FPX Nickel Completes Confirmatory Large-Scale Mineral Processing Pilot Testwork with Funding Support from the Government of Canada

FPX Nickel Completes Confirmatory Large-Scale Mineral Processing Pilot Testwork with Funding Support from the Government of Canada

FPX Nickel Corp. (TSXV: FPX) (OTCQB: FPOCF) (" FPX " or the " Company ") is pleased to announce that it has successfully completed a large-scale mineral processing pilot testing campaign for the Baptiste Nickel Project (" Baptiste " or the " Project "), the first significant component of the ongoing feasibility study (" FS ") metallurgical testwork campaign.  Results from this testwork confirm the 2023 preliminary feasibility study (" PFS ") basis, thereby validating FPX's processing strategy, flowsheet, and key metallurgical criteria, including estimated recoveries.  The pilot testing campaign was funded in part by a $725,000 grant from Natural Resources Canada (" NRCan ") under the Government of Canada's Critical Minerals Research, Development and Demonstration (" CMRDD ") program, which is advancing the commercial readiness of processing technologies that will support the development Canada's EV battery material supply chain.

Highlights
  • Pilot-scale mineral processing testwork is now complete, with metallurgical performance matching the 2023 PFS basis, confirming expected recoveries and other key performance criteria
  • Testwork identified multiple opportunities to further optimize the mineral processing flowsheet through further process simplification
  • Testwork produced sufficient high-grade concentrate (60% nickel) for pilot-scale testing of the downstream hydrometallurgy refinery for the production of battery-grade nickel sulphate
  • Preparations for the downstream hydrometallurgical refining pilot plant are underway, with results expected to be announced in the third quarter of 2024

"These first results from our FS metallurgical testwork program further validate the processing advantages of awaruite which were demonstrated in the Baptiste PFS," commented Andrew Osterloh , FPX Nickel's Senior Vice President, Projects & Operations.  "Conducted with support from NRCan, this large-scale pilot program has demonstrated that the processing strategy, flowsheet, and metallurgical basis from the PFS are robust, and has identified further optimization opportunities to lower capital and operating costs.  This is another positive step as we continue to advance Baptiste as a potential producer of disruptive quantities of low-carbon, low-cost, Canadian nickel."

Background

The Baptiste processing strategy leverages awaruite's distinct properties in a simple, yet robust flowsheet.  The front end of the flowsheet utilizes magnetic separation to create a "magnetics rich" concentrate of awaruite and magnetite – a process made effective due to awaruite's intense ferromagnetism and high density.  The back end of the flowsheet then utilizes conventional froth flotation to separate awaruite from magnetite – a process made effective due to awaruite's active surface properties and magnetite's general lack of floatability.  Finally, based on awaruite's very high nickel content, a very high-grade nickel concentrate (60% nickel) can be produced.

Downstream of the mineral processing plant, awaruite's properties continue to provide distinct advantages, including unparalleled downstream market flexibility.  Unlike conventional nickel mineral concentrates which have a high sulphur content, Baptiste's awaruite concentrate is nearly sulphur-free and low in deleterious elements, meaning it can bypass intermediate smelting and be used directly in stainless steel fabrication.  Alternatively, the Baptiste awaruite concentrate is also an ideal feedstock for the production of high-purity, battery-grade nickel sulphate for the electric vehicle (" EV ") supply chain.  The Company's PFS metallurgical testing programs have well demonstrated this flexibility, and the FS metallurgical testing program is expected to confirm these previous findings at an even larger scale.

Mineral Processing Pilot Plant

The primary objectives of the FS mineral processing pilot plant were (1) to further demonstrate the Baptiste concentrator flowsheet at a larger scale; and (2) to produce sufficient awaruite concentrate to conduct pilot-scale, continuous testing of the downstream hydrometallurgy refinery for the production of battery-grade nickel sulphate.

The testwork reported herein represents the third pilot-scale mineral processing campaign the Company has completed for Baptiste.  Key parameters from each pilot plant are summarized in Table 1, highlighting that the FS pilot plant was conducted at a significantly greater scale and run time than previously completed campaigns, permitting a longer duration of steady-state operation.

Table 1 – Summary of Baptiste Pilot-Scale Mineral Processing Testing Campaigns

Pilot Campaign

2021

2022

2023/24

Metallurgical Testwork Program

PFS

PFS

FS

Ore Feed Rate

160 kg/h

210 kg/h

320 kg/h

Feed Material

Life of mine composite

Bulk sample from early mine plan years

Bulk sample from early mine plan years

Run Time

0.9 days

3.3 days

9.9 days

Unit Operations Tested

Magnetic Separation

Magnetic Separation and Flotation

Magnetic and Gravity Separation and Flotation

Objective

Flowsheet development and generation of magnetic concentrate for bench-scale flotation testing

Flowsheet validation and generation of flotation concentrate for bench-scale refinery testing

Further flowsheet validation and generation of flotation concentrate for pilot-scale refinery testing

The FS pilot plant followed the flowsheet defined in the 2023 PFS, but also tested multiple optimization opportunities.  The tested flowsheet is presented in Figure 1, with blue unit operations representing continuously-tested PFS flowsheet elements and green unit operations representing potential flowsheet optimizations which were also tested.

Figure 1 – Baptiste Mineral Processing Pilot Flowsheet (CNW Group/FPX Nickel Corp.)

The Company re-engaged Corem ( Quebec, Canada ) to conduct the FS pilot plant, building on their experience with previous piloting and numerous bench-scale programs for Baptiste.  A total of 76 tonnes of material were processed in the pilot plant, resulting in approximately 9.9 days of continuous run-time in the primary grinding and magnetic separation circuits.

When operating under normal conditions, the FS pilot plant delivered metallurgical performance that closely matched the metallurgical performance assumed in the PFS.  This includes stage-by-stage recoveries, as well as the ability to produce the high-grade nickel concentrate (60% nickel) envisioned in the PFS.  While these were expected results, given the quality and scale of the PFS metallurgical testwork program, the success of the FS pilot plant nevertheless provides further validation for the proposed Baptiste processing strategy, flowsheet, and metallurgical basis. Examples of the awaruite concentrates produced in the pilot plant are presented in Figures 2 and 3.

Figure 2 – First Batch of Flotation Concentrate from FS Pilot Plant (CNW Group/FPX Nickel Corp.)

Figure 3 – Micrograph of Upgraded Gravity Concentrate (CNW Group/FPX Nickel Corp.)

Optimization Opportunities

The extended duration of the FS pilot plant also permitted trial of two flowsheet optimizations, firstly the production and upgrading of a gravity concentrate, and secondly the elimination of the second regrind and recleaning magnetic separation stage. As discussed below, both of these optimization opportunities have the potential to contribute to flowsheet enhancements that contribute to lower associated processing costs.

Early Recovery of Coarse, Liberated Awaruite to Final Concentrate

The second PFS pilot plant noted considerable circulating load of awaruite in the first regrind circuit due to the high specific gravity and malleability of awaruite and the use of a hydrocyclone to close the grinding circuit.  Continuous testing during the FS pilot plant demonstrated the technical viability of using a centrifugal concentrator to recover coarse, liberated awaruite from grinding circuit recirculating loads.  This approach is commonly applied in the gold industry to recover coarse gold particles.  Gravity concentrates grading 20-40% nickel were produced, and then successfully upgraded to the final concentrate grade of 60% nickel using magnetic separation and flotation steps.

While the PFS envisioned advancing the coarse, liberated awaruite to the cleaner magnetic separation feed, the early recovery of this material to a final product reduces the risk of downstream overgrinding and its potential recovery impact.  As such, FS pilot testwork clearly demonstrates that awaruite's high density can be effectively managed in an industrial grinding circuit.

Elimination of Secondary Regrinding and Recleaning Magnetic Separation

The second optimization trialed the elimination of the second regrind and recleaner magnetic separation circuits.  To test this, cleaner magnetic separation concentrate was directly fed to froth flotation.  Testwork showed overall recoveries comparable to the PFS flowsheet.  For this approach, rougher concentrate would then be reground prior to cleaner froth flotation, but this would require a significantly smaller regrind circuit, resulting in process simplification, capital cost savings, and operating costs savings. This opportunity will be further investigated and validated in upcoming stages of the FS metallurgical testwork program, with the potential for additional processing cost benefits for the Project.

Hydrometallurgical Refinery Pilot Plant

The awaruite concentrate generated during the mineral processing plant will now be used in the downstream hydrometallurgical refining pilot plant.  FPX has re-engaged Sherritt Technologies Ltd. to conduct this testwork, building on their successful completion of the previous batch-scale testing program in 2023.  As noted in the Company's news release dated May 17, 2023 , the 2023 program successfully demonstrated FPX's proposed refinery flowsheet can produce battery grade nickel sulphate at the batch-scale, and FS testwork program will now aim to demonstrate similar findings at the pilot-scale.  Preparations for this pilot plant are underway and results are expected to be announced in the third quarter of 2024.

Qualified Person

The metallurgical information in this news release has been prepared in accordance with Canadian regulatory requirements set out in National Instrument 43-101: Standards of Disclosures for Minerals Projects of the Canadian Securities Administrators (" NI 43-101 ").  Testwork was supervised, reviewed, and verified by Kyle D. Marte , P.Eng., FPX Nickel's Principal Metallurgist and a "Qualified Person" as defined by NI 43-101.

About the Decar Nickel District

The Company's Baptiste Nickel Project represents a large-scale greenfield discovery of nickel mineralization in the form of a sulphur-free, nickel-iron mineral called awaruite (Ni 3 Fe) hosted in an ultramafic/ophiolite complex.  The Baptiste mineral claims cover an area of 245 km 2 west of Middle River and north of Trembleur Lake, in central British Columbia.  In addition to the Baptiste Deposit itself, awaruite mineralization has been confirmed through drilling at several target areas within the same claims package, most notably at the Van Target which is located 6 km to the north of the Baptiste Deposit.  Since 2010, approximately US $30 million has been spent on the exploration and development of Baptiste.

The Baptiste Deposit is located within the Baptiste Creek watershed, on the traditional and unceded territories of the Tl'azt'en Nation and Binche Whut'en, and within several Tl'azt'enne and Binche Whut'enne keyohs. FPX has conducted mineral exploration activities to date subject to the conditions of agreements with First Nations and keyoh holders.

About FPX Nickel Corp.

FPX Nickel Corp.  is focused on the exploration and development of the Decar Nickel District, located in central British Columbia , and other occurrences of the same unique style of naturally occurring nickel-iron alloy mineralization known as awaruite.  For more information, please view the Company's website at https://fpxnickel.com/ .

On behalf of FPX Nickel Corp.

"Martin Turenne"
Martin Turenne , President, CEO and Director

Forward-Looking Statements

Certain of the statements made and information contained herein is considered "forward-looking information" within the meaning of applicable Canadian securities laws. These statements address future events and conditions and so involve inherent risks and uncertainties, as disclosed in the Company's periodic filings with Canadian securities regulators. Actual results could differ from those currently projected. The Company does not assume the obligation to update any forward-looking statement.

Neither the TSX Venture Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this release.

SOURCE FPX Nickel Corp.

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/April2024/30/c4334.html

News Provided by Canada Newswire via QuoteMedia

FPX:CA
FPX Nickel

FPX Nickel Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

The Conversation (0)
OTXQB: FPOCF

FPX Nickel


Keep reading...Show less
FPX Nickel Reports Value Engineering Studies Outlining Improvements in Mineral Processing Facilities and Validating PFS Project Schedule

FPX Nickel Reports Value Engineering Studies Outlining Improvements in Mineral Processing Facilities and Validating PFS Project Schedule

 FPX Nickel Corp. (TSXV: FPX) (OTCQB: FPOCF) (" FPX " or the " Company ") is pleased to provide an update on value engineering (" Value Engineering ") studies focused on the mineral processing and infrastructure facilities for the Baptiste Nickel Project (" Baptiste " or " the Project ") in central British Columbia .  The mineral processing and infrastructure Value Engineering studies have achieved significant value creation through facility optimization, flowsheet refinement, enhanced operability, and improvements to the project build strategy and execution basis.

FPX Nickel logo (CNW Group/FPX Nickel Corp.)

Highlights

  • Primary crushing: Changing from a gyratory-type primary crusher to mineral sizers has reduced earthwork and structural quantities, improved Phase 1 operability, and eliminated the need for a second primary crushing circuit in Phase 2
  • Concentrator expansion: A new integrated approach to the Phase 2 expansion has reduced overall quantities, improved Phase 2 operability, and reduced the footprint of process and infrastructure facilities
  • Project phasing: The phased approach and throughput rates in the preliminary feasibility study (" PFS ") have been validated, while acceleration of the Phase 2 expansion improves Baptiste's metal production profile
  • Execution schedule has been confirmed, further validating the PFS's estimated three-year construction duration

"Results from our mineral process and infrastructure Value Engineering studies have added significant value to the Baptiste Nickel Project," commented Andrew Osterloh , the Company's Senior Vice President, Projects & Operations.  "By reducing quantities, improving operating efficiency, and advancing the project execution plan, we have enhanced Baptiste's potential as a long life, large-scale, low-cost, and low-carbon producer of made-in- Canada nickel units. We look forward to advancing additional engineering studies on the mining and refinery aspects of the Project in advance of commencing a feasibility study."

Background

The Baptiste 2023 preliminary feasibility study (" PFS ") demonstrates the potential to develop a high-margin and low-carbon nickel mine producing an average of 59,100 tonnes per year of nickel over a 29-year mine life (see the Company's September 6, 2023 news release).  Due to awaruite's properties, Baptiste has the unparalleled flexibility to produce either a high-grade concentrate (60% nickel) for direct feed into the stainless steel industry (the " Base Case ") or for further refining into battery-grade nickel, cobalt, and copper products for the electric vehicle battery supply chain (the " Refinery Option ").

While the PFS presents robust economics, including a Base Case after-tax NPV 8% of US$2.01 Billion and after-tax IRR of 18.6% at US$8.75 /lb Ni, FPX strives to add further value to Baptiste, focusing on a holistic blend of economics, constructability, operability, risk and ESG considerations.

The key Value Engineering studies pursued by FPX in 2024 are:

  • Mineral processing and infrastructure (described herein)
  • Mine planning and engineering (to be completed in the third quarter of 2024)
  • Refinery planning (to be completed in the third quarter of 2024)

Mineral Processing & Infrastructure Value Engineering Studies

FPX engaged Fluor Canada Ltd. (" Fluor ") and Wood Canada Ltd. (" Wood ") to perform detailed reviews of the 2023 PFS and to conduct mineral process and infrastructure Value Engineering studies.  The consultants identified three primary opportunities to add further value, which are described in greater detail hereunder:

  • Primary crushing: application of mineral sizers
  • Phase 2 concentrator expansion
  • Project phasing

As described below, each of the mineral process and infrastructure Value Engineering studies validated several key tenets from the PFS and added significant project value through reduced quantities, improved operability, reduced process operating costs, and reduced process and infrastructure footprint.

Primary Crushing

The PFS considered a gyratory-type primary crusher.  In re-evaluating the Project's geotechnical and communication datasets, the Company has identified an opportunity to use mineral sizers for primary crushing.  Taking advantage of the modest compressive strength and fractured nature of the Baptiste ore, mineral sizers have added significant value through reduced earthwork and structural quantities, increased operating availability, and the complete elimination of the second primary crushing line for the planned mine expansion from an initial Phase 1 processing throughput of 108,000 tonnes per day (" tpd ") to 162,000 tpd in Year 10 (" Phase 2 ").

Phase 2 Concentrator Expansion

The PFS considered the construction of a standalone processing facility for the Phase 2 expansion from 108,000 tpd to 162,000 tpd.  A new approach to expansion is based on an integrated concentrator approach which entails an expansion of the Phase 1 processing facility rather than the construction of a new standalone facility for Phase 2. This integrated approach results in a reduced process and infrastructure footprint, improved Phase 2 operability, and reduced Phase 2 work force requirements.

Project Phasing

A Value Engineering study re-evaluated the phased approach to processing throughput and compared it with a series of single-build scenarios ranging from 80,000 to 163,000 tpd.  Following this evaluation, the PFS's phased approach has been validated; however, the Phase 2 expansion has been accelerated to Year 6 from Year 10.  This acceleration in metal production is expected to generate improved economics versus the PFS, with the Phase 2 expansion funded from operating free cash flow following the 3.7 year after-tax payback demonstrated in the PFS.

Project Execution

Both Fluor and Wood were assigned further scope to review the PFS's execution basis, including the permanent facility layout, construction sequence, contracting approach, and overall execution schedule. Note that Fluor and Wood jointly executed the detailed engineering and construction management of the nearby Mt. Milligan Mine, which was commissioned in 2013 and is located 80 km east of Baptiste. Mt. Milligan is of comparable size and complexity to Baptiste, which uniquely positions Fluor and Wood to provide relevant context to the Baptiste project execution plan.

Through this additional execution planning effort, numerous scheduling improvements to the PFS were identified, thereby improving the constructability, operability, and maintainability of Baptiste.  In addition, increased focus on allowances for temporary construction facilities has improved execution scope assurance ahead of the environmental assessment  and permitting processes.  Fundamentally, these robust execution planning efforts further de-risk the Baptiste execution schedule, including the PFS assumption of a three-year construction period.

Andrew Osterloh , P.Eng., FPX Nickel's Qualified Person under NI 43-101, has reviewed and approved the technical content of this news release.

About the Decar Nickel District

The Company's Baptiste Nickel Project represents a large-scale greenfield discovery of nickel mineralization in the form of a sulphur-free, nickel-iron mineral called awaruite (Ni 3 Fe) hosted in an ultramafic/ophiolite complex.  The Baptiste mineral claims cover an area of 408 km 2 west of Middle River and north of Trembleur Lake, in central British Columbia.  In addition to the Baptiste Deposit itself, awaruite mineralization has been confirmed through drilling at several target areas within the same claims package, most notably at the Van Target which is located 6 km to the north of the Baptiste Deposit.  Since 2010, approximately US $30 million has been spent on the exploration and development of Baptiste.

The Baptiste Deposit is located within the Baptiste Creek watershed, on the traditional territories of the Tl'azt'en Nation and the Binche Whut'en, and within several Tl'azt'enne and Binche Whut'enne keyohs. FPX has conducted mineral exploration activities to date subject to the conditions of agreements with First Nations and keyoh holders.

About FPX Nickel Corp.

FPX Nickel Corp.  is focused on the exploration and development of the Decar Nickel District, located in central British Columbia , and other occurrences of the same distinctive style of awaruite nickel-iron mineralization.  For more information, please view the Company's website at https://fpxnickel.com/ or contact Martin Turenne , President and CEO, at (604) 681-8600 or ceo@fpxnickel.com .

On behalf of FPX Nickel Corp.

"Martin Turenne"
Martin Turenne , President, CEO and Director

Forward-Looking Statements

Certain of the statements made and information contained herein is considered "forward-looking information" within the meaning of applicable Canadian securities laws. These statements address future events and conditions and so involve inherent risks and uncertainties, as disclosed in the Company's periodic filings with Canadian securities regulators. Actual results could differ from those currently projected. The Company does not assume the obligation to update any forward-looking statement.

Neither the TSX Venture Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this release.

SOURCE FPX Nickel Corp.

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/July2024/10/c9969.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
FPX Nickel Advances Baptiste Project Engagement Initiatives with Opening of Community Office in Fort St. James

FPX Nickel Advances Baptiste Project Engagement Initiatives with Opening of Community Office in Fort St. James

 FPX Nickel Corp. (TSXV: FPX) (OTCQB: FPOCF) (" FPX Nickel " or the " Company ") is pleased to announce the opening of a Fort St. James office ( "Community Office" ) and hiring of a locally-based Community Manager to support ongoing and increased engagement with First Nation governments and with local businesses and communities for the Baptiste Nickel Project (" Baptiste " or " the Project "). These measures are being implemented to support the Company's commitments to collaboration for responsible project development, in particular with the First Nations whose territories encompass the proposed mine project area, including the Tl'azt'en Nation, the Binche Whut'en, the Yekooche First Nation, and the Takla Nation.

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
FPX Nickel Re-initiates Exploration at the Mich Property in the Yukon

FPX Nickel Re-initiates Exploration at the Mich Property in the Yukon

FPX Nickel Corp. (TSX-V: FPX) (OTCQB: FPOCF) (" FPX " or the " Company ") is pleased to announce the re-initiation of exploration activities at the Company's Mich property (" Mich "), located 50 km southeast of Whitehorse in the Yukon.  The Company has recently expanded its claims at Mich by over 350% and will conduct a wide-ranging surface sampling program over the summer of 2024 with the goal of advancing Mich to drill-ready status.

Highlights

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
FPX Nickel Announces Results of 2024 Annual General and Special Meeting

FPX Nickel Announces Results of 2024 Annual General and Special Meeting

FPX Nickel Corp. (TSXV: FPX) (OTCQB: FPOCF) (" FPX " or the " Company ") is pleased to announce the results of its 2024 Annual General and Special Meeting held on May 29 2024.

FPX Nickel logo (CNW Group/FPX Nickel Corp.)

At the meeting, the shareholders voted to set the number of Board members at seven and elected Kim Baird , Peter M.D. Bradshaw , Anne Currie , James S. Gilbert , Peter J. Marshall , Robert B. Pease and Martin E. Turenne as directors of the Company to hold office for the ensuing year.  The shareholders also voted in favour of the appointment of DeVisser Gray LLP as the auditor of the Company for the ensuing year and approved the Company's Share Compensation Plan.

The Company notes that William ("Bill") H. Myckatyn , who had served with distinction on the Board since 1999, did not stand for re-election at the meeting.

"Bill's extensive knowledge as a mining engineer has been very important in guiding the Company's growth, from the initial focus on the novel style of awaruite nickel mineralization at Baptiste to the completion of a preliminary feasibility study and all the milestones achieved along the way," said Mr. Bradshaw, Chairman of the Board.  "Bill has always been very generous with his time and contributing the wisdom gained from his very successful career, from being the President and CEO of Princeton Mining and Gibraltar Mines, as the founder and CEO of Quadra Mining, and from over 17 years with Placer Dome.  On behalf of the Company's Board, our shareholders and myself, I would like to extend my very great appreciation to Bill for his many years of dedicated service to FPX Nickel."

About FPX Nickel Corp.

FPX Nickel Corp.  is focused on the exploration and development of the Decar Nickel District, located in central British Columbia , and other occurrences of the same unique style of naturally occurring nickel-iron alloy mineralization known as awaruite.  For more information, please view the Company's website at https://fpxnickel.com/ or contact Martin Turenne , President and CEO, at (604) 681-8600 or ceo@fpxnickel.com .

On behalf of FPX Nickel Corp.

"Martin Turenne"
Martin Turenne , President, CEO and Director

Forward-Looking Statements

Certain of the statements made and information contained herein is considered "forward-looking information" within the meaning of applicable Canadian securities laws. These statements address future events and conditions and so involve inherent risks and uncertainties, as disclosed in the Company's periodic filings with Canadian securities regulators. Actual results could differ from those currently projected. The Company does not assume the obligation to update any forward-looking statement.

Neither the TSX Venture Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this release.

SOURCE FPX Nickel Corp.

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/May2024/30/c5917.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
FPX Nickel Announces New Leadership for Carbon Capture and Storage Subsidiary

FPX Nickel Announces New Leadership for Carbon Capture and Storage Subsidiary

 FPX Nickel Corp. (TSXV: FPX) (OTCQB: FPOCF) (" FPX Nickel " or the " Company ") is pleased to announce the appointment of Scott Larson as the new President and Chief Executive Officer of CO2 Lock Corp. (" CO2 Lock "), the Company's majority-owned subsidiary specializing in carbon capture and storage (" CCS ") via permanent mineralization.  Mr. Larson brings to CO2 Lock over 25 years of combined corporate finance, technology development and entrepreneurial experience.

FPX Nickel logo (CNW Group/FPX Nickel Corp.)

"We are very pleased to welcome Scott to lead CO2 Lock through the next phase of growth in pursuit of large-scale, low-cost and permanent carbon capture and storage," commented FPX Nickel's Chairman, Peter Bradshaw .  "CO2 Lock is at a pivotal stage of development.  In late-2023, the company completed a comprehensive field program at its SAM project site in central British Columbia , including the first-ever successful injection of CO2 into a brucite-rich ultramafic deposit.  Scott will be leading CO2 Lock's execution of a large-scale pilot program in early 2025, which will result in the first commercial carbon mineralization project in British Columbia ."

Before joining CO2 Lock, Mr. Larson was CEO and co-founder of SpaceAlpha, an earth observation company building synthetic aperture radar technology and Helios Wire, a satellite company building out a space-enabled IoT/M2M network which was successfully sold.  He was also previously CEO and co-founder of UrtheCast, scaling the Company from inception, taking it public on the Toronto Stock Exchange, raising $200 million , and growing the company to 250 employees with seven offices around the world.

"The opportunity to be part of a technology and process that will allow CO2 Lock to sequester carbon permanently, on a global scale, is very compelling," said Scott Larson .  "I'm looking forward to building value, scaling up, and developing partnerships throughout the carbon capture and cleantech sector."

Mr. Larson has assumed the role of CO2 Lock's CEO from Mr. Cooper Quinn .  On behalf of the Board of Directors, FPX Nickel and CO2 Lock extend our thanks to Mr. Quinn for his commitment and contributions to the company.

Background

On March 30, 2022 , FPX announced the formation of CO2 Lock as a self-funding subsidiary to pursue geoscience-related CCS opportunities. FPX retains 100% of the carbon credits associated with CCS on its own properties, and can use any intellectual property developed by CO2 Lock for the benefit of FPX's own properties.

About FPX Nickel Corp.

FPX Nickel Corp.  is focused on the exploration and development of the Decar Nickel District, located in central British Columbia , and other occurrences of the same unique style of naturally occurring nickel-iron alloy mineralization known as awaruite.  For more information, please view the Company's website at https://fpxnickel.com/.

On behalf of FPX Nickel Corp.

"Martin Turenne"
Martin Turenne , President, CEO and Director

Forward-Looking Statements

Certain of the statements made and information contained herein is considered "forward-looking information" within the meaning of applicable Canadian securities laws. These statements address future events and conditions and so involve inherent risks and uncertainties, as disclosed in the Company's periodic filings with Canadian securities regulators. Actual results could differ from those currently projected. The Company does not assume the obligation to update any forward-looking statement.

Neither the TSX Venture Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this release.

SOURCE FPX Nickel Corp.

Cision View original content to download multimedia: http://www.newswire.ca/en/releases/archive/May2024/29/c6618.html

News Provided by Canada Newswire via QuoteMedia

Keep reading...Show less
Canadian Critical Minerals Closes $222,000 Financing

Canadian Critical Minerals Closes $222,000 Financing

Canadian Critical Minerals Inc. (TSXV: CCMI) (OTCQB: RIINF) ("CCMI" or the "Company") has closed a financing for proceeds of $222,000, comprised of 3,700,000 Flow-Through Units with an issue price of $0.06 per unit. Each Flow-Through Unit consists of one common share and one half of one common share purchase warrant that is exercisable into a common share at an exercise price of $0.09 per share for a period of two years.

All securities issued are subject to a statutory hold period that expires four months and one day from issuance.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Heritage Mining Zone 3 Successful SGH Soil Survey

Heritage Mining Zone 3 Successful SGH Soil Survey

(TheNewswire)

Heritage Mining Ltd.

NOT INTENDED FOR DISTRIBUTION TO UNITED STATES NEWS WIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES

News Provided by TheNewsWire via QuoteMedia

Keep reading...Show less
The Falco Horne 5 Project in Front of the BAPE

The Falco Horne 5 Project in Front of the BAPE

Falco Resources Ltd. (TSX-V: FPC) ( "Falco" or the " Corporation" ) is pleased to announce that the Minister of the Environment, the Fight against Climate Change, Wildlife and Parks, Benoit Charette, has given the mandate to the Office of Public Hearings on the Environment ( "BAPE" ) to hold an inquiry and a public hearing concerning Falco's Horne 5 project (the "Falco Horne 5 Project" or the " Project "). This mandate will begin on August 26 and will have a maximum duration of four months.

Falco is pleased with this decision which marks an important milestone for the Falco Horne 5 Project. Falco's team will be supported by expert resources, including the firms A2GC, Sanexen, SoftdB, BGC and WSP in order to respond to questions and requests from the population and the BAPE during the hearings. The inquiry commission will be composed of Joseph Zayed, who will act as President, as well as Martin Lessard and Geneviève Meloche, who will act as commissioners. The curricula vitae of the commissioners can be consulted on the BAPE website.

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
Osisko Metals Provides Update at Gaspé Copper

Osisko Metals Provides Update at Gaspé Copper

Osisko Metals Incorporated (the " Company " or " Osisko Metals ") ( TSX-V:OM ; OTCQX:OMZNF ; FRANKFURT:0B51 ) is pleased to provide an update on the activities being carried out this summer as part of the development of the Gaspé Copper project.

Mr. Robert Wares, President and CEO of Osisko Metals, commented: "Since the beginning of the summer, significant work has been completed marking key advances in our efforts to eventually re-open the mine. Our 2024 drilling program is progressing well, as is surface water characterization of the mine site and surrounding area, both of which will continue into the fall. Detailed sampling of the pit waters as well as experimental fishing downstream from the mine site are also planned to better understand the health of fish populations and the potential impacts of pit dewatering. Publication of the preliminary economic assessment( PEA) is still scheduled for early 2025. In parallel with our technical work, we are pleased to support local community activities by sponsoring several events."

News Provided by GlobeNewswire via QuoteMedia

Keep reading...Show less
World Copper Ltd. and CEO Provide Corporate Update

World Copper Ltd. and CEO Provide Corporate Update

World Copper Ltd. (TSXV: WCU) (OTCQB: WCUFF) (FSE:7LY0) ("World Copper" or the "Company") is pleased to provide the following update on corporate activities, as well as additional insights into the Company's operations over the past six months from Gordon Neal, President, Director and CEO of World Copper.

World Copper appointed Gord Neal as its CEO a little over six months ago, and it would like to properly introduce him and his work history to the Company's shareholders. Gord Neal originally began in the resource sector in 2003 as the Vice President of Corporate Development for MAG Silver (NYSE: MAG) (TSX: MAG). He left MAG after ten years to join Silvercorp Metals (NYSE: SVM) (TSX: SVM) as Vice President of Corporate Development. Gord made the decision to join Silvercorp to expand his knowledge of silver mining production, and in 2017, he was appointed as President of New Pacific Metals (NYSE: NEWP) (TSX: NUAG). Gord worked in Bolivia with New Pacific Metals for seven years and brought its Silver Sand project from discovery to a Preliminary Economic Assessment. Gord has taken pride in his work and his association with the many companies he has had the opportunity to serve, and he has been instrumental in creating significant corporate and shareholder value. All three of the abovementioned companies reached billion-dollar market cap valuations under his watch, and his plan is to produce similar results for World Copper.

News Provided by Newsfile via QuoteMedia

Keep reading...Show less
Aston Bay and American West Metals Confirm Expansion of High-Grade Copper Zones at the Storm Project, Nunavut, Canada

Aston Bay and American West Metals Confirm Expansion of High-Grade Copper Zones at the Storm Project, Nunavut, Canada

Intervals up to 121.2m of continuous visual copper mineralization intersected

HIGHLIGHTS

News Provided by ACCESSWIRE via QuoteMedia

Keep reading...Show less
FPX Nickel

FPX Nickel Investor Kit

  • Corporate info
  • Insights
  • Growth strategies
  • Upcoming projects

GET YOUR FREE INVESTOR KIT

Latest Press Releases

Related News

×