PDF here. Keep Reading...
Quarterly Activities and Cash Flow Report

Quarterly Activities and Cash Flow Report

Galan Lithium (GLN:AU) has announced Quarterly Activities and Cash Flow ReportDownload the PDF here. Keep Reading...
Incentive Regime for HMW Project in Argentina

Incentive Regime for HMW Project in Argentina

Galan Lithium (GLN:AU) has announced Incentive Regime for HMW Project in ArgentinaDownload the PDF here. Keep Reading...
Trading Halt

Trading Halt

Galan Lithium (GLN:AU) has announced Trading HaltDownload the PDF here. Keep Reading...
SAGA Metals Advances Radar Project to Stage 2 RCL Optimization Targeting First High-Purity Titanium, Vanadium and Iron Products

SAGA Metals Advances Radar Project to Stage 2 RCL Optimization Targeting First High-Purity Titanium, Vanadium and Iron Products

-- Eight-week program with Temas Resources designed to lock in the RCL flowsheet, generate merchant-quality product samples and establish engineering criteria for a proposed mini-pilot-- Saga Metals Corp. (TSXV: SAGA,OTC:SAGMF) (OTCQX: SAGMF) (FSE: 20H) ("SAGA" or the "Company"), a North... Keep Reading...
Temas and SAGA Advance RCL to Stage 2 Targeting Titanium, Vanadium and Iron Products in Preparation for Pilot Studies

Temas and SAGA Advance RCL to Stage 2 Targeting Titanium, Vanadium and Iron Products in Preparation for Pilot Studies

VANCOUVER, BC / ACCESS Newswire / September 29, 2026 / Temas Resources Corp. ("Temas" or the "Company") (ASX:TIO)(CSE:TMAS)(OTCQB:TMASF)(FSE:26P0) is pleased to announce the advancement of its collaborative metallurgical program with Saga Metals Corp. ("SAGA") (TSXV:SAGA,OTC:SAGMF) to Stage 2 -... Keep Reading...
NextSource Materials Secures Binding Agreement for US$30 Million Strategic Investment from Japan's Hanwa and JOGMEC to Advance its UAE Battery Anode Facility

NextSource Materials Secures Binding Agreement for US$30 Million Strategic Investment from Japan's Hanwa and JOGMEC to Advance its UAE Battery Anode Facility

TORONTO, ON / ACCESS Newswire / September 28, 2026 / NextSource Materials Inc. (TSX:NEXT,OTC:NSRCF)(OTCQB:NSRCF) ("NextSource" or the "Company") is pleased to announce that it has executed a binding Share Subscription Agreement with Hanwa Co. Ltd., a major Japanese trading company, and the Japan... Keep Reading...
Spartan Metals Receives BLM Approval for Seven Additional Drill Sites at its Tungstonia Claims, Nevada

Spartan Metals Receives BLM Approval for Seven Additional Drill Sites at its Tungstonia Claims, Nevada

Spartan Metals Corp. (TSXV: W,OTC:SPRMF) (OTCQB: SPRMF) (FSE: J03) ("Spartan" or the "Company"), an exploration and development company focused on tungsten and critical minerals in the western United States, is pleased to announce that the United States Bureau of Land Management ("BLM") has... Keep Reading...
Nevada Sunrise Announces Results of Soil Sampling Program at the Fivemile Gold Project, Cortez Mining District, Nevada

Nevada Sunrise Announces Results of Soil Sampling Program at the Fivemile Gold Project, Cortez Mining District, Nevada

Nevada Sunrise Metals Corporation (TSXV: NEV,OTC:NVSGF) (OTC Pink: NVSGF) ("Nevada Sunrise" or the "Company") is pleased to announce the results of an Ionic LeachTM soil survey program (the "Survey") at the Fivemile Gold Project ("Fivemile", or the "Property"), located within the Battle... Keep Reading...
SAGA Metals Drills 485.4 m at 32.21% Fe2O3, 5.30% TiO2, 0.191% V2O5 Including 56.8 m at 49.56% Fe2O3, 8.17% TiO2, 0.339% V2O5 at Radar Critical Minerals Project in Labrador

SAGA Metals Drills 485.4 m at 32.21% Fe2O3, 5.30% TiO2, 0.191% V2O5 Including 56.8 m at 49.56% Fe2O3, 8.17% TiO2, 0.339% V2O5 at Radar Critical Minerals Project in Labrador

Saga Metals Corp. (TSXV: SAGA,OTC:SAGMF) (OTCQX: SAGMF) (FSE: 20H) ("SAGA" or the "Company"), a North American exploration company focused on critical mineral discoveries, is pleased to report additional assay results from drill holes R-0075, -0076, -0077, -0078, -0079, -0080, and -0081 drilled... Keep Reading...

Interactive Chart

Latest Press Releases

Related News